Question

In: Accounting

Cranberry Handcraft is a manufacturer of picture frames for large retailers. Every picture frame passes through...

Cranberry Handcraft is a manufacturer of picture frames for large retailers. Every picture frame passes through two​ departments: the assembly department and the finishing department. This problem focuses on the assembly department. The​ process-costing system at Cranberry has a single​ direct-cost category​ (direct materials) and a single​ indirect-cost category​ (conversion costs). Direct materials are added when the assembly department process is​ 10% complete. Conversion costs are added evenly during the assembly​ department's process. Cranberry uses the​ weighted-average method of process costing. Consider the following data for the assembly department in April 2017​:

Physical Units (frames) Direct Materials Conversion Costs
Work in process, April 1^a 140 $ 3,190 $ 192
Started during April 2017 505
Completed during April 2017 465
Work in process, April 30^b 180
Total costs added during April 2017 $16,160 $ 9,156

a Degree of​ completion: direct​ materials, 100%; conversion​ costs, 40%.

b Degree of​ completion: direct​ materials,100​%; conversion​ costs, 15​%.

Question:

1.

Summarize total assembly department costs for April 2017​, and assign them to units completed​ (and transferred​ out) and to units in ending work in process.

2.

What issues should a manager focus on when reviewing the equivalent units​calculation?

Solutions

Expert Solution

Statement showing equivalents units using weighted average method
Flow of production Physical units Equivalent units
Direct material Conversion costs
Work in progress beginning 140
Started during current period 505
To account for 645
Completed and transferred out 465 465 465
Work in progress ending 180
(Degree of completion 100%, 15%) 180 27
Accounted for 645
Equivalent units completed till date 645 492
Statement showing Total costs, costs per equivalent unit and assignment of costs
Total Production costs Direct Material costs Conversion costs
Work in progress beginning 3,382 3,190 192
Cost incurred during April 25,316 16,160 9,156
Total Costs 28,698 19,350 9,348
Cost Incurred till date 19,350 9,348
Divide: Equivalent units of work done till date 645 492
Cost per Equivalent Unit 30 $ 19 $
Assignment of Costs:
Completed and transferred out(465) 22,785 13,950 8,835
Work in progress Ending (180) 8,820 5,400 3,420
Total costs accounted for 31,605 19,350 12,255

Working Note:

- Completed and transferred out units are given...and will multiply by cost per equivalent unit(found out in previous step). and the total of Direct material and conversion will become total costs.

2) The manager should focus on following issues

  • The Method followed for Inventory valuation. Means he should focus on whether department followed First in First Out(FIFO), First in Last Out (LIFO) or weighted average method.  
  • Degree of completion in regarding to Beginning and Ending Work-in-Progress.
  • Cost related to Beginning Work In Progress and cost incurred during the period.

Related Solutions

MacLean Handcraft is a manufacturer of picture frames for large retailers. Every picture frame passes through...
MacLean Handcraft is a manufacturer of picture frames for large retailers. Every picture frame passes through two​ departments: the assembly department and the finishing department. This problem focuses on the assembly department. The​ process-costing system at MacLean has a single​ direct-cost category​ (direct materials) and a single​ indirect-cost category​ (conversion costs). Direct materials are added when the assembly department process is​10% complete. Conversion costs are added evenly during the assembly​ department's process. MacLean uses the​ weighted-average method of process costing....
A company produces gold picture frames. The cost per picture frame is: Materials                            &nbsp
A company produces gold picture frames. The cost per picture frame is: Materials                                               $9 Packaging                                             $1 Decorations on the frame                       $5 Shipping and handling                           $1.5 Each worker earns $30,000 annually in salary and benefits. The number of workers changes based on the level of production. This means this is a variable cost. The artist who creates the designs on the picture frames is paid $25,000 annually. Senior management are paid a total of $200,000 annually. Other annual costs are:...
Funky frames makes frames. Every frame goes through 2 depts: assembly and finishing. The Beg. WIP...
Funky frames makes frames. Every frame goes through 2 depts: assembly and finishing. The Beg. WIP is 100% done for DM and 40% done for CC. The Ending WIP is 100% done for DM and 30% done for CC. Funky frames uses the weighted average method. Physical Units DM CC Beg. WIP 95 $1665 $988 Ending WIP 130 Completed 455 Costs added this year $17,640 $11,856 Compute WIP ending for the assembly dept. Compute cost of completed units for the...
Lala Corporation manufactures frames. It costs $200 to manufacture each picture frame, $50 to market each...
Lala Corporation manufactures frames. It costs $200 to manufacture each picture frame, $50 to market each picture frame, and $30 to ship each picture frame to customers. Research and developments costs are allocated at $40 per unit. Lala Corporation plans to use cost-plus pricing. Calculate the prospective selling price: if Lala Corporation marks up the manufacturing cost of the picture frames by 60% and if Lala Corporation marks up the full cost of the picture frames by 10%. Show your...
Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires 4 linear...
Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires 4 linear feet of bamboo, which costs $2.00 per foot. Each frame takes approximately 30 minutes to build, and the labor rate averages $12.00 per hour. Iguana has the following inventory policies: Ending finished goods inventory should be 40 percent of next month’s sales. Ending direct materials inventory should be 30 percent of next month’s production. Expected unit sales (frames) for the upcoming months follow: March...
Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires 4 linear...
Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires 4 linear feet of bamboo, which costs $3.00 per foot. Each frame takes approximately 30 minutes to build, and the labor rate averages $15 per hour. Iguana has the following inventory policies: Ending finished goods inventory should be 40 percent of next month’s sales. Ending raw materials inventory should be 30 percent of next month’s production. Expected unit sales (frames) for the upcoming months follow:    March...
Iguana, Inc., manufactures bamboo picture frames that sell for $30 each. Each frame requires 4 linear...
Iguana, Inc., manufactures bamboo picture frames that sell for $30 each. Each frame requires 4 linear feet of bamboo, which costs $3.00 per foot. Each frame takes approximately 30 minutes to build, and the labor rate averages $13 per hour. Iguana has the following inventory policies: Ending finished goods inventory should be 40 percent of next month’s sales. Ending direct materials inventory should be 30 percent of next month’s production. Expected unit sales (frames) for the upcoming months follow: March...
Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires 4 linear...
Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires 4 linear feet of bamboo, which costs $3.00 per foot. Each frame takes approximately 30 minutes to build, and the labor rate averages $15 per hour. Iguana has the following inventory policies: Ending finished goods inventory should be 40 percent of next month’s sales. Ending direct materials inventory should be 30 percent of next month’s production. Expected unit sales (frames) for the upcoming months follow: March...
Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires 4 linear...
Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires 4 linear feet of bamboo, which costs $2.50 per foot. Each frame takes approximately 30 minutes to build, and the labor rate averages $14 per hour. Iguana has the following inventory policies: Ending finished goods inventory should be 40 percent of next month’s sales. Ending direct materials inventory should be 30 percent of next month’s production. Expected unit sales (frames) for the upcoming months follow: March...
number 1. Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires...
number 1. Iguana, Inc., manufactures bamboo picture frames that sell for $25 each. Each frame requires 4 linear feet of bamboo, which costs $2.00 per foot. Each frame takes approximately 30 minutes to build, and the labor rate averages $13 per hour. Iguana has the following inventory policies: Ending finished goods inventory should be 40 percent of next month’s sales. Ending raw materials inventory should be 30 percent of next month’s production. Expected unit sales (frames) for the upcoming months...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT