In: Finance
John Claire, the CFO of Projection Investment Ltd, is
considering two
mutually exclusive projects.
Year | Cash Flow (X) $’000 | Cash Flow (Y) $’000 |
0 | -40,000 | -40,000 |
1 | 19,000 | 4,000 |
2 | 15,200 | 12,600 |
3 | 12,400 | 14,900 |
4 | 6,000 | 28,000 |
In each case, show your calculation clearly.
a If he applies the payback criterion, which project will he
choose?
b If he applies the IRR criterion, which project will he choose?
c If he applies the NPV criterion with a required return of 9%, which project will he choose?
d At which discount rate (correct to 1 decimal place of a percentage) would he be indifferent between these two projects?
a. Payback Period Criterion:
X = 2.47 years
Y = 3.30 years
PROJECT X (in '000) | |||||||
Particulars | Initial Outlay | Year 1 | Year 2 | Year 3 | Year 4 | ||
Undiscounted Net Cash Flow | $ (40,000) | $ 19,000 | $ 15,200 | $ 12,400 | $ 6,000 | ||
Cumulative Net Cash Flow | (21,000) | (5,800) | 6,600 | 12,600 | |||
Completed Years | 2 | ||||||
Uncompleted Years | 0.47 | =-5800/(-5800+6600) | |||||
Payback period | 2.47 years |
PROJECT Y (in '000) | |||||||
Particulars | Initial Outlay | Year 1 | Year 2 | Year 3 | Year 4 | ||
Undiscounted Net Cash Flow | $ (40,000) | $ 4,000 | $ 12,600 | $ 14,900 | $ 28,000 | ||
Cumulative Net Cash Flow | (36,000) | (23,400) | (8,500) | 19,500 | |||
Completed Years | 3 | ||||||
Uncompleted Years | 0.30 | =8500/(8500+19500) | |||||
Payback period | 3.30 years |
Project X is better since the payback period is less.
b. IRR Criterion:
The project with higher IRR is chosen, hence Project X will be chosen.
c. NPV Criterion:
Project X- (Fig. in '000)
Years | Cash Flows | PV factor | PV |
0 | -40,000 | 1 | -40,000.00 |
1 | 19,000 | 0.91743 | 17,431.19 |
2 | 15,200 | 0.84168 | 12,793.54 |
3 | 12,400 | 0.77218 | 9,575.08 |
4 | 6,000 | 0.70843 | 4,250.55 |
NPV | 4,050.35 |
Project Y- (Fig. in '000)
Years | Cash Flows | PV factor | PV |
0 | -40,000 | 1 | -40,000.00 |
1 | 4,000 | 0.91743 | 3,669.72 |
2 | 12,600 | 0.84168 | 10,605.17 |
3 | 14,900 | 0.77218 | 11,505.53 |
4 | 28,000 | 0.70843 | 19,835.91 |
NPV | 5,616.33 |
Project Y is better since NPV is more.
d. The rate at which project will be indifferent: