Question

In: Accounting

At the high and low levels of activity during the month, direct labor hours are 90,000...

At the high and low levels of activity during the month, direct labor hours are 90,000 and 40,000, respectively. The related costs are $165,000 and $100,000. What are the fixed and variable costs at any level of activity?

Solutions

Expert Solution

Answer- Variable Cost per hour = $1.3 per hour.

Total variable cost at 90000 direct labor hours = $117000.

Total fixed costs = $48000.

Explanation:-High-Low Method:-

Variable Cost per Unit

Variable cost per unit (b) is calculated using the following formula:

Variable cost per unit = (Y2-Y1)/(X2-X1)

Where,
y2 is the total cost at highest level of activity;
y1 is the total cost at lowest level of activity;
x2 are the number of units/miles/ labor ,machine hours etc. at highest level of activity; and
x1 are the number of units/miles/ labor, machine hours etc. at lowest level of activity

The variable cost per unit is equal to the slope of the cost volume line (i.e. change in total cost ÷ change in number of machine hours).

Total Fixed Cost

Total fixed cost (a) is calculated by subtracting total variable cost from total cost, thus:

Total Fixed Cost = (y2 – b)*x2 = (y1 – b*x1)

We have,
at highest activity: x2 = 90000 hours; y2 = $165000
at lowest activity: x1 = 40000 hours; y1 = $100000

Variable Cost per labor hour = ($165000 - $100000) /(90000 hours − 40000 hours)  

= $65000/50000 hours

= $1.3 per hour
Total variable cost on 90000 hours = 90000 hours*$1.3 per hour

= $117000

Total fixed costs= $165000 - $117000

= $48000


Related Solutions

Activity Driver Driver Frequency Cost of Activity Direct Labor Direct Labor Hours                   50,000 $ 1,250,000.00...
Activity Driver Driver Frequency Cost of Activity Direct Labor Direct Labor Hours                   50,000 $ 1,250,000.00 Vacuuming Machine Hours                      2,000 $       62,000.00 Set-up Job                      5,000 $     200,000.00 Testing Tests made                      5,000 $       60,000.00 Customer service Orders taken                      1,200 $       30,000.00 Invoicing Invoices mailed                      2,400 $       48,000.00 Total $ 1,650,000.00 Activity Pool Opening Pump Repair Pool Cleaning Materials 350 1000 50 Direct Labor Hours 15 40 2 Vacuuming 3 0 2 Set-up 1 1 1 Testing...
Johnson Company applies overhead to products using direct labor hours as the activity level. During 2019,...
Johnson Company applies overhead to products using direct labor hours as the activity level. During 2019, Johnson Company had the following estimated costs: Direct materials .................... $278,000 Direct labor ........................ 255,000 (15,000 hours expected) Advertising ......................... 37,000 Rent on factory building ............ 38,000 Depreciation .................... ... 60,000 Indirect materials .................. 20,000 Sales commissions ................... 40,000 Production supervisor's salary ...... 50,000 Insurance on factory equipment ...... 18,000 CEO's salary ........................ 95,000 The following additional information is available: 1. 30% of the...
MAnufacturing overhead is applied on the basis of direct labor hours. The direct labor hours for...
MAnufacturing overhead is applied on the basis of direct labor hours. The direct labor hours for the period are 500 and the estimated manufacturing overhead is 2000. actual direct labor hours were 160 and actual overhead was 1000. Compute the manufacturing overhead applied during this period.
Overhead is applied on the basis of direct labor hours. Three direct labor hours are required...
Overhead is applied on the basis of direct labor hours. Three direct labor hours are required for each product unit. Planned production for the period was set at 8,000 units. Manufacturing overhead for the period is budgeted at $204,000, of which 30 percent is fixed. The 26,200 hours worked during the period resulted in production of 8,500 units. Manufacturing overhead cost incurred was $220,500. Required: a. Calculate the overhead spending variance: b. Calculate the overhead efficiency variance: c. Calculate the...
James Corp. applies overhead on the basis of direct labor hours. For the month of May,...
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 36,000 Budgeted overhead Variable overhead costs Indirect materials $ 21,600 Indirect labor 36,000 Power 7,200 Maintenance 3,600 Total variable costs 68,400 Fixed overhead costs Rent of factory building 20,000 Depreciation—Machinery...
James Corp. applies overhead on the basis of direct labor hours. For the month of May,...
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 26,000 Budgeted overhead Variable overhead costs Indirect materials $ 15,600 Indirect labor 26,000 Power 7,800 Maintenance 2,600 Total variable costs 52,000 Fixed overhead costs Rent of factory building 22,000 Depreciation—Machinery...
James Corp. applies overhead on the basis of direct labor hours. For the month of May,...
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 30,000 Budgeted overhead Variable overhead costs Indirect materials $ 21,000 Indirect labor 30,000 Power 6,000 Maintenance 3,000 Total variable costs 60,000 Fixed overhead costs Rent of factory building 14,000 Depreciation—Machinery...
James Corp. applies overhead on the basis of direct labor hours. For the month of May,...
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 27,000 Budgeted overhead Variable overhead costs Indirect materials $ 16,200 Indirect labor 27,000 Power 5,400 Maintenance 5,400 Total variable costs 54,000 Fixed overhead costs Rent of factory building 23,000 Depreciation—Machinery...
James Corp. applies overhead on the basis of direct labor hours. For the month of May,...
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 27,000 Budgeted overhead Variable overhead costs Indirect materials $ 16,200 Indirect labor 27,000 Power 5,400 Maintenance 5,400 Total variable costs 54,000 Fixed overhead costs Rent of factory building 23,000 Depreciation—Machinery...
James Corp. applies overhead on the basis of direct labor hours. For the month of May,...
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 20,000 Budgeted overhead Variable overhead costs Indirect materials $ 15,000 Indirect labor 20,000 Power 5,000 Maintenance 2,000 Total variable costs 42,000 Fixed overhead costs Rent of factory building 15,000 Depreciation—Machinery...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT