Question

In: Finance

Problem 9-13 Project Evaluation [LO 2] Kolby’s Korndogs is looking at a new sausage system with...

Problem 9-13 Project Evaluation [LO 2]

Kolby’s Korndogs is looking at a new sausage system with an installed cost of $753,000. This cost will be depreciated straight-line to zero over the project’s six-year life, at the end of which the sausage system can be scrapped for $96,000. The sausage system will save the firm $184,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $42,000.
  
What is the aftertax salvage value of the equipment? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)
  

Aftertax salvage value            $

What is the annual operating cash flow? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)
  
OCF            $

If the tax rate is 35 percent and the discount rate is 7 percent, what is the NPV of this project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
  
NPV            $

Solutions

Expert Solution

Time line 0 1 2 3 4 5 6
Cost of new machine -753000
Initial working capital -42000
=Initial Investment outlay -795000
Savings 184000 184000 184000 184000 184000 184000
-Depreciation Cost of equipment/no. of years -125500 -125500 -125500 -125500 -125500 -125500
=Pretax cash flows 58500 58500 58500 58500 58500 58500
-taxes =(Pretax cash flows)*(1-tax) 38025 38025 38025 38025 38025 38025
+Depreciation 125500 125500 125500 125500 125500 125500
=after tax operating cash flow 163525 163525 163525 163525 163525 163525
reversal of working capital 42000
+After tax salvage cash flow =selling price* ( 1 -tax rate) 62400
+Tax shield on salvage book value =Salvage value * tax rate 0
=Terminal year after tax cash flows 104400
Total Cash flow for the period -795000 163525.00 163525.0000 163525.00 163525 163525 267925
Discount factor= (1+discount rate)^corresponding period 1 1.07 1.1449 1.225043 1.310796 1.4025517 1.5007304
Discounted CF= Cashflow/discount factor -795000 152827.1028 142829.068 133485.1103 124752.44 116591.07 178529.74
NPV= Sum of discounted CF= 54014.53

Related Solutions

Kolby’s Korndogs is looking at a new sausage system with an installed cost of $675,000. The...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $675,000. The asset qualifies for 100 percent bonus depreciation and can be scrapped for $89,000 at the end of the project’s 5-year life. The sausage system will save the firm $191,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $43,000. If the tax rate is 24 percent and the discount rate is 8 percent, what is...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $882,000. This...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $882,000. This cost will be depreciated straight-line to zero over the project’s seven-year life, at the end of which the sausage system can be scrapped for $97,000. The sausage system will save the firm $185,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $43,000. If the tax rate is 30 percent and the discount rate is...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $695,000. This...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $695,000. This cost will be depreciated straight-line to zero over the project’s 5-year life, at the end of which the sausage system can be scrapped for $93,000. The sausage system will save the firm $199,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $51,000. If the tax rate is 23 percent and the discount rate is...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $720,000. This...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $720,000. This cost will be depreciated straight-line to zero over the project’s 6-year life, at the end of which the sausage system can be scrapped for $98,000. The sausage system will save the firm $209,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $61,000. What is the aftertax salvage value of the equipment? (Do not round...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $680,000. This...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $680,000. This cost will be depreciated straight-line to zero over the project’s 5-year life, at the end of which the sausage system can be scrapped for $90,000. The sausage system will save the firm $193,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $45,000. If the tax rate is 25 percent and the discount rate is...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $514,000. This...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $514,000. This cost will be depreciated straight-line to zero over the project’s four-year life, at the end of which the sausage system can be scrapped for $102,000. The sausage system will save the firm $190,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $48,000. PLEASE SHOW WORK WITHOUT EXCEL    What is the aftertax salvage value...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $720,000. The...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $720,000. The asset qualifies for 100 percent bonus depreciation and can be scrapped for $98,000 at the end of the project’s 5-year life. The sausage system will save the firm $209,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $61,000. If the tax rate is 23 percent and the discount rate is 9 percent, what is...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $655,000. This...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $655,000. This cost will be depreciated straight-line to zero over the project’s five-year life, at the end of which the sausage system can be scrapped for $107,000. The sausage system will save the firm $195,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $53,000. What is the aftertax salvage value of the equipment? Aftertax salvage value...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $745,000. This...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $745,000. This cost will be depreciated straight-line to zero over the project’s 7-year life, at the end of which the sausage system can be scrapped for $103,000. The sausage system will save the firm $219,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $71,000. a)What is the aftertax salvage value of the equipment? Aftertax salvage value=...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $665,000. This...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $665,000. This cost will be depreciated straight-line to zero over the project’s 5-year life, at the end of which the sausage system can be scrapped for $87,000. The sausage system will save the firm $187,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $39,000. If the tax rate is 22 percent and the discount rate is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT