In: Finance
Risky Cash Flows
The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $7,250 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions:
Project A | Project B | ||
Probability | Cash Flows | Probability | Cash Flows |
0.2 | $7,000 | 0.2 | $ 0 |
0.6 | 6,750 | 0.6 | 6,750 |
0.2 | 8,000 | 0.2 | 20,000 |
BPC has decided to evaluate the riskier project at a 13% rate and the less risky project at a 8% rate.
What is the expected value of the annual cash flows from each project? Do not round intermediate calculations. Round your answers to the nearest dollar.
Project A | Project B | |
Net cash flow | $ | $ |
What is the coefficient of variation (CV)? (Hint: σB=$6,522 and CVB=$0.81.) Do not round intermediate calculations. Round σ values to the nearest cent and CV values to two decimal places.
σ | CV | |
Project A | $ | |
Project B | $ |
What is the risk-adjusted NPV of each project? Do not round intermediate calculations. Round your answers to the nearest cent.
Project A | $ | |
Project B | $ |
If it were known that Project B is negatively correlated with other cash flows of the firm whereas Project A is positively correlated, how would this affect the decision?
This would tend to reinforce the decision to -Select-acceptrejectItem 9 Project B.
If Project B's cash flows were negatively correlated with gross domestic product (GDP), would that influence your assessment of its risk?
-Select-YesNoItem 10
Part a)
The expected value of the annual cash flows from each project is calculated as below:
Probability (1) | Project A Cash Flows (2) | Project B Cash Flows (3) | Expected Value Project A (1*2) |
Expected Value Project B (1*3) |
0.2 | 7,000 | 0 | 1,400 | 0 |
0.6 | 6,750 | 6,750 | 4,050 | 4,050 |
0.2 | 8,000 | 20,000 | 1,600 | 4,000 |
$7,050 | $8,050 |
Net Cash Flow (Project A) = $7,050
Net Cash Flow (Project B) = $8,050
_____
The standard deviation and covariance of Project A is arrived as follows:
Standard Deviation = [Probability 1*(Cash Flow 1 - Net Cash Flow)^2 + Probability 2*(Cash Flow 2 - Net Cash Flow)^2 + Probability 3*(Cash Flow 3 - Net Cash Flow)^2]^1/2
Substituting values in the above formula, we get,
Standard Deviation of Project A = [.2*(7,000 - 7,050)^2 + .6*(6,750 - 7,050)^2 + .2*(8,000 - 7,050)^2]^(1/2) = $485
Coefficient of Variation (Project A) = Standard Deviation of Project A/Expected Value of Project A = 484.77/7,050 = $0.07
Standard Deviation of Project B = [.2*(0 - 8,050)^2 + .6*(6,750 - 8,050)^2 + .2*(20,000 - 8,050)^2]^(1/2) = $6522
Coefficient of Variation (Project B) = Standard Deviation of Project B/Expected Value of Project B = 6,521.88/8,050 = $0.81
____
Tabular Representation:
σ | CV | |
Project A | $485 | $0.07 |
Project B | $6522 | $0.81 |
_____
Part b)
The risk-adjusted NPV is calculated as below:
Standard deviation and coefficient of variation are both the measures of risk. A project with higher standard devation/coefficient of variation would be more risky. Therefore, project B would be treated as riskier project and project A would be considered as less risky project.
Risk-Adjusted NPV = -Initial Investment + Cash Flow Year 1/(1+Discount Rate)^1 + Cash Flow Year 2/(1+Discount Rate)^2 + Cash Flow Year 3/(1+Discount Rate)^3
Risk-Adjusted NPV (Project A) [Less Risky Project] = -7,250 + 7,050/(1+8%)^1 + 7,050/(1+8%)^2 + 7,050/(1+8%)^3 = $10918.53 or $10,919
Risk-Adjusted NPV (Project A) [Riskier Project] = -7,250 + 8,050/(1+13%)^1 + 8,050/(1+13%)^2 + 8,050/(1+13%)^3 = $11,757.28 or $11,757
____
Tabular Representation:
NPV | |
Project A | $10,919 |
Project B | $11,757 |
_____
Part c)
If it were known that Project B is negatively correlated with other cash flows of the firm whereas Project A is positively correlated, how would this affect the decision?
This would tend to reinforce the decision to select Project B. It is because Project B would become less risky as it will have lesser effect on the company's overall portfolio.
_____
Part d)
If Project B's cash flows were negatively correlated with gross domestic product (GDP), would that influence your assessment of its risk?
Yes. It is because Project B will provide more profits when the economy is down and therefore, it would be considered less risky as compared to Project A during such times. In such a case, the company would again benefit from accepting project B.