In: Accounting
You are to prepare a cost estimate for producing 1000 assemblies. Each assembly consists of a cylindrical tube, two identical end covers, and a purchased bracket. The brackets cost $8.25 each. Each tube costs $180 for the casting and requires 2.5 standard hours of machining. It requires 12 hours to set up the machining operations and a setup is good for the machining of 500 castings. The end covers are produced on a punch press that requires 1.2 hours per cover of run time and 4.0 hours for press setup. Press setup is good for producing 400 pieces. Material costs per cover is $.50. The direct labor rate is $16.00 per hour. Manufacturing overhead is 150 percent of direct manufacturing labor. Material overhead is 3 percent of the total material and subcontract amount. General and administrative costs are 15 percent of labor and material with appropriate overhead.
What is the calculated unit cost through general and administrative costs? Show your calculations
You are to prepare a bid for producing 100 brackets. The brackets are made on a punch press and screen printed with a part number. All screen printing is done at one time, but the brackets are made in batches of 40. Punch press set up time is 2 hours per setup and .05 hour per print. Screen printing required is 6 minutes per bracket. Assume no attrition or learning curve on either process. Material cost is $.50 per piece. Direct labor rate is $15.00 and overhead is 200 percent of direct labor. G&A is 30 percent of total material, labor, and overhead costs. A 10 percent profit is expected.
What is your total bid price for the 100 brackets? Show your calculations.
The John Day Company proposed a general and administrative (G&A) rate of 16.8 percent of total manufacturing costs on a 20x8 proposal. The contractor provided the following data upon the request of the contract negotiator who desired to analyze the rate.
Given: | ||
1 Assembly comprises: | No./ Assembly | |
a. | Tube | 1 |
b. | End-cover | 2 |
c. | Brackets | 1 |
1 | Material cost calculations: | |
a. | Cost of Tube/ Assembly | Amount $ |
Cost of Casting for Tube/Assembly $ | 180 | |
Therefore, for 1000 Assemblies | 1,80,000 | |
b. | Cost of End cover set/ Assembly | |
No. of end-covers / assembly | 2 | |
i | Cost of 1 end-cover $/Unit | 0.5 |
ii | Cost of 2 end-covers (2*$0.5) | 1 |
Cost of end-cover set/ assembly | 1 | |
iii. | Cost of 1000 end-cover sets for 1000 Assemblies | 1,000 |
c. | Cost of Brackets | |
Cost per Bracket $ / Unit per Assembly | 8.25 | |
Therefore, cost of 1000 brackets for 1000 Assemblies | 8,250 | |
A | Material Cost Summary for 1000 Assemblies | Amount $ |
1 | Tube - See working 1a | 1,80,000 |
2 | 2 End covers - See Working 1 b | 1,000 |
3 | Brackets - See Working 1c | 8,250 |
A | Total Direct Material Cost for 1000 Assemblies | 1,89,250 |
2 | Direct Labor cost calculations: | |
a. | Tubes for 1000 Assemblies: | |
i | Machining Time (in Hours) | |
No. of Standard hours of machining per Tube | 2.5 | |
Therefore, Machining Hours fir 1000 Tubes | 2,500 | |
ii. | Set-up Time | |
Set-up time required for machining operations (in Hrs) | 12 | |
Set-up time for 1000 assemblies ( as each set-up is good for 500 Castings or 500 Assemblies. So, only 1 Set-up will be required) : 12*1 | 12 | |
a. | Therefore, Total Machining and Set-up time for 1000 Tubes for 1000 Assemblies (i+ii) | 2,512 |
b. | Direct Labor Time for end-covers | |
i. | Run-Time on Punch press | |
Run-time per end-cover | 1.2 | |
Run-time for 2 end-covers (or set of end-covers) | 2.4 | |
i. | Therefore, Run-Time for 1000 end-cover sets | 2400 |
ii. | Set-up time: | |
No. of hours per Set-up | 4 | |
1 set-up is good for | 400 pieces | |
No. of end-cover pieces in 1000 assemblies (2 end-covers per assembly) | 2000 | |
Therefore, No. of set-ups for 2000 pieces (2000/400 = 5 - 1 = 4 set-ups | 4 | |
Therefore, total Set-up time for 1000 Assemblies (4*5) | 16 | |
b. | Therefore, Direct Labour Time (hrs) for end-covers (i+ii) | 2416 |
Therefore, Direct Labor Hours for 1000 Assemblies (a+b) | 4,928 | |
Direct Labor Rate / Hour (in $) | 16 | |
b. | Therefore, Direct Labor Cost for 1000 Assemblies | 78,848 |
c. | Manufacturing Overhead @ 150% of Direct Labour Cost (150% * $79,104) | 1,18,272 |
d. | Material overheads: | Amount$ |
i | Direct Material cost (see a above) | 1,89,250 |
ii. | Direct Labour cost (as these Machining and Punch Press are done on sub contract) | 78,848 |
Total Material + Sub-contract | 2,68,098 | |
d. | Therefore, Material Overhead at 3% of Material + Sub Contract | 8042.94 |
e | General & Administrative costs: | Amount $ |
i | Direct Material (see a above) | 1,89,250 |
ii | Direct Labor cost ( see b above) | 78,848 |
iii | Appropriate overhead on Material ( i.e.,Material Overhead - see d above) | 8042.94 |
Total Base for General and Administrative costs | 2,76,141 | |
e | Therefore, General and Administrative cost @ 15% of above base | 41,421.14 |
S.No. | Unit Cost | Amount $ |
i | Direct Material cost | 1,89,250 |
ii | Direct Labor cost | 78,848 |
iii | Material Overhead | 8042.94 |
iv | Manufacturing Overhead | 1,18,272 |
v | Total Manufacturing Cost ( Product Cost) : i+ii+iii+iv | 3,94,413 |
vi. | General and Administrative cost | 41,421.14 |
vii | Total cost ( (v+ vi) | 4,35,834.08 |
viii | Total number of Assemblies | 1000 |
Answer | Total Unit Cost ( vii/viii) | 435.83 |
Q 2 | Price Bid for 100 Brackets | |
S.No. | Particulars | Amount $ |
i. | Material cost of 100 Brackets @ $ 0.50/ Unit | 50.00 |
ii. | Direct Labor cost ( See Note f below) | 285.00 |
iii. | Overheads @ 200% of Direct Labor Cost | 570.00 |
iv. | Total Manufacturing Cost ( I + ii+iii) | 905.00 |
v. | General & Administrative cost @ 30% of iv above | 271.50 |
vi. | Total cost for 100 Brackets (iv + v) | 1,176.50 |
vii. | Profits @ 10% of Price Bid ( 10% of viii) | 130.72 |
viii. | Total Price Bid for 100 Brackets ( 100/90* $ 1,176.5) | 1,307.22 |
Note f. | Computation of Direct Labor cost for 100 Brackets | |
Direct Labor Hours for Punch Press | ||
Punch Press time / bracket (in hrs) | 0.05 | |
i | Punch Press time for 100 brackets ( 100*0.05) - in hours | 5 |
ii | Set-up time | |
No of brackets per batch | 40 | |
No. of batches for 100 Brackets (100/40) | 2.5 | |
Time for each set-up / batch - in hours | 2 | |
ii | No. of batches for 100 units -Every batch of 40 Brackets will need a set up time of 2 hrs. So, 100 brackets will need 2 set-ups. Therefore, set-up time for 100 brackets: 2* 2 = 4 hrs | 4 |
iii | Direct Labour hours in Punch Press for 100 Brackets (I + ii) | 9 |
iv | Direct Labor Hours for Printing of Part numbers on Brackets: | |
Time required for printing per bracket ( 6 min / bracket or 6/60 of 1 hr) | 0.1 | |
iv | Therefore, printing time for 100 brackets (100*0.10) - in hours | 10 |
v | Therefore, Total Direct Labor Hours for 100 brackets (iii + iv) | 19 |
vi. | Direct Labor Rate / Hour in $ | 15 |
vii. | Therefore, Direct Labor Cost for 100 Brackets (v * vi) | 285 |