In: Finance
You are manager of a manufacturing business. Business is going very well and one production line is at full capacity. You want to double the size of the production line. Engineering has estimated the cost and time required. It can be accomplished without effecting the existing production. The timing of the cash flows for the facility is as follows.
Month |
Cash Flow |
1 |
$ (20,000.00) |
2 |
$ (45,000.00) |
3 |
$ (55,000.00) |
4 |
$ (70,000.00) |
5 |
$ (75,000.00) |
6 |
$ (80,000.00) |
7 |
$ (90,000.00) |
8 |
$ (90,000.00) |
9 |
$ (120,000.00) |
10 |
$ (140,000.00) |
11 |
$ (180,000.00) |
12 |
$ (200,000.00) |
13 |
$ (225,000.00) |
14 |
$ (175,000.00) |
15 |
$ (200,000.00) |
16 |
$ (50,000.00) |
Total |
$ (1,815,000.00) |
The current cost of capital is 9% APR. What is the total cost of the project?
You pay interest on the project every year (i.e., you do not pay off the capital, only the interest.) Calculate the total project cost including interest. Use annual numbers to calculate the internal rate of return.
Sales start after the project is completed. You estimate that sales for the first year will be at 30% of capacity and increase to 60% in year 2. Sales after year 2 are estimated at 85% of capacity. The current production line generates $1,100,000 in net profit. The profit at 30% is 0. The profit above 30% will be proportional to the percent capacity utilized. The company demands a minimum 20% internal rate of return for capital projects. Does the 10-year rate of return meet the company requirements? Assume that the company pays interest on the capital for the entire ten years. (Show correct total project cost including Interest, 10 year cash flow, and IRR for project)
Please identify formulas and explain why. Thank
you!
Month = n | Cash Flow | Int.=Cash flow*9%*(16-n)/12 | |
1 | 20,000 | 2250 | |
2 | 45,000 | 4725 | |
3 | 55,000 | 5363 | |
4 | 70,000 | 6300 | |
5 | 75,000 | 6188 | |
6 | 80,000 | 6000 | |
7 | 90,000 | 6075 | |
8 | 90,000 | 5400 | |
9 | 120,000 | 6300 | |
10 | 140,000 | 6300 | |
11 | 180,000 | 6750 | |
12 | 200,000 | 6000 | |
13 | 225,000 | 5063 | |
14 | 175,000 | 2625 | |
15 | 200,000 | 1500 | |
16 | 50,000 | 0 | |
Total | 1,815,000 | 76,838 | 1,891,838 |
Total capital incl.int. at timt =mth 16 end=1815000+76838=1891838 | |||
Future value at time mth 16 end=1891838 | |||
So, value(PV) of the total capital at t=0 (beginning of the yr.)= | |||
PV=1891838/(1.0075)^4= | |||
1836131 |
Explanation for-- Int.=Cash flow*9%*(16-n)/12 (Column 3) |
Given that "total project cost to be calculated including interest" |
Formula used for purpose of calculation in EXCEL. |
Interest for the amount borrowed (assuming end of month borrowing)at the rate of 9% p.a for ,so many months, |
ie.amt. was borrowed over a period of 16 months. |
20000*9%*15/12=2250 |
45000*9%*14/12=4725 |
55000*9%*13/12=5363 |
& so on till 16 the mth(which carries no interest as 16-16-0) |
At the end of 16 months, total interest comes to $ 76838 |
which when added to the principal ,puts the cost of the total investment(Principal+interest) at time t=16 mths.= 1891838. |
Then this 1891838 was brought down(discounted) to its Present Value at end of t=12 mths or beginning of the next time= 0 as 1836131 using monthly interest of 9% /12 =0.0075 |
Year | Capacity utilised | |||||
Yr. 0 Project cost | -1836131 | |||||
1 | 0 | 30% | Profit at 30% | 0 | ||
2 | 660000 | 60% | 100% capacity | 1100000 | ||
3 | 935000 | 85% | 60% | 1100000/100*60= | 660000 | |
4 | 935000 | 85% | 85% | 1100000/100*85= | 935000 | |
5 | 935000 | 85% | ||||
6 | 935000 | 85% | ||||
7 | 935000 | 85% | ||||
8 | 935000 | 85% | ||||
9 | 935000 | 85% | ||||
10 | 935000 | 85% | ||||
IRR | 32.60% | |||||
Cash flows after annual interest at 9%*1836131=165252 | ||||||
Year | Capacity utilised | |||||
Yr. 0 Project cost | -1836131 | |||||
1 | -165252 | 30% | ||||
2 | 494748 | 60% | ||||
3 | 769748 | 85% | ||||
4 | 769748 | 85% | ||||
5 | 769748 | 85% | ||||
6 | 769748 | 85% | ||||
7 | 769748 | 85% | ||||
8 | 769748 | 85% | ||||
9 | 769748 | 85% | ||||
10 | 769748 | 85% | ||||
IRR | 24.84% | |||||
Given, | ||||||
The company demands a minimum 20% internal rate of return for capital projects | ||||||
As the IRR in both the above cases >20%, the project is recommended. | ||||||