Question

In: Accounting

the construction activity for the year-end 31 December 2020, are as follows: project contract price costs...

the construction activity for the year-end 31 December 2020, are as follows:

project contract price costs incurred to 31/12/2020 estimated costs to complete billing to 31/12/2020 cash collections to 31/12/2020
AA $1,500,000 $400,000 $1,200,000 $300,000 $280,000

Required:

1) Prepare a schedule by project, showing clearly the amount of gross profit (loss) of the project before deducting selling, general, and administrative expenses for the year ended 31 December 2020 using the percentage-of-completion method.(based on estimated costs.)

2)Based on the schedule, show the amount of gross profit ( or loss) before selling, general,and administrative expenses for the year ended 31 December 2020, which would be reported if the following method are used:

(I) the cost-recovery method.

(II) The percentage-of-completion method ( based on estimated costs)

3) Determine the construction in process balance that would appear in the statement of financial position of the company as at 31/12/2020 for the project AA, assuming that the precentage-of-completion method is used. show all the working.

Solutions

Expert Solution

1) Preparation of schedule for the year ended 31st December 2020 :

Contract Contract Price Estimated costs Estimated gross profit/(loss) Revenue earned Cost of revenue   Gross Profit Estimated cost to complete Billed to date under billed
AA $1500000 $1600000 ($100000) $375000 $400000 ($25000) $1200000 $300000 $75000

Percent Complete = Cost of IncurredTo Date / Total Estimated Contract Cost

= $400000/ $1600000 = 25%

Contract Amount X Percent Complete = Total Earned Revenues = %1500000 * 25% = $375000

Total Earned Revenues - Total Cost of Revenues = Gross Profit = $375000 - $400000 = ($25000)

2) Computation of gross profit under the following methods :

I) Cost recovery method

The cost recovery method of revenue recognition refers to a method in which a business does not recognize income related to a sale until the cash collected exceeds the cost of the goods or services sold. In other words, using this method, revenue is only recognized when cash payments have recovered the seller’s cost.

Here in this senario since the amount of cash collected $280000 does not recover the costs incurred till date by the seller $400000, the profit would not be recognized or reported in the current year. The revenue would be recognized during the period in which the cash collected exceeds the cost incurred till date.

II) Percentage of completion method :

The percentage of completion indicates that revenue from performance obligations recognized over a period of time should be based on the percentage of completion. The method recognizes revenues and expenses in proportion to the completeness of the contracted project. It is commonly measured through the cost-to-cost method.

Therefore as per this method , a loss of $25000 shall be reported in the current year financial statements.

3) Construction in process balance which would appear in the statement of financial position of the company as at 31/12/2020 is as follows :

Project AA 31/12/2020
Beginning balance nil
Cost accumulated during the period $1,600,000
Total Non transferred costs $1,600,000
Costs Transferred to P & L ($400,000)
Ending balance in Project AA's CIP $12,00,000

