In: Finance
Consider the following two mutually exclusive projects: |
Year | Cash Flow (A) | Cash Flow (B) |
0 | –$199,954 | –$15,324 |
1 | 27,800 | 5,058 |
2 | 55,000 | 8,105 |
3 | 56,000 | 13,036 |
4 | 404,000 | 8,859 |
Whichever project you choose, if any, you require a 6 percent return on your investment. |
Required: |
(a) | What is the payback period for Project A? |
(Click to select) 2.99 years 3.25 years 3.15 years 3.06 years 3.31 years |
(b) | What is the payback period for Project B? |
(Click to select) 2.23 years 2.27 years 2.1 years 2.17 years 2.06 years |
(c) | What is the discounted payback period for Project A? |
(Click to select) 3.41 years 3.34 years 3.24 years 3.08 years 3.15 years |
(d) | What is the discounted payback period for Project B? |
(Click to select) 2.37 years 2.42 years 2.24 years 2.31 years 2.19 years |
(e) | What is the NPV for Project A? |
(Click to select) $254,359.08 $242,246.74 $230,134.4 $234,979.34 $249,514.14 |
(f) | What is the NPV for Project B ? |
(Click to select) $13,892.38 $15,354.73 $14,184.85 $14,623.55 $15,062.26 |
(g) | What is the IRR for Project A? |
(Click to select) 35.02% 35.7% 32.98% 32.3% 34% |
(h) | What is the IRR for Project B? |
(Click to select) 38% 39.14% 36.1% 39.9% 36.86% |
(i) | What is the profitability index for Project A? |
(Click to select) 2.322 2.212 2.278 2.101 2.145 |
(j) | What is the profitability index for Project B? |
(Click to select) 2.013 2.052 1.857 1.896 1.954 |
(a) | 3.15 Years | ||||||||
(b) | 2.17 Years | ||||||||
(c) | 3.24 Years | ||||||||
(d) | 2.31 Years | ||||||||
(e) | $ 2,42,246.74 | ||||||||
(f) | $ 14,623.55 | ||||||||
(g) | 34% | ||||||||
(h) | 38% | ||||||||
(i) | 2.212 | ||||||||
(j) | 1.954 | ||||||||
Working: | Project A | Project B | |||||||
Year | Discount factor | Cash flow | Cumulative Cash flow | Present value of cash flow | Cumulative Present value of cash flow | Cash flow | Cumulative Cash flow | Present value of cash flow | Cumulative Present value of cash flow |
a | b=1.06^-a | c | x | d=b*c | e | f | y | g=b*f | h |
0 | 1.0000 | $ -1,99,954.00 | $ -1,99,954.00 | $ -1,99,954.00 | $ -1,99,954.00 | $ -15,324.00 | $ -15,324.00 | $ -15,324.00 | $ -15,324.00 |
1 | 0.9434 | 27,800.00 | -1,72,154.00 | $ 26,226.42 | -1,73,727.58 | 5,058.00 | -10,266.00 | 4,771.70 | -10,552.30 |
2 | 0.8900 | 55,000.00 | -1,17,154.00 | $ 48,949.80 | -1,24,777.78 | 8,105.00 | -2,161.00 | 7,213.42 | -3,338.88 |
3 | 0.8396 | 56,000.00 | -61,154.00 | $ 47,018.68 | -77,759.10 | 13,036.00 | 10,875.00 | 10,945.28 | 7,606.40 |
4 | 0.7921 | 4,04,000.00 | 3,42,846.00 | $ 3,20,005.84 | 2,42,246.74 | 8,859.00 | 19,734.00 | 7,017.16 | 14,623.55 |
IRR | =irr(C4:C8) | =irr(G4:G8) | |||||||
34.00% | 38.00% | ||||||||
Payback of : | |||||||||
Project A | = | 3+(61154/404000) | = | 3.15 | |||||
Project B | = | 2+(2161/13036) | = | 2.17 | |||||
Discounted payback of: | |||||||||
Project A | = | 3+(77759.10/320005.84) | = | 3.24 | |||||
Project B | = | 2+(3338.88/10945.28) | = | 2.31 | |||||
Profitability index of: | |||||||||
Project A | = | Present value of cash inflow /Cost of project | |||||||
= | (199954+242246.74)/199954 | ||||||||
= | 2.212 | ||||||||
Project B | = | Present value of cash inflow /Cost of project | |||||||
= | (15324+14623.55)/15324 | ||||||||
= | 1.954 |