In: Civil Engineering
Environmental Engineering
desalination techologies
Quesition: By choosing one of the thermal desalination facilities installed worldwide; its purpose, location, technology, capacity and quality values of feed, product and concentrate streams etc. Prepare a report about the details.
Carlsbad Desalination Project, San Diego, California
PLANT TYPE
Desalination plant
LOCATION
Carlsbad, San Diego, California
PLANT PROPOSED
1998
CONSTRUCTION COMMENCED
November 2009
COMPLETION
2016
INTAKE WATER SOURCE
Pacific Ocean
PLANT CAPACITY
189,000m³/day (50MGD)
PROJECT DEVELOPER AND FINANCIER
Poseidon Resources Corporation
ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC) CONTRACTORS
American Water, JR Filanc Construction Company and PBS&J and Acciona Agua and its partners
The Carlsbad desalination project in San Diego County, California US, is the largest desalination plant in the western hemisphere. The $922m project is the first large-scale desalination plant on the West Coast, privately financed and developed by the Poseidon Resources Corporation (Poseidon).
The project includes a desalination plant, a pumping station,
product water storage and a ten-mile finished water conveyance
pipeline.
Poseidon leased a four-acre site adjacent to the existing Encina
Power Station site, owned by Cabrillo Power, for 60 years for the
desalination plant. On the south of the plant site is the Agua
Hedionda Lagoon of the Pacific Ocean.
The plant produces 50 million gallons of desalinated seawater (MGD) a day and provide 10% of the total drinking water needed by San Diego. It supplies 56,000 acre-feet (approximately 2,440 cubic feet) of water a year, sufficient for 300,000 people.
The water from this plant is purchased by the Carlsbad water agencies, and is supplemented with imported water from San Diego County Water Authority (SDCWA), the region’s water supplier.
Bidding for EPC of the project was made in February 2006 and the contract awarded in 2007.
In 2008, the plant received approvals from the State Lands Commission and the California Coastal Commission. In May 2009, the Regional Water Quality Control Board approved the plant’s construction. In September 2009, the city of Carlsbad approved the desalination project with minor changes to the main plant building and pipeline network to the certified EIR.
Construction of the first phase of the Carlsbad desalination plant started in November 2009.
In January 2010, the project was allocated $530m in private activity bonds (PABs) by the California Debt Limitation Allocation Committee (CDLAC). Financing for the project was closed in December 2012 to clear the way for the start of construction.
The plant generated 2,300 jobs during the construction phase and 575 jobs during operation. It began supplying desalinated water in December 2015.
Utilities and companies involved with California’s project-
The Carlsbad desalination project was developed as a public-private partnership between local utilities and municipalities in San Diego County and Poseidon Resources. Poseidon has 30-year contracts, with an option for an extension, for long-term, fixed-price water purchase from nine public water agencies in San Diego.
"The plant produces 50 million gallons of desalinated seawater (MGD) a day."
The water agencies include Carlsbad Municipal Water District, Rincon del Diablo Municipal Water District, Olivenhain Municipal Water District, Vallecitos Water District, Sweetwater Authority, Valley Centre Municipal Water District, Santa Fe Irrigation District, Rainbow Municipal Water District and city of Oceanside Municipal Water District.
Engineering, procurement and construction (EPC) contracts for the first phase of the project were awarded to American Water, JR Filanc Construction Company, PBS&J, Acciona Agua and its partners. Poseidon selected Barclays Capital as the financial adviser for the Carlsbad desalination project in June 2009.
The engineering, procurement and construction (EPC) contracts for the second phase of the project were awarded to the joint venture (JV) of Kiewit Shea Desalination. The JV comprises Kiewit Corporation and J.F. Shea Construction. The seawater process plant was designed by IDE Technologies in collaboration with the JV.
Operation and maintenance (O&M) of the plant is being carried out by IDE Technologies for a period of 30 years.
Need for the Carlsbad desalination plant
Approximately 30% of the California state water project (SWP) goes to San Diego, but the county still imports 90% of its water from the Bay-Delta and the Colorado River. California has seen a prolonged drought, along with changes in its environmental pattern and population growth, meaning that tapering sources and stringent water treatment requirements are increasing the cost of traditional water sources.
The Carlsbad desalination project aims to provide a local source of potable water with an increased quality level (between 250mg and 350mg) and reliability by using economically feasible technology.
