A.John works at Company X as the Director of IT. He has recently authorized the start...

A.John works at Company X as the Director of IT. He has recently authorized the start of a new project to replace an ageing server with a new model. What is the Project Management term for John’s role within the project? Describe the key aspects of the role in your own words.

B.Vijay is responsible for overseeing a group of related projects within an organization. What is the Project Management term for Vijay’s job description? Describe the key aspects of the job description in your own words.

Solutions

Expert Solution

(ANSWER):-The Project Management term for John’s role within the project is Senior Responsible Owner .

The role of the Senior Responsible Owner in Project Managment :-

The Senior Responsible Owner is the owner Of the project and champion.Being responsible for delivery of the project SRO is required to:-

Authorise leadership and provide direction to other members of the Project Board and to the Project Manager

Be aware that all important members of the project are committed to the project and properly represented in the project's organisation structure ·

Also ensure that budget holders and resource owners are committed to the project and that the funds and other resources required are made available when required ·

Be sure that project governance arrangements which have a wide importance are put in place properly ·

Inform senior stakeholders about the current and forecast status of the project the are working on·

receive, consider and act on regular frequent reports/briefings from the Project Manager ·

Conduct round table meetings of the Project Board ·

Be sure that key satke holders of the Project Board understand their roles which is the achievement of required outcomes and benifits from the project.

Ensure that the Project is viewed and analysed on a day to day by project manager.

Be sure that the Project Manager is cautious about the limits of her/his authority and understands that issues outside those limits must be escalated to the SRO at the earliest opportunity.

The Project Management term for Vijay’s job description is Project Manager:-

Project Manager key Roles include:-

On behalf of Senior Responsible Owner the Project Manager will be liable for daily establishment of the project plan and ready to deal with issues that might affect achievement of the plan.

Project Manager require to maintain the Project Initiation Document and submit the document in front of Project Board for approval ·

Project Manager also needs to present any revised versions of the Project Plan and Business Case in front of Project Board for approval ·

Project Manager needs examine operations of the project then identify the issues and take action to deal with the issues which may act as a barrier in project achievement

Project Manager require to prepare a Risk Register/Log and manage risks properly and actively by using resources and approaches within limits of delegated authority ·


Related Solutions

Your friend, Brian, works as an Electrician working on several Commercial Buildings. He has recently finished...
Your friend, Brian, works as an Electrician working on several Commercial Buildings. He has recently finished his apprenticeship and is starting to get paying customers. He has contacted you as he knows you have been undertaking some accounting studies as part of your qualifications as he has decided to start his own Electrical Business. He wants some advice regarding his options for the structure of his new business venture, which are either a sole trader or a company. He anticipates...
13.a. The principal has no obligation to reimburse for an act that he has not authorized:...
13.a. The principal has no obligation to reimburse for an act that he has not authorized: A) true, the principal is only bound to reimburse the reasonable expenses incurred by the agent in the exercise of his functions. B) false, the principal is required to reimburse twice the expenses incurred by the agent in the performance of his duties. C) false, the principal is required to reimburse all expenses incurred by the agent in the performance of his duties, D)...
The Financial Director of your company has recently asked you to attend a conference where a...
The Financial Director of your company has recently asked you to attend a conference where a paper on Balanced Scorecards entitled ‘Linking Management Accounting with Strategy’ was presented. At the next Board meeting of the company you have been asked to: (a) Discuss what the four perspectives of a Balanced Scorecard are, and how they are translated into performance measures and targets. (b) Critically appraise the success of the application of Balanced Scorecards in business organisations and whether they are...
Andrew works at a public company called TNN Manufacturing Ltd. He has observed that the company...
Andrew works at a public company called TNN Manufacturing Ltd. He has observed that the company is trying to expand its operation in the market over the past one year. The management has heavily invested in plant and equipment over this period. Considering the high growth potential of the business, Andrew is planning to invest in this company by purchasing shares. He consulted with this friend Peter regarding this plan. After reviewing TNN Manufacturing’s balance sheet for past two years,...
Jason works at a call center for an insurance company called ABF, and he has been...
Jason works at a call center for an insurance company called ABF, and he has been answering calls regarding auto insurance. Recently, he started to attend a training program about home insurance. Upon successful completion of this training program, Jason will be able to handle home insurance questions and queries as well. Jason now will get in addition to his base salary a medical insurance, vacations, day care assistance, and spot bonus. ABF does not employ highly experienced and knowledgeable...
Amir works for a foreign company that has engineering offices in Canada. He notices that his...
Amir works for a foreign company that has engineering offices in Canada. He notices that his boss has hired several men rather than more qualified women. He asks his boss about it and the boss explains that he doesn’t want women in the office because they are distracting to the male engineers. Amir knows that such a policy violates the Ontario Human Rights Code, but doesn’t want to upset his boss. The office in Canada is very small and he...
Joe is a company director in a proprietary company. He is proposing to put a resolution...
Joe is a company director in a proprietary company. He is proposing to put a resolution to his company that it buy out the smaller holdings. Joe reasons that there are a number of quite large shareholders and many of the smaller members have little interest in the company. Joe doesn't want to force any member to sell their shares but would like to clean up the register by buying out the smaller holdings. Required:advice Joe on the legal implications...
MF has decided to start saving for his retirement. He will start at the end of...
MF has decided to start saving for his retirement. He will start at the end of this year saving $2000 a year for 10 years and $5,000 a year for the next 15 years after that. When he has finished with this period, he will still have 10 years left until he retires. The interest rate before retirement is 9.5% interest per year. After he retires the expected interest rate is 8%. If he wants to withdraw from his account...
An HR manager works at a company in a state that recently legalized the use of...
An HR manager works at a company in a state that recently legalized the use of marijuana for medical purposes. The company restricts the use of drug testing to employees on a probable-cause basis, and tests are given to employees only when they have accidents, engage in unsafe job behavior, or show signs of impaired judgment. Assuming the HR manager wants to avoid discriminating against employees with medical conditions who are legitimate cardholders for the use of medical marijuana, what...
A) The company where you work as Finance Director works on two different projects to increase...
A) The company where you work as Finance Director works on two different projects to increase sales volume and efficiency. Your estimations and expectations regarding the projects are as follows. After you have proven mathematically which project you choose why? please explain your decision Project A: You estimate that the initial investment cost required for the new machinery will be $2,300,000. You predict that the useful life of the new machinery will be 6 years. You expect the new machine...