In: Accounting
Cost of Production and Journal Entries
AccuBlade Castings Inc. casts blades for turbine engines. Within the Casting Department, alloy is first melted in a crucible, then poured into molds to produce the castings. On May 1, there were 700 pounds of alloy in process, which were 60% complete as to conversion. The Work in Process balance for these 700 pounds was $102,620, determined as follows:
Direct materials (700 x $140) | $98,000 |
Conversion (700 x 60% x $11) | 4,620 |
$102,620 |
During May, the Casting Department was charged $897,600 for 6,600 pounds of alloy and $26,320 for direct labor. Factory overhead is applied to the department at a rate of 150% of direct labor. The department transferred out 6,800 pounds of finished castings to the Machining Department. The May 31 inventory in process was 40% complete as to conversion.
a1. Prepare the May journal entry for the Casting Department for the materials charged to production.
a2. Prepare the May journal entry for the Casting Department for the conversion costs charged to production. If an amount box does not require an entry, leave it blank.
a3. Prepare the May journal entry for the Casting Department for the completed production transferred to the Machining Department.
b. Determine the Work in Process—Casting
Department May 31 balance.
$
c. Compute the change in the costs per equivalent unit for direct materials and conversion from the previous month (April).
Cost per Equivalent Unit | ||
Change in materials | $ | |
Change in conversion |
General Journal | Debit | Credit | |
a-1 | Work in process-Casting department | $897,600 | |
Raw material inventory | $897,600 | ||
a-2 | Work in process-Casting department | $65,800 | |
Factory wages | $26,320 | ||
Factory overhead ($26,320*150%) | 39,480 | ||
a-3 | Work in process - Machining department | $996,020 | |
Work in process-Casting department | $996,020 |
b.
Work in process - Casting department May 31 balance:
Material cost (500*$136) | $68,000 |
Conversion cost (200*$10) | 2,000 |
Cost of Work in process - Casting department May 31 balance | $70,000 |
c.
Cost per equivalent unit | ||
Change in material | Decrease | $4 ($140-136) |
Change in conversion | Decrease | $1 ($11-10) |
Equivalent units | |||||
Material | Conversion | ||||
Physical units | %completion | Units | %completion | Units | |
Beginning work in process | 700 | 40% | 280 | ||
Units started and completed | 6,100 | 100% | 6,100 | 100% | 6,100 |
Units completed and transferred | 6,800 | ||||
Ending work in process | 500 | 100% | 500 | 40% | 200 |
Total | 7,300 | 6,600 | 6,580 |
Material | Conversion | ||
Cost incurred during May | $897,600 | $65,800 | |
Total equivalent units | 6,600 | 6,580 | |
Cost per equivalent unit | $136 | $10 | $146 |
Cost of units transferred to machining department:
Cost of beginning work in process: | |
Beginning balance | $102,620 |
Further cost incurred (280*$10) | 2,800 |
Cost of beginning work in process (A) | $105,420 |
Cost of units started and completed (6,100*$146) (B) | $890,600 |
Total cost of units transferred to machining department (A)+(B) | $996,020 |