In: Accounting
James Corp. applies overhead on the basis of direct labor hours.
For the month of May, the company planned production of 10,000
units (80% of its production capacity of 12,500 units) and prepared
the following overhead budget:
Operating Levels | |||
Overhead Budget | 80% | ||
Production in units | 10,000 | ||
Standard direct labor hours | 27,000 | ||
Budgeted overhead | |||
Variable overhead costs | |||
Indirect materials | $ | 16,200 | |
Indirect labor | 27,000 | ||
Power | 5,400 | ||
Maintenance | 5,400 | ||
Total variable costs | 54,000 | ||
Fixed overhead costs | |||
Rent of factory building | 23,000 | ||
Depreciation—Machinery | 10,800 | ||
Supervisory salaries | 14,800 | ||
Total fixed costs | 48,600 | ||
Total overhead costs | $ | 102,600 | |
During May, the company operated at 90% capacity (11,250 units) and
incurred the following actual overhead costs:
Overhead Costs | |||
Indirect materials | $ | 16,200 | |
Indirect labor | 29,875 | ||
Power | 6,075 | ||
Maintenance | 6,710 | ||
Rent of factory building | 23,000 | ||
Depreciation—Machinery | 10,800 | ||
Supervisory salaries | 18,200 | ||
Total actual overhead costs | $ | 110,860 | |
2. Compute the overhead volume variance.
3. Prepare an overhead variance report at the
actual activity level of 11,250 units.
Ans.1: Computation of Overhead volume variance |
||||
Particulars |
Plant Capacity |
Budget Variance |
Remarks |
|
Overhead Budget |
80% |
90% |
||
Production Units |
10000 |
11250 |
-1250 |
i.e., For 80% = 10000 units then for 90% = 10000/0.80 X 0.90 = 11250 units |
Standard Direct Labour hours |
27000 |
30375 |
-3375 |
For 10000 units = 27000 hrs then Direct labour hour per unit =
27000/10000 = 2.70 hr |
Budget Overhead |
||||
Variable Overhead costs |
||||
Indirect Materials |
16,200.00 |
18,225.00 |
-2025 |
For 10000 units = $16,200, Hence 11,250 units = $16,200/10000 X 11250 |
Indirect Labour |
27,000.00 |
30,375.00 |
-3375 |
Labour directly attributable to no.of hours worked, for 27000
hrs = $27000 labour cost; |
Power |
5,400.00 |
6,075.00 |
-675 |
Power costs directly attributable to no.of man hours worked, for
27000 labour hrs = $5,400 power cost; |
Maintenance |
5,400.00 |
6,075.00 |
-675 |
Maintenance costs directly attributable to no.of man hours
worked, for 27000 labour hrs = $5,400 maintenance costs; |
Total Overhead Costs |
54,000.00 |
60,750.00 |
(6,750.00) |
|
Fixed overhead costs |
||||
Rent of Factory Building |
23,000.00 |
23,000.00 |
- |
Building rent remain same and no additional costs despite of increase in production. |
Depreciation - Machinery |
10,800.00 |
10,800.00 |
- |
Plant working in its normal capacity, hence there is no additional wear and tear |
Supervisory Salaries |
14,800.00 |
14,800.00 |
- |
This costs shall not be effect despite of increase or decrease in production. |
Total Fixed Costs |
48,600.00 |
48,600.00 |
- |
|
Total Overhead costs |
102,600.00 |
109,350.00 |
(6,750.00) |
|
Ans.2: Overhead variance report at the actual activity level of 11,250 units |
||||
Particulars |
Plant Capacity |
Variance |
Explanation |
|
Overhead Budget |
Budget |
Actual |
||
Production Units |
11250 |
11250 |
- |
|
Overheads |
||||
Variable Overhead costs |
||||
Indirect Materials |
18,225.00 |
16,200.00 |
(2,025.00) |
Decrease in material costs |
Indirect Labour |
30,375.00 |
29,875.00 |
(500.00) |
Decrease in labour costs |
Power |
6,075.00 |
6,075.00 |
- |
Nil |
Maintenance |
6,075.00 |
6,710.00 |
635.00 |
Increase in Maintenance costs |
Total Overhead Costs |
60,750.00 |
58,860.00 |
(1,890.00) |
|
Fixed overhead costs |
||||
Rent of Factory Building |
23,000.00 |
23,000.00 |
- |
Nil |
Depreciation - Machinery |
10,800.00 |
10,800.00 |
- |
Nil |
Supervisory Salaries |
14,800.00 |
18,200.00 |
(3,400.00) |
Increase in supervisory salaries |
Total Fixed Costs |
48,600.00 |
52,000.00 |
(3,400.00) |
|
Total Overhead costs |
109,350.00 |
110,860.00 |
(5,290.00) |