Newago, Inc. is strapped for cash for investment projects and must decide which of four projects...

Newago, Inc. is strapped for cash for investment projects and must decide which of four projects it will fund. Below are the projects and information about them:

Life Of:

Net The Internal

Investment Present Project Rate Of

Project Required Value In Yrs. Return

1. 80,000 210,000 6 13%

2. 750,000 340,000 10 17%

3. 845,000 333,000 7 12%

4. 695,000 202,000 5 18%

A. Compute the project profitability index for each project.

B. Rank the four projects in order of preference in terms of:

Internal rate Of Return

Project Profitability Index

Net Value

C. Which of the three rankings above do you prefer?

What are the strengths and weaknesses of each method?  

Solutions

Expert Solution

Project Investment required Net present value Life of the project IRR
1 80000 210000 6 13%
2 750000 340000 10 17%
3 845000 333000 7 12%
4 695000 202000 5 18%
Project Net present value Investment required Profitability Index of Projects =1+(NPV/Investment required)
1 210000 80000 3.63
2 340000 750000 1.45
3 333000 845000 1.39
4 202000 695000 1.29
Ranking on the Basis of IRR
Rank Projects IRR
1 4 18%
2 2 17%
3 1 13%
4 3 12%
Ranking on the Basis of NPV
Rank Projects NPV
1 3 845000
2 2 750000
3 4 695000
4 9 80000
Ranking on the Basis of Profitability Index
Rank Projects PI
1 1 3.63
2 2 1.45
3 3 1.39
4 4 1.29
I would prefer ranking of Profitability Index because according to the PI ranking, projects are ranked on the basis of the benefits provided over the value of Investment required
Major Weakness of the IRR method is its assumptions like it consider that intermediate cash flows are reinvested at a rate equal to IRR which in actual not possible, drawback of NPV method is that It consider the value of benefits in terms of dollars and ignores the value of initial investment. while PI method consider the both cash inflow and outflow to calculate the ratio between the two and it is the best method to rank the project.

Related Solutions

The management of Sugar Daddy Cupcakes are analyzing two competing investment projects and must decide which...
The management of Sugar Daddy Cupcakes are analyzing two competing investment projects and must decide which one should be done immediately and which one to postpone for at least a year. The details of each proposed investment are provided below. The company has a 12% required rate of return to evaluate all investments that directly impact operations and amortizes the investment in plant and equipment using straight-line depreciation over 10 years. The company’s tax rate is 25%. The CCA rate...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $8,000 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: PROJECT A PROJECT B Probability Net Cash Flows Probability Net Cash Flows 0.2 $5,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 7,000 0.2 19,000 BPC has decided to evaluate the riskier...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $7,000 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $7,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 7,000 0.2 16,000 BPC has decided to evaluate the riskier project at...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $5,250 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $7,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 8,000 0.2 20,000 BPC has decided to evaluate the riskier project at...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $7,250 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $7,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 8,000 0.2 20,000 BPC has decided to evaluate the riskier project at...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each...
Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $7,250 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $7,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 8,000 0.2 20,000 BPC has decided to evaluate the riskier project at...
QUESTION 4: (a) The Workshop Manager must decide the sequence in which the four vehicles in...
QUESTION 4: (a) The Workshop Manager must decide the sequence in which the four vehicles in the workshop must be serviced. He has developed these estimates based on the First-Come-First-Served sequence rule: Vehicle ID Number Estimated Maintenance Time (days) Time to Promised Delivery (days) FCFS Order Sequence 226 27 39 1 229 33 30 2 224 41 60 3 225 29 75 4 Rank the FCFS, SPT and CR sequencing rules on three evaluation criteria: average flow time, average number...
Dunning, Inc. is trying to decide between two investment projects using NPV. Project A requires an...
Dunning, Inc. is trying to decide between two investment projects using NPV. Project A requires an initial investment of $600,000 and has annual cash inflows of $196,000 for the next 5 years. Project B has an initial investment of $400,000 and offers annual cash inflows of $88,000 over the next 7 years. Dunning, Inc. uses a 6% discount rate to evaluate investment projects. a) Calculate the NPV for both projects and determine which investment Dunning should choose.
OpenSea, Inc. is evaluating investment opportunities and should decide between two mutually exclusive projects: A, or...
OpenSea, Inc. is evaluating investment opportunities and should decide between two mutually exclusive projects: A, or B. Both projects require the same initial investments 14 million and generate different cash flows as follow: -Project (A) generates 3.0 million per year in a perpetuity - Project (B) generates 1.9 million in perpetuity growing at 2.2% (forever) If OpenSea is using the IRR to make her final decision, calculate the IRR of each of the following project. Calculate the NPV of both...
a) Four investment projects have the following net cash flows. The cost of capital is 15%....
a) Four investment projects have the following net cash flows. The cost of capital is 15%. Decide which of them should be accepted using the net present value method. Find the discounted payback period. YEAR PROJECT A PROJECT B PROJECT C PROJECT D 0 (10,000) (15,000) (20,000) (30,000) 1 5,000 5,000 10,000 0 2 5000 5,000 10,000 0 3 20,000 5,000 4,000 100,000 4 1,000 10,000 2,000 120,000 5 - 5,000 - 60,000
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT