Question

In: Finance

Problem 3: A construction firm must obtain a bulldozer to work on a long-term project. There...

Problem 3: A construction firm must obtain a bulldozer to work on a long-term project. There are two options available to the firm – using a loan to purchase the bulldozer for $825,000, and leasing it from the equipment dealer. If the firm decides to purchase, it can finance the entire cost through a commercial bank for 8 years at an interest rate of 7.5% compounded annually. At the end of eight years, the firm will sell the bulldozer for a salvage value of $80,000.   If the firm decides to lease, it will pay the equipment dealer an up-front fee equal to 5% of the purchase price, followed by eight annual payments of $135,000. At the end of the lease, the firm will return the equipment to the dealer. The firm’s required rate of return is 10%.

  1. Build an Excel worksheet to model the two options and help the firm decide which to choose. You can ignore depreciation or tax effects in your analysis (i.e., evaluate the options simply based on their respective cash flows).
  2. Assuming that the equipment dealer is exactly indifferent between the construction firm purchasing or leasing, what is the dealer’s implied required rate of return? Note: the dealer retains the salvage value if the firm leases.

Solutions

Expert Solution

Under the purchase option

Annual payment of Loan (A) is given by

A/0.075*(1-1/1.075^8) = 825000

=> A = 140849.79

Net cost of bulldozer = 140849.79/1.1+140849.79/1.1^2+....+140849.79/1.1^8 - 80000/1.1^8

=140849.79/0.1*(1-1/1.1^8)-80000/1.1^8

=$714102.64

Under the Leasing option

Net cost of bulldozer = present value of payments

=5%*$825000 + 135000/1.1+135000/1.1^2+.....+135000/1.1^8

=$41250 + 135000/0.1*(1-1/1.1^8)

=$761465.04

So, in this case, the purchase option is better for the construction firm as the net cost is lesser in case of purchase

The dealer will spend $825000 today and receive 5% upfront fee as well as the annual lease payments and will also receive the salvage value at end of 8 years . So , the implied rate of return (r) to the dealer is given by

-825000+41250 + 135000/r*(1-1/(1+r)^8) + 80000/(1+r)^8 = 0

Solving r= 0.091176 or 9.12%

The dealer’s implied required rate of return is 9.12%


Related Solutions

PERCENTAGE OF COMPLETION METHOD AttiK Construction Company currently has a long-term construction project. The project has...
PERCENTAGE OF COMPLETION METHOD AttiK Construction Company currently has a long-term construction project. The project has a contract price of $130,000,000 with total estimated costs of $100,000,000. AttiK appropriately uses the percentage of completion method. After 2 years of construction, the following costs have been accumulated: Actual cost incurred, Year 1 $30,000,000 Total estimated costs remaining after Year 1 70,000,000 Actual cost incurred, Year 2 50,000,000 Total estimated cost remaining after Year 2 20,000,000 Determine the gross profit for each...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
What are the short-term and long-term effects on the environment that can arise from the construction...
What are the short-term and long-term effects on the environment that can arise from the construction of dams?
Show all work in the space provided. All work must be shown to obtain full credit....
Show all work in the space provided. All work must be shown to obtain full credit. If a calculator function was used, list exactly what was entered into the calculator. All z-score calculations must be shown. 1. According to one study, the average hours of sleep on a weeknight for men was 6.9 hours with a standard deviation of 1.5 hours. a. Find the proportion of men who sleep for more than 8 hours per night. b. Find the proportion...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 50 $ 150 $ 45 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018   Costs incurred during the year $ 50 Estimated costs to complete as of December 31 $200 2019  Costs incurred during...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 40 $ 80 $ 50 Estimated costs to complete as of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT