In: Accounting
ZABZUGU TATALE produces a specialized product KANZO. The product passes through three (3) cost centers namely: machining, assembly and painting shop. Data relating to the cost centers is as below:
Machining |
Assembly |
Painting shop |
Engineering shop |
Stores |
|
Number of employees |
81 |
51 |
39 |
30 |
24 |
Engineering shop-service |
18,000 |
12,000 |
10,000 |
- |
- |
Stores (orders) |
180 |
135 |
90 |
45 |
- |
At a management meeting dated 24th September 20X0, the following overheads were budgeted for the production and service cost centers exclusively for the ensuing period:
Cost centers |
GHS 000 |
Machining |
180,000 |
Assembly |
160,000 |
Painting shop |
130,000 |
Engineering shop |
84,000 |
Stores |
52,000 |
Canteen |
75,000 |
Equally, the following budgeted data relates to the production cost centers:
Machining |
Assembly |
Painting shop |
|
Machine hours |
9,200 |
8,100 |
6,600 |
Labor hours |
8,300 |
11,250 |
9,000 |
Labor cost (GHS) |
40,000 |
88,000 |
45,000 |
Actual results for the production cost centers were:
Machining |
Assembly |
Painting shop |
|
Machine hours |
10,000 |
8,200 |
6,600 |
Labor hours |
4,500 |
7,800 |
6,900 |
Labor cost (GHS) |
25,000 |
42,000 |
35,000 |
Actual overheads (GHS) |
290,000 |
167,000 |
155,000 |
Required:
Machining - Machine hours.
Assembly - Labor hours.
Paint shop - Labor costs.
answer a:
Canteen, stores and engineering shop are service cost senters, while others are procustion cost centers.
service center cost are allocated to production cost center in the basis of repeated distribution method, as you can see that canteen cost is first allocated to other service cost centers stores and engineering shop. then the cost of stores is allocated to engineering shop after that cost of engineering shop is allocated among production deparments.
Answer b
statement showing the under/over absorption
meaning of under absoption: when the actual overheads incurred by a cost center are more than budgeted overhead.
meaning of over absoption: when actual overheads incurred by the cost center are less than the budgeted overheads allocated to the center.
calculation of budgeted overheads:
we are given below mentioned table in question
further above in part a we had calculated OH absorption rate, now we would multiple machine hours to absorption rate of machining departmet 10000*11.55, 8200*11.55, 6600*11.55
similarly we would do it for assembly (multiply by labor hours), and for painting shop by labor cost.
____________________________________
please provide feed back in the comment section to refine the answer,
i also politely request those who gave thumb-down rating to please share the reason for the same, so i can improve in future.
thanks.