The total factory overhead for Bardot Marine Company is budgeted for the year at $816,000, divided...

The total factory overhead for Bardot Marine Company is budgeted for the year at $816,000, divided into two departments: Fabrication, $648,000, and Assembly, $168,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require four direct labor hours in Fabrication and three direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and three direct labor hours in Assembly. Each product is budgeted for 4,000 units of production for the year.

If required, round all per unit answers to the nearest cent.

a. Determine the total number of budgeted direct labor hours for the year in each department.

Fabrication direct labor hours
Assembly direct labor hours

b. Determine the departmental factory overhead rates for both departments.

Fabrication $ per dlh
Assembly $ per dlh

c. Determine the factory overhead allocated per unit for each product using the department factory overhead allocation rates.

Speedboat: $ per unit
Bass boat: $ per unit

Solutions

Expert Solution

Answer:

a. Determine the total number of budgeted direct labor hours for the year in each department

Fabrication 24000 direct labor hours
Assembly 24000 direct labor hours

Fabrication :-

Speedboats = 4 hour * 4000 = 16000 hours

Bass boats = 2 hour * 4000 = 8000 hours

Total = 8000 + 16000= 24000 hours

Assembly:-

Speedboats = 3 hour * 4000 = 12000 hours

Bass boats = 3 hour * 4000 = 12000 hours

Total = 12000 + 12000 = 24000 hours

b. Determine the departmental factory overhead rates for both departments.

Fabrication $27 per dlh
Assembly $7 per dlh

Fabrication :-

Overhead/Direct labor hours

= $648000/24000 DL hours = $27

Assembly :-

Overhead/Direct labor hours

$168000/24000 DL hours = $7

c. Determine the factory overhead allocated per unit for each product using the department factory overhead allocation rates.

Speedboat: $129 per unit
Bass boat: $75 per unit

Speedboat:-

Fabrication = $27 * 4 hour = $108

Assembly = $7 * 3 hours = $21

Total = $108 + $21 = $129

Bass boat:-

Fabrication = $27 * 2 hour = $54

Assembly = $7* 3 hours = $21

Total = $54+ $21= $75


Related Solutions

total factory overhead for Bardot Marine Company is budgeted for the year at $778,050, divided into...
total factory overhead for Bardot Marine Company is budgeted for the year at $778,050, divided into four activities: fabrication, $357,000; assembly, $147,000; setup, $148,050; and inspection, $126,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows: Fabrication Assembly Setup Inspection Speedboat 5,250 dlh 15,750 dlh 38 setups 66 inspections Bass boat 15,750 5,250 277 459 21,000 dlh 21,000 dlh 315 setups 525 inspections Each product...
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,262,000, divided...
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,262,000, divided into two departments: Fabrication, $990,000, and Assembly, $272,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require three direct labor hours in Fabrication and one direct labor hour in Assembly. The bass boats require two direct labor hours in Fabrication and three direct labor hours in Assembly. Each product is budgeted for 8,000 units of production for the year....
The total factory overhead for Bardot Marine Company is budgeted for the year at $522,500, divided...
The total factory overhead for Bardot Marine Company is budgeted for the year at $522,500, divided into two departments: Fabrication, $190,000, and Assembly, $332,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and four direct labor hours in Assembly. The bass boats require one direct labor hour in Fabrication and three direct labor hours in Assembly. Each product is budgeted for 5,000 units of production for the year....
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,078,500, divided...
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,078,500, divided into four activities: fabrication, $490,000; assembly, $228,000; setup, $194,250; and inspection, $166,250. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows: Fabrication Assembly Setup Inspection Speedboat 8,750 dlh 28,500 dlh 63 setups 109 inspections Bass boat 26,250 9,500 462 766 35,000 dlh 38,000 dlh 525 setups 875 inspections Each...
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,144,800, divided...
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,144,800, divided into four activities: fabrication, $512,000; assembly, $180,000; setup, $244,800; and inspection, $208,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows: Fabrication Assembly Setup Inspection Speedboat 8,000 dlh 22,500 dlh 58 setups 100 inspections Bass boat 24,000 7,500 422 700 32,000 dlh 30,000 dlh 480 setups 800 inspections Each...
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for...
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for the year at $1,305,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboat and bass boat each require six direct labor hours for manufacture. Each product is budgeted for 7,500 units of production for the year. When required, round all per unit answers to the nearest cent. a. Determine the total number of budgeted direct labor hours for the year....
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for...
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for the year at $1,100,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboat and bass boat each require five direct labor hours for manufacture. Each product is budgeted for 8,000 units of production for the year. When required, round all per unit answers to the nearest cent. a. Determine the total number of budgeted direct labor hours for the year....
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for...
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for the year at $1,710,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboat and bass boat each require four direct labor hours for manufacture. Each product is budgeted for 9,000 units of production for the year. When required, round all per unit answers to the nearest cent. a. Determine the total number of budgeted direct labor hours for the year....
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $519,000, divided into two departments: Fabrication, $451,500, and Assembly, $67,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require four direct labor hours in Fabrication and one direct labor hour in Assembly. The bass boats require three direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 3,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $576,000, divided into two departments: Fabrication, $423,000, and Assembly, $153,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and two direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 6,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT