Question

In: Accounting

Juguette has decided to implement ABC. Expected product-costing data are given below: Robots Race Cars Total...

Juguette has decided to implement ABC. Expected product-costing data are given below:

Robots

Race Cars

Total

Units produced

50,000

250,000

Prime costs

$200,000

$750,000

$950,000

Machine hours

20,000

10,000

30,000

Number of setups

25

75

100

Number of moves

140

210

350

Inspection hours

1,200

2,800

4,000

Overhead costs:

    Machining

$150,000

    Setting up

80,000

    Moving materials

70,000

    Inspecting products

50,000

   

  1. Calculate the four activity rates:

Machining:

Setting up:

Moving materials:

Inspecting products:

  1. Calculate the unit costs using activity rates.

Solutions

Expert Solution

Under activity rates method, the cost are allocated on the basis of each activity by first calculating the activity rate and then multiplying the rate with the activity of the respective product.

Computation of overheads using activity rates will be:

1. Machining rate= Total Machining Overhead Costs/Total Machine hours

Therefore, Machining rate = $150,000/30,000 hours = $5 per hour

2. Setting up rate= Total Setting Up Costs/Total no of set ups

Therefore, Setting up rate = $80,000/100 set ups = $800 per Setup

3. Moving Material rate= Total Moving Material Costs/Total no of moves

Therefore, Moving Material rate = $70,000/350 Moves = $200 per moves

4. Inspecting rate= Total Inspecting Costs/Total Inspection Hours

Therefore, Inspecting rate = $50,000/4,000 Hours = $12.5 per inspection hours

Computation of unit costs using activity rates:


Related Solutions

A firm has decided to acquire as asset costing $150,000 that has an expected life 3...
A firm has decided to acquire as asset costing $150,000 that has an expected life 3 years. Straight line depreciation method is to be applied without residual value. The asset can be purchsed by borrowing or it can be leased. If leasing is used, the lessor requires 10% return, where payment to be made semi-annually at the beginning of each period. If loan, the cost of borrowing is 8% and the loan will be paid semi-annually. If tax rate is...
Project ABC has an expected return on total capital that is above required return of the...
Project ABC has an expected return on total capital that is above required return of the outside investor, and where the investor and the entrepreneum plan to had identical ownership claim. Also consider the market is competitive. Provide an example to determine the amount the investor should contribute in order to acquire a fixed percentage of the equity. (consider to return>require)
Using the ABC data, determine the total amount of overhead cost assigned to each product.
Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Activity Measure ExpectedOverhead Cost Expected Activity Labor-related Direct labor-hours $ 311,500   44,500   DLHs Purchase orders Number of orders $ 8,840   221   orders Parts management Number of part types $ 71,280   99   part types Board etching Number of boards $ 63,700   1,820...
Using the ABC data, determine the total amount of overhead cost assigned to each product.
Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools: Activity Cost Pool Activity Measure ExpectedOverhead Cost ExpectedActivity Labor-related Direct labor-hours $ 30,115 1,585 DLHs Purchase orders Number of orders $ 2,320 580 orders Product testing Number of tests $ 6,930 330 tests Template etching Number of templates $ 870 30 templates General factory Machine-hours $ 65,100 9,300 MHs  ...
Proocess Costing Instructions: Using the following data, complete the requirements given below. When you are given...
Proocess Costing Instructions: Using the following data, complete the requirements given below. When you are given amounts to assume as the answers to previous requirements, be careful to use such assumed amounts rather than your answers (in order to minimize carry-through errors). The Finishing Department of Curtis Corporation reports the following for January 2011: Production: All materials are added at the beginning of the process. Beginning work in process 20,000 units, 60% complete. Units started into production 240,000 units. Ending...
Given below is November's unit and cost data for a manuclaclaring fine that uses FIFO costing.
Given below is November's unit and cost data for a manuclaclaring fine that uses FIFO costing. Required:A] Calculate the equivalent units ford,ot materials and conversion cos.B) Prepare the COST ACCOUNTED FOR section of the cast of production report for department 2.
ABC Company manufacture one product with the following data January February Expected sales (units)          10,000          11,000...
ABC Company manufacture one product with the following data January February Expected sales (units)          10,000          11,000 Beginning inventory (units)            2,000 The company requires to have ending inventory equals to 20% of the next month sales in units. Find the need purchases for January a. 10,000 b. 10,200 c. 10,300 d. 10,450
Just Implement Inorder, Preorder and Postorder of Tree Data Structure in given code below. Thank You....
Just Implement Inorder, Preorder and Postorder of Tree Data Structure in given code below. Thank You. #include<bits/stdc++.h> using namespace std; struct Node{     int data;     Node* left;     Node* right; }; Node* createNode(int value){     Node* newNode = new Node();     newNode->data = value;     newNode->left = NULL;     newNode->right = NULL;     return newNode; } Node* insert(Node *currentNode, int value){     if(currentNode==NULL){         currentNode = createNode(value);     }else if(value <= currentNode->data){         currentNode->left = insert(currentNode->left,value);     }else{        ...
(TCO 2) Given the data below, calculate the expected return, variance, and standard deviation of the...
(TCO 2) Given the data below, calculate the expected return, variance, and standard deviation of the following company. In a recessionary economy, which is expected to occur with a 30% probability, the expected returns would be -5%. In an expanding economy with an expected probability of occurrence of 20%, the expected return would be 10%. In a normal economy, expected to occur 50% of the time, the expected return would be 5%.
Traditional Product Costing versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $636,400 consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $ 132,000 Setup hours 2,000 Materials handing 64,800 Number of moves 600 Assembly 360,000 Assembly hours 18,000 Maintenance 79,600 Maintenance hours 1,990 Total $636,400 Total direct labor hours used during the month were...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT