In: Economics
An industrial grade Farm wants to permanently expand its production and increase profits by an estimated 15,000 $/yr for the next 20 yrs. The expansion would need additional irrigation over the expected 20 years life of the expansion, therefore additional water consumption. The Farm has two options for increasing its water consumption: bring the needed water from a nearby reservoir, or dig a well on its property; each alternative has its own characteristics:
The Farm will have to borrow the necessary capital from a Lending Institution; however, farm’s management does not know what interest the Institution will charge. In order to prepare for negotiating the interest rate, the Farm assumes the following forecast of parameters for the two alternatives:
Installation Cost O&M/yr Pump Replacement Water Cost/yr Life
Alternative A 25,000 1,000 N/A 4,000 20
Alternative B 35,000 3,000 5,000/10 yrs N/A 20
Identify the interest ranges where the farm should go for Alternative A, for Alternative B, which interest rate would make the two alternatives equivalent, and at which interest rate none of the two alternatives are economically feasible
Alternative A;
Installation cost = 25000
O&M Per year = 1,000
Water Cost /yr = 4000
Increase profit estimate = 15000
So monthly inflow = 15000- 1000 - 4000 = 10,000 for the next 20 years.
Let the rate of interest be x
So PV of Alternative A = -25000 + 10000/(1+x/100)^1 + 10000/(1+x/100)^2 + ... + 10000/(1+x/100)^20
= -25000 + 10000/(1+x/100) (1 + 1/(1+x/100)^1 + 1/(1+x/100)^2 + ... + 1/(1+x/100)^19)
= -25000 + 10000/(1+x/100) * (1/(1+x/100)^20 - 1) / (1/(1+x/100) - 1)
Alternative B:
Installation cost = 35000
O&M Per year = 3,000
Increase profit estimate = 15000
So monthly inflow = 15000- 3000 = 12,000 for the next 20 years.
Pump replacement = 5000 / 10 years
Let the rate of interest be x
So PV of Alternative B = -35000 + 12000/(1+x/100)^1 + 12000/(1+x/100)^2 + ... + 12000/(1+x/100)^20 - 5000*(1 /(1+x/100)^10)
= -35000 + 12000/(1+x/100) (1 + 1/(1+x/100)^1 + 1/(1+x/100)^2 + ... + 1/(1+x/100)^19) - 5000*(1 /(1+x/100)^10)
= -35000 + 12000/(1+x/100) * (1/(1+x/100)^20 - 1) / (1/(1+x/100) - 1) - 5000*(1 /(1+x/100)^10)
Let 1/(1+x/100) = y
If Alternative A is to be selected, then
-25000 + 10000y * (y^20 - 1) / (y - 1) > -35000 + 12000y * (y^20 - 1) / (y - 1) - 5000*(y^10)
or 2000y(y^20-1) / (y-1) - 5000 * y^10 < 10000
or 2y(y^20 - 1) / (y - 1) - 5y^10 < 10
Solving, we get y<0.85
or 1/(1+x/100)<0.85
or 1+x/100 > 1.176
or x>17.6%
If Alternative B is to be selected,
-25000 + 10000y * (y^20 - 1) / (y - 1) < -35000 + 12000y * (y^20 - 1) / (y - 1) - 5000*(y^10)
or 2000y(y^20-1) / (y-1) - 5000 * y^10 > 10000
or 2y(y^20 - 1) / (y - 1) - 5y^10 > 10
Solving, we get y>0.85
or 1/(1+x/100)>0.85
or 1+x/100 < 1.176
or x<17.6%
If neither of the option has to be feasible,
-25000 + 10000y * (y^20 - 1) / (y - 1) <0 and -35000 + 12000y * (y^20 - 1) / (y - 1) - 5000*(y^10)<0
solving, we get y<0.714 and y<0.7466
So at y<0.714, the projects are not feasible
or 1/(1+x/100) < 0.714
or 1+x/100 > 1.4
or x>40%
So Alternative A can be selected when the interest rate is between 17.6% and 40%
Alternative B can be selected when interest rate is less than 17.6%
Both the alternatives are equal at interest rate of 17.6%
Neither of the projects will be feasible at interest rates above 40%.
If you found this helpful, please rate it so that I can have higher earnings at no extra cost to you. This will motivate me to write more.