In 1998, the Carlsbad officials in San Diego teamed up with Poseidon Resources to secure a sustainable future water supply in the region. The public-private-partnership has since then been working towards construction of the 50MGD plant.
The Carlsbad desalination plant underwent ten years of planning and was in California’s permitting process for five years, until the Carlsbad Municipal Water District signed a water purchase agreement with Poseidon in September 2004.
Design of the Californian desalination plant
The desalination plant construction involved demolishing the fuel storage tank of the power plant, which was not in use. The building houses the reverse osmosis (RO) system, chemical storage and pumps for water treatment and product water.
"Poseidon leased a four-acre site adjacent to the existing Encina Power Station site, owned by Cabrillo Power, for 60 years."
To obtain permission from the city of Carlsbad, the design of
the building was rotated, a proposed on-site underground pipeline
and off-site pipelines routes were finalised. The new pipeline
routes are 1.2 miles shorter than the original proposal pipeline of
17 miles. The pipe diameter of the delivery system is in the range
of 24in in the downstream portions and 48 inches in the upstream
portions.
The plant’s compact design reduces its physical footprint. It was
built following LEED programme guidelines and is fully automated to
reduce its impact on the environment.
The plant incorporates a solar power generation system on its approximately 50,000ft² rooftop, pressure exchanger-based energy recovery system and variable frequency drives and energy efficient motors for all pumps.
About 80% of the pipes for the plant were made of high-density polyethylene (HDPE) and fibreglass-reinforced plastic (FRP) materials for energy-saving seawater conveyance.
Water pre-treatment and treatment technology
Pre-treatment of the water uses either granular media filtration or membrane filtration technology, along with a micro-screen filtration process. A chemically enhanced backwash of the pre-treatment membranes is conducted every day using acid, chlorine and base conditioning of membrane modules.
The solution is treated before disposal at the Encina Water Pollution Control Facility (EWPCF).
"The Carlsbad desalination plant underwent ten years of planning and was in California’s permitting process for five years."
Seawater from the Encina power plant, used for cooling boilers in operation, is diverted to the desalination facility through an existing cooling water discharge system. The source water is pre-treated and processed using RO membranes for producing the drinking water. The treated water is temporarily stored in on-site facilities before its transmission to the regional distribution systems.
The RO system is equipped with 12 operational treatment trains and one auxiliary train. They are arranged discretely and have a total installed water production capacity of 54MGD. The design production capacity averages 50MGD annually.
Filter effluent transfer pumps are used for conveying the pre-treatment filter effluent through the RO system cartridge filters. The effluent is forced into high-pressure RO feed pumps that feed the pre-treated seawater to the reverse osmosis membrane treatment trains.
The 13 high-speed RO feed pumps (one for each RO treatment train) enable the water and salt separation. They also have energy-efficient shafts. The reverse osmosis membrane was manufactured completely within San Diego County.
The water from the RO system is disinfected using chloramination, the process of adding chlorine and ammonia. The biological growth in transmission pipelines and the reservoirs of the distribution system is controlled by forming chloramines in the water. Further, the water is chloraminated with the application of ammonia and sodium hypochlorite.
The water at the delivery level has a chloramine residual concentration in the range of 2mg/l to 2.5mg/l. The produced water is conditioned with carbon dioxide and lime to avoid corrosion of the delivery facilities with the product water. Water from the RO system is pumped to the off-site water distribution system.
One gallon of potable water of water produced in the RO membrane separation process produces a gallon of concentrate. The concentrate is twice as saline as seawater (67,000ppm). The water is conveyed to the cooling water discharge canal of the power plant.
The concentrate is blended with the cooling water of the power plant before being discharged in to the Pacific Ocean through the power plant’s discharge canal. All the membranes of the RO train are cleaned twice a year to remove the accumulated fouling materials and particulates.
Environmental aspects of the Carlsbad desalination project
The Carlsbad plant conserves local and regional water and complements the recycling programmes. The project also dedicates 15 acres of lagoon and oceanfront for improving public access and recreation. The project enhances, restores and maintains the marine environment.
Poseidon also developed a voluntary greenhouse gas reduction and energy minimisation plan covering the reduction of carbon emissions according to California Coastal Commission’s coastal development permit.
In May 2006, the American Academy of Environmental Engineers awarded the Carlsbad pilot plant the Grand Prize for Excellence in Environmental Engineering Research.
In June 2006, Carlsbad City Council certified the environmental impact report (EIR) of the desalination plant, through the independent preparation of consulting firm Dudek & Associates.