In: Other
7)
Correct answer is D) Taking orders from customers
Taking orders from customers is a value-added work
8)
correct answer is D) Labor content
Labor content can NOT be used to determine the extent to which an operation is lea
9)
probability of catching a defect = 0.9*0.8*0.7*0.9 = 0.4536
10)
Correct answer is A) the expected completion time of the project
the expected completion time of the project is not shown in Gantt chart
11)
Correct answer is B) The majority of problems can be explained by a few root causes
Pareto chart says 80% of issues are created by 20% root causes
12)
There are 20 stations between station 10 and last station as cycle time is 5 minutes so information turnaround time = 20*5 = 100 minutes