In: Accounting
Predetermined Overhead Rates, Overhead Variances, Unit Costs
Primera Company produces two products and uses a predetermined overhead rate to apply overhead. Primera currently applies overhead using a plantwide rate based on direct labor hours. Consideration is being given to the use of departmental overhead rates where overhead would be applied on the basis of direct labor hours in Department 1 and on the basis of machine hours in Department 2. At the beginning of the year, the following estimates are provided:
Department 1 | Department 2 | ||
Direct labor hours | 640,000 | 128,000 | |
Machine hours | 16,000 | 192,000 | |
Overhead cost | $384,000 | $1,152,000 |
Actual results reported by department and product during the year are as follows:
Department 1 | Department 2 | ||
Direct labor hours | 627,200 | 134,400 | |
Machine hours | 17,600 | 204,800 | |
Overhead cost | $400,000 | $1,232,000 |
Product 1 | Product 2 | ||
Direct labor hours | |||
Department 1 | 480,000 | 147,200 | |
Department 2 | 96,000 | 38,400 | |
Machine hours | |||
Department 1 | 8,000 | 9,600 | |
Department 2 | 24,800 | 180,000 |
Required:
1. Compute the plantwide predetermined overhead
rate.
$ per direct labor hour
Calculate the overhead assigned to each product.
Product 1 | $ |
Product 2 | $ |
2. Calculate the predetermined departmental overhead rates. If required, round your answers to the nearest cent.
Department 1 | $ per direct labor hour |
Department 2 | $ per machine hour |
Calculate the overhead assigned to each product.
Product 1 | $ |
Product 2 | $ |
3. Using departmental rates, compute the
applied overhead for the year.
$
What is the under- or overapplied overhead for the firm?
$
4. Prepare the journal entry that disposes of the overhead variance calculated in Requirement 3, assuming it is not material in amount.
Requirement 1: Plant wide rate
plant wide overhead rate: Total overheads / Total labour
hours
Total overheads = 384,000+1152,000 = $1536,000
Total labour hours = 640,000 + 128,000 = 768,000 labour
hours
Plant wide rate = Total overheads / Total labour hours
(1536,000 / 768,000 ) = $2 per labour hours
Product 1 | Product 2 | |
Labour hours | ||
Department 1 | 480000 | 147200 |
Department 2 | 96000 | 38400 |
Total Labour hours | 576000 | 185600 |
Overheads applied @$2 per hour | 1152000 | 371200 |
Overheads applied | |
Product 1 | $1,152,000 |
Product 2 | $371,200 |
Req 2: Departmental overhead rate
Department 1: Total overheads of department / labour
horus
(384000 /640000) = $ 0.60 per labour hour
Department 2: Total overheads of department/ Machine
hours
(1152,000 /192000) = $ 6 per machine hour
Product 1 | Product 2 | |
Labour hours of Dept 1 | 480000 | 147200 |
Machine hours of Dept 2 | 24800 | 180000 |
Overheads assigned: | |||
Department 1(@ $ 0.60 per labour hour) | 288000 | 88320 | 376320 |
Department 2($6.00 per machine hour) | 148800 | 1080000 | 1228800 |
Total overheads assigned | 436800 | 1168320 | 1605120 |
Overheads applied | |
Product 1 | $436,800 |
Product 2 | $1,168,320 |
Req 3: Using departmental rates
As computed above, The total overheads assigned is $ 1605,120 (i.e.
436800+1168320)
Under-over applied overheads:
Overheads applied:
1605120
Less: Overheads incurred
Department 1 400,000
Department 2 1232000
1632000
Under applied overheads
26880
Req 4: Joural entry is as follows:
Cost of goods sold Account
Dr. $
26,880
Manufacturing overheads
$26,880