In: Economics
The table below contains average cost data for four
different-sized plants—1, 2, 3, and 4—which are the only four sizes
possible.
Output | Plant 1 | Plant 2 | Plant 3 | Plant 4 |
110 | $135 | $155 | $180 | $200 |
160 | 125 | 135 | 160 | 180 |
210 | 135 | 120 | 135 | 150 |
260 | 150 | 140 | 115 | 140 |
310 | 180 | 160 | 140 | 110 |
360 | 210 | 180 | 165 | 150 |
410 | 245 | 205 | 195 | 180 |
a. What is the economic capacity output for each of the four
plants?
Plant 1:
Plant 2:
Plant 3:
Plant 4:
b. In what plant and at what output is minimum long-run average
cost achieved?
Output of in (Click
to
select) 1 2 3 4 .
c. Which plant is the right size to produce an output of 210?
(Click to
select) Plant 1 Plant 2 Plant
3 Plant 4
d. Which plant is the right size to produce an output of 110?
(Click to
select) Plant 1 Plant 2 Plant
3 Plant 4
(a) The output corresponding to minimum average cost is the economic capacity of that plant.
Minimum average cost in Plant 1 is $125 corresponding to 160 units of output.
Thus, economic capacity of plant 1 is 160 units of output.
Minimum average cost in Plant 2 is $120 corresponding to 210 units of output.
Thus, economic capacity of plant 2 is 210 units of output.
Minimum average cost in Plant 3 is $115 corresponding to 260 units of output.
Thus, economic capacity of plant 3 is 260 units of output.
Minimum average cost in Plant 4 is $110 corresponding to 310 units of output.
Thus, economic capacity of plant 4 is 310 units of output.
(b)
Output | Plant 1 | Plant 2 | Plant 3 | Plant 4 | Long run average cost |
110 | 135 | 155 | 180 | 200 | 135 |
160 | 125 | 135 | 160 | 180 | 125 |
210 | 135 | 120 | 135 | 150 | 120 |
260 | 150 | 140 | 115 | 140 | 115 |
310 | 180 | 160 | 140 | 110 | 110 |
360 | 210 | 180 | 165 | 150 | 150 |
410 | 245 | 205 | 195 | 180 | 180 |
Long run average cost is the minimum average cost of producing each output among the four plants.
For example, the minimum average cost of producing 110 uints of output is $135 using plant 1.
Minimum long run average cost is achieved is $110 at 310 units of output. This cost is achieved in plant 4.
Answer: Plant 4.
Output 310
(c) Plant 2 is the right size to produce an output of 210.
becasue the average cost is minimum for 210 units of output if it is produced in plant 2.
(d) Plant 1 is the right size to produce an output of 110.
because the average cost is minimum for 110 units of output if it is produced in plant 1.
Please Hit the Like Button :)