In: Economics
You are a hotel manager and you are considering four projects that yield different payoffs, depending upon whether there is an economic boom or a recession. The potential payoffs and corresponding payoffs are summarized in the following table. Project Boom (50%) Recession (50%) A $20 -$10 B -$10 $20 C $30 -$30 D $50 $50 If a manager adopted both project A and B simultaneously, the variance in returns associated with this joint project would be:
Solution:-
Following Formula is used to Calculate the Mean
Mean=Total observation/No. of observations
The following formula is used to calculate the Variance
Variance=[∑(X-Mean)^2]/No. of Observation
Find the mean and Variance of A and B Projects:
Project A:
Mean=20-10/2=10/2=5
Variance=[(20-5)^2+(-10-5)^2]/2
=[(15)^2+(-15)^2]/2
=225+225/2
=225
So, the Variance of Project A is 225.
Project B:
Mean=-10+20/2=10/2=5
Variance= [(-10-5)^2+(20-5)^2]/2
=[(-15)^2+(15)^2]/2
=225+225/2
=225
So, the Variance of Project A is 225.
Thus,the variance in returns associated with this joint project would be 225.