In: Accounting
AccuBlade Castings Inc. casts blades for turbine engines. Within the Casting Department, alloy is first melted in a crucible, then poured into molds to produce the castings. On May 1, there were 360 pounds of alloy in process, which were 60% complete as to conversion. The Work in Process balance for these 360 pounds was $50,112, determined as follows:
| 
 1  | 
 Direct materials (360 × $132)  | 
 $47,520.00  | 
| 
 2  | 
 Conversion (360 × 60% × $12)  | 
 2,592.00  | 
| 
 3  | 
 $50,112.00  | 
During May, the Casting Department was charged $353,600 for 2,600 pounds of alloy and $22,651 for direct labor. Factory overhead is applied to the department at a rate of 150% of direct labor. The department transferred out 2,760 pounds of finished castings to the Machining Department. The May 31 inventory in process was 15% complete as to conversion.
Required:
| A. | 
  | 
||||||||
| B. | Determine the Work in Process-Casting Department May 31 balance. | ||||||||
| C. | Compute and evaluate the change in the costs per equivalent unit for direct materials and conversion from the previous month (April). | 
| A) | ||||||
| a) | Account Titles & explanation | Debit | Credit | |||
| Work in Process—Casting Department | $ 3,53,600.00 | |||||
| Materials—Alloy | $ 3,53,600.00 | |||||
| b) | Work in Process—Casting Department | $ 56,627.50 | ||||
| Wages Payable | $ 22,651.00 | |||||
| Factory Overhead ($22,651 x 150%) | $ 33,976.50 | |||||
| c) | Work in Process—Machining Department | $ 4,32,497.46 | ||||
| Work in Process—Casting Department | $ 4,32,497.46 | |||||
| Cost of 2,760 transferred-out pounds: | ||||||
| Inventory in process, May 1 | $ 50,112.00 | |||||
| Cost to complete May 1 inventory (360 x 60% x $21.40) | $ 4,622.65 | |||||
| Pounds started and completed in May [2,400 lbs. × ($136 + $21.40)] | $ 3,77,762.81 | |||||
| Transferred to Machining Department | $ 4,32,497.46 | |||||
| Equivalent unit and cost per equivalent unit calculations: | ||||||
| 
 Equivalent Units  | 
||||||
| Physical units | Material | Conversion | ||||
| Inventory in process, May 1 (60% completed) | 360.00 | 0.00 | 216.00 | |||
| Started and completed in May (2760 -360) | 2400.00 | 2400.00 | 2400.00 | |||
| Transferred to Machining Department in may | 2760.00 | 2400.00 | 2616.00 | |||
| Inventory in process, May 31 (15% completed) (360+2600-2760) | 200.00 | 200.00 | 30.00 | |||
| Total | 2960.00 | 2600.00 | 2646.00 | |||
| Cost per equivalent unit of materials: = 353600 /2600 | 136.00 | Per Pound | ||||
| Cost per equivalent unit of conversion: 56,627.50/2646 | 21.40 | Per pound | ||||
| B) | ||||||
| Direct materials (200 × $136) | $ 27,200.00 | |||||
| 
 Conversion (200 × 15% × $21.40)  | 
$ 642.04 | |||||
| Work in Process-Casting Department May 31 balance | $ 27,842.04 | |||||
| C) | ||||||
| Materials | 
 From current period  | 
$ 136.00 | ||||
| From beginning inventory | $ 132.00 | |||||
| Increase | $ 4.00 | |||||
| Conversion | 
 From current period  | 
$ 21.40 | ||||
| From beginning inventory | $ 12.00 | |||||
| Increase | $ 9.40 | |||||
| The cost per equivalent unit of materials increased by $4 per pound and the cost per equivalent unit of conversion cost increased by $9.40 per pound | ||||||