Determine the labor costs required to manufacture the 100th item if the first item requires 50 days to produce and the learning curve is 82%. The manufacturing process requires two 9-hour shifts working each day, with 8 employees per shift. The employees are paid $17.50 per hour.
Solution :-
As per Learning Curve theory
Y = axb
Where a is time required for 1st unit = 50 * 9 * 2 = 900
X is Number of Units Produced
b is learning coefficient
Value of b = Log ( 0.82 ) / Log ( 2 ) = - 0.086186 / 0.30103 = - 0.2863
Now Cummulative hours required for 99 Units =
Y = ( 900 ) ( 99 )-0.2863
Y = 900 * 0.268318 = 241.486 hours
Therefore time required for 99 Units = 99 * 241.486 = 23907.114 Hours
Now Cummulative hours required for 100 Units =
Y = ( 900 ) (100 )-0.2863
Y = 900 * 0.267547 = 240.792 hours
Therefore time required for 100Units =100 * 240.792 = 24079.225 hours
Therefore time Required for 100 th Units = 24079.225 hours - 23907.114 Hours = 172.11 hours
Labor cost for 1 hour per employee = $17.50
Now Labor Cost for one unit that is of 8 workers per unit for 172.11 hours = 172.11 * 17.50 * 8 = $24,095.54
If there is any doubt please ask in comments
Thank you please rate ....