Related Solutions

the construction activity for the year-end 31 December 2020, are as follows: project contract price costs...
the construction activity for the year-end 31 December 2020, are as follows: project contract price costs incurred to 31/12/2020 estimated costs to complete billing to 31/12/2020 cash collections to 31/12/2020 AB $2,000,000 $600,000 $1,400,000 $450,000 $410,000 Required: 1) Prepare a schedule by project, showing clearly the amount of gross profit (loss) of the project before deducting selling, general, and administrative expenses for the year ended 31 December 2020 using the percentage-of-completion method. (based on estimated costs.) 2)Based on the schedule,...
Carla Tool Company’s December 31 year-end financial statements contained the following errors. December 31, 2020 December...
Carla Tool Company’s December 31 year-end financial statements contained the following errors. December 31, 2020 December 31, 2021 Ending inventory $9,400 understated $7,900 overstated Depreciation expense $2,200 understated — An insurance premium of $64,800 was prepaid in 2020 covering the years 2020, 2021, and 2022. The entire amount was charged to expense in 2020. In addition, on December 31, 2021, fully depreciated machinery was sold for $16,300 cash, but the entry was not recorded until 2022. There were no other...
Indigo Tool Company’s December 31 year-end financial statements contained the following errors. December 31, 2020 December...
Indigo Tool Company’s December 31 year-end financial statements contained the following errors. December 31, 2020 December 31, 2021 Ending inventory $10,300 understated $7,300 overstated Depreciation expense $2,500 understated — An insurance premium of $63,300 was prepaid in 2020 covering the years 2020, 2021, and 2022. The entire amount was charged to expense in 2020. In addition, on December 31, 2021, fully depreciated machinery was sold for $14,800 cash, but the entry was not recorded until 2022. There were no other...
Construction Ltd. had the following activity related to its shares for the year ended December 31,...
Construction Ltd. had the following activity related to its shares for the year ended December 31, 2020. Common shares outstanding, January 1: 150,000 $3, cumulative preferred shares outstanding, January 1: 3,000 During 2020 April 1: Declared a 2-for-1 stock split on common shares July 1: Issued 20,000 common shares. August 1: Issued 1,000 $2, non-cumulative preferred shares. October 1: Repurchased 50,000 common shares. December 1: Declared a 15% stock dividend on common shares. Net income for the year was $476,000....
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows: 2018 2019 2020 Costs incurred during the year $250,000 $600,000 $190,000 Partial billings $375,000 $500,000 $375,000 Estimated costs to complete $750,000 $212,500 $0 Collections $187,500 $469,000 $593,500 Instructions: 1. Assuming Deen the percentage of completion method: (a) Prepare a schedule that computes the gross profit for 2018 - 2020 (b) Determine...
Lyrtricks Ltd., which has a December 31 year end, had the following transactions in December 2020...
Lyrtricks Ltd., which has a December 31 year end, had the following transactions in December 2020 and January 2021: 2020 Dec. 1 The company borrowed $170,000 from a bank on a five-year loan payable. The terms of the loan stipulate that Lyrtricks must repay 1/5 of the principal every November 30 plus the interest accrued to that date. The loan bears interest at 9% per annum. Dec. 31 Recorded employee wages for December. The wages earned by employees amounted to...
Armada Ski’s year end is December 31. Some of the 2019 transactions are as follows: March...
Armada Ski’s year end is December 31. Some of the 2019 transactions are as follows: March 1 Paid $135,000 cash to purchase the following two assets:                                     Market               Est. Useful Est. Residual                Asset           Value                       Life                Value                Land             $80,000                    -                      -                Warehouse     60,000             20 years           $5,000 Armada Ski will use the straight-line amortization method for the warehouse. April 1    Purchased a used delivery van for $20,000 cash. The van sells for $30,000 when new. The van is...
The adjusted trial balance for Tybalt Construction as of December 31, 2017, follows.    TYBALT CONSTRUCTION...
The adjusted trial balance for Tybalt Construction as of December 31, 2017, follows.    TYBALT CONSTRUCTION Adjusted Trial Balance December 31, 2017 No. Account Title Debit Credit 101 Cash $ 5,000 104 Short-term investments 23,000 126 Supplies 8,100 128 Prepaid insurance 7,000 167 Equipment 40,000 168 Accumulated depreciation—Equipment $ 20,000 173 Building 150,000 174 Accumulated depreciation—Building 50,000 183 Land 55,000 201 Accounts payable 16,500 203 Interest payable 2,500 208 Rent payable 3,500 210 Wages payable 2,500 213 Property taxes payable...
The adjusted trial balance for Tybalt Construction as of December 31, 2015, follows.     TYBALT CONSTRUCTION...
The adjusted trial balance for Tybalt Construction as of December 31, 2015, follows.     TYBALT CONSTRUCTION Adjusted Trial Balance December 31, 2015 No. Account Title Debit Credit 101   Cash $ 5,000 104   Short-term investments 23,000 126   Supplies 8,100 128   Prepaid insurance 7,000 167   Equipment 40,000 168   Accumulated depreciation—Equipment $ 20,000 173   Building 150,000 174   Accumulated depreciation—Building 50,000 183   Land 55,000 201   Accounts payable 16,500 203   Interest payable 2,500 208   Rent payable 3,500 210   Wages payable 2,500 213   Property taxes payable...
Journalize the adjusting entry needed on December 31, 2020 the company’s year end, for each of...
Journalize the adjusting entry needed on December 31, 2020 the company’s year end, for each of the following independent cases. Adjusting entries are only made on December 31 in this company. Details of the Prepaid Rent Expense account are shown: prepaid rend Jan. 1 Bal 4500 Mar. 31 9000 Sept. 30 9000 The company pays office rent semi-annually on March 31 and September 30. At December 31, part of the last payment is still available to cover January to march...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT