In: Electrical Engineering
Resolve Example 6.20, except with the generation at bus 2 set to a fixed value (i.e., modeled as off of AGC). Plot the variation in the total hourly cost as the generation at bus 2 is varied between 0 to 200 MW in 5-MW steps, resolving the economic dispatch at each step. What is the relationship between bus 2 generation at the minimum point on this plot and the value from economic dispatch in Example 6.20? Assume a load scalar of 1.0
Example 6.20: PowerWorld Simulator case Example 6_20 uses a
five-bus, three-generator lossless case to show the interaction
between economic dispatch and the transmission system (see Figure
6.19). The variable operating costs for each of the units are given
by C1 = 10P1 + 0.016P 1 Square $yhr C2 =8P2 + 0.018P2 Square $yhr
C4 = 12P4 + 0.018P 4 Square $yhr where P1, P2, and P4 are the
generator outputs in megawatts. Each generator has minimum/maximum
limits of 100 <=P1 <=400 MW 150 <=P2 <= 500 MW 50 <=
P4 <=300 MW In addition to solving the power flow equations,
PowerWorld Simulator can simultaneously solve the economic dispatch
problem to optimally allocate the generation in an area. To turn on
this option, select Case Information, Aggregation,
Areas… to view a list of each of the control areas in a case (just
one in this example). Then toggle the AGC Status field to ED. Now
anytime the power flow equations are solved, the generator outputs
are also changed using the economic dispatchInitially, the case has
a total load of 392 MW with an economic dispatch of P1 =141 MW, P2
= 181, and P4 = 70, and an incremental operating cost, l, of 14.52
$?MWh. To view a graph showing the incremental cost curves for all
of the area generators, right-click on any generator to display the
generator’s local menu, and then select All Area Gen IC Curves
(right-click on the graph’s axes to change their scaling). To see
how changing the load impacts the economic dispatch and power flow
solutions, first select Tools, Play to begin the simulation. Then,
on the oneline, click on the up/down arrows next to the Load Scalar
field. This field is used to scale the load at each bus in the
system. Notice that the change in the Total Hourly Cost field is
well approximated by the change in the load multiplied by the
incremental operating cost. Determine the maximum amount of load
this system can supply without overloading any transmission line
with the generators dispatched using economic dispatch.