Question

In: Economics

You are a hotel manager and you are considering four projects that yield different payoffs, depending...

You are a hotel manager and you are considering four projects that yield different payoffs, depending upon whether there is an economic boom or a recession. The potential payoffs and corresponding payoffs are summarized in the following table. Project Boom (50%) Recession (50%) A $20 -$10 B -$10 $20 C $30 -$30 D $50 $50 If a manager adopted both project A and B simultaneously, the variance in returns associated with this joint project would be:

Solutions

Expert Solution

Solution:-

Following Formula is used to Calculate the Mean

Mean=Total observation/No. of observations

The following formula is used to calculate the Variance

Variance=[∑(X-Mean)^2]/No. of Observation

Find the mean and Variance of A and B Projects:

­Project A:

Mean=20-10/2=10/2=5

Variance=[(20-5)^2+(-10-5)^2]/2

                =[(15)^2+(-15)^2]/2

                =225+225/2

                =225

So, the Variance of Project A is 225.

­Project B:

Mean=-10+20/2=10/2=5

Variance= [(-10-5)^2+(20-5)^2]/2

                =[(-15)^2+(15)^2]/2

                =225+225/2

                =225

So, the Variance of Project A is 225.

Thus,the variance in returns associated with this joint project would be 225.


Related Solutions

you are a hotel manager, and are considering four projects that yield different payoffs, depending upon...
you are a hotel manager, and are considering four projects that yield different payoffs, depending upon whether there is an economic boom or recession. The potential payoffs and corresponding payoffs are summarized in the following table. Boom (60%) Recession (40%) A 50 -5 B 30 -30 C 20 10 D 60 -30 Calculating expected value and standard deviation, and explain what is your preferred project if you are risk neutral? Risk averse? If you could combine project C and D...
1-If you were the manager of a luxury hotel with 300 rooms and different types of...
1-If you were the manager of a luxury hotel with 300 rooms and different types of restaurants, what functionalities would you want from the PMS? Give examples for the integration between the PMS and three other IT systems. 2-Give examples of other channels that you will use to sell the hotel and how the PMS will help you to manage those channels?
DO NOT ANSWER IN EXCEL Mangement is considering two hotel projects. Project A will be in...
DO NOT ANSWER IN EXCEL Mangement is considering two hotel projects. Project A will be in Jamaica with an intial investment of $865,000 and Project B will be in Canada with an initial investment of $750,000 Years     Project A   Project B Year 1 CashFlow                           316,000.00    200,000.00 Year 2 CashFlow                           350,000.00    200,000.00 Year 3 CashFlow                           (20,000.00)    (15,000.00) Year 4 CashFlow                           280,000.00    390,000.00 The cost of capital for Project A is 13% and...
Mangement is considering two hotel projects. Project A will be in Jamaica with an intial investment...
Mangement is considering two hotel projects. Project A will be in Jamaica with an intial investment of $865,000 and Project B will be in Canada with an initial investment of $750,000 Years     Project A   Project B Year 1 CashFlow                           316,000.00    200,000.00 Year 2 CashFlow                           350,000.00    200,000.00 Year 3 CashFlow                           (20,000.00)    (15,000.00) Year 4 CashFlow                           280,000.00    390,000.00 The cost of capital for Project A is 13% and the cost of capital for...
Toby is considering two hotel projects. Project A will be in Jamaica with an initial investment...
Toby is considering two hotel projects. Project A will be in Jamaica with an initial investment of $865,000 and Project B will be in Canada with an initial investment of $750,000. years Project a Project b Yr1 316000 200000 Yr2 350000 200,000 Yr3 (20000) (15000) yr 4 280000 390000 The cost of capital for Project A is 13% and the cost of capital for project B is 15%. Calculate the following; Calculate the discounted payback period of Project A.                                     Calculate...
Mercer Development is considering the potential of four different development projects. Each project would be completed...
Mercer Development is considering the potential of four different development projects. Each project would be completed in at most three years. The required cash outflow for each project is given in the table below, along with the net present value (NPV) of each project and the budget cash that is available to spend for each year. Cash Outflow Required ($ million) Budget Cash Available ($ million) Project 1 Project 2 Project 3 Project 4 Year 1 10 9 6 12...
You have been appointed as the new general manager of a named hotel. The hotel is...
You have been appointed as the new general manager of a named hotel. The hotel is not performing as expected and is not meeting its target. Your first assignment is to resolve this problem. Describe in details how you would go about addressing this problem. Hint: Describe the data collection approaches you would use (Observation, interviews, surveys, historical research (past 5 years), etc.) and why you chose this specific form of data collection etc.
The market sells four different types of perfumes. The manager reports that the four different perfumes...
The market sells four different types of perfumes. The manager reports that the four different perfumes are equally popular. Suppose that a sample of 100 purchases yields observed counts 30, 24, 22, and 24, for types 1, 2, 3, and 4 respectively. Use a 0.10 significance level to test the claim that the four types are equally popular. (a) Identify the appropriate hypothesis test and explain the reasons why it is appropriate for analyzing this data. (b) Identify the null...
A firm is considering two mutually exclusive projects, A and B. The projects are different in...
A firm is considering two mutually exclusive projects, A and B. The projects are different in that they have different returns depending on general economic conditions. The firm forecasts that return on the market, and the returns on each project, along with their associated probabilities will be given by the following table. You can assume a 5% risk free rate and a 6% market risk premium. Assume the CAPM holds. Compare the expected returns to the cost of capital for...
TtThere are two different projects which you are managing as a project manager, the team members...
TtThere are two different projects which you are managing as a project manager, the team members and stockholders for the project are four and six respectfully, calculate the number of communication channels and provide a diagram illustrating the people and the communication channels for each project.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT