Question

In: Civil Engineering

Given a strip commercial development near Columbia, SC, with the following characteristics: overland flow length =...

  1. Given a strip commercial development near Columbia, SC, with the following characteristics: overland flow length = 180 ft on 2.1% grade over asphalt cover (n=0.011); shallow concentrated flow length of 1000 ft on 1.8% grade (paved gutter); drainage area = 5 acres; runoff coefficient = 0.60

  1. Sheet flow travel time (minutes) =                           
  2. Shallow concentrated flow travel time (minutes) =                              
  3. Watershed time of concentration (minutes) =                         
  4. 10-year design rainfall intensity (inches/hour) =                                 
  5. Runoff peak (cfs) for 10-year design rainfall =                                   

  1. Given a 28-acre watershed with the following land use mix: 8 acres of SFR (38% impervious) on HSG-B soils, 5 acres of SFR (30% impervious) on HSG-C soils, and 15 acres of open space (park and playground) in fair condition on HSG-C soils. Watershed time of concentration is 21 minutes. The design return period 24-hour rainfall depth is 5.25 inches.

  1. The runoff-weighted average curve number (CN) =                             
  2. The area-weighted unit hydrograph peak rate factor (PRF) =                                                                 

c)    The runoff volume from a rainfall of 3.25 inches (watershed inches) =                             

d)   The runoff volume from a rainfall of 0.47 inches (watershed inches) =                             

Solutions

Expert Solution

Ans a) We know, time of concentration for sheet flow can be given as,

Tc = 0.007 (NL)^0.8 / [(P)^0.5 (S)^0.4)]

where, N =Manning roughness coefficient = 0.011

L = Length = 180 ft

P = 2 yr 24 hr rainfall = 4.2 in/hr as per IDF curve of Columbia,SC

S = Slope = 2.1 % or 0.021

Putting values,

=> Tc = 0.007(0.011x180)^0.8 / [(4.2)^0.5 x (0.021)^0.4)]

=> Tc = 0.027 hr or 1.66 min

Ans b) According to TR-55 ,time of concentration for shallow concentrated flow can be given as,

Tc' = L / V

where, V = Velocity in ft/s

For paved gutter flow, V = 20.328 S^0.5

=> V = 20.328 (0.018)^0.5 = 2.72 ft/s

=> Tc' = 1000 ft / 2.72 ft/s = 368 sec or 6.12 min

Ans c) Total time of concentration of watershed ,T

T= Tc + Tc'

=> T = 1.66 + 6.12 = 7.78 min

Ans d) According to IDF curve of Columbia,SC rainfall intensity for T = 7.78 min and 10 yr design rainfall , i = 6.6 in/hr

Ans e) According to Rational method, peak discharge (Qp) ,

Qp = C i A

where, C = Runoff coefficient = 0.60

i = Rainfall intensity = 6.6 in/hr

A = Drainage area = 5 acres

Putting values,

=> Qp = 0.60 x 6.6 x 5

    => Qp = 19.8 cfs


Related Solutions

Calculate the time of concentrations (or overland flow) for the two sub-areas of a watershed given...
Calculate the time of concentrations (or overland flow) for the two sub-areas of a watershed given below by multiple applicable methods (at least 3). Compare your answers for each method and watershed and discuss which may be the most accurate and why. Sub Area Area (acres) Impervious Acres Avg. Surface Slope (%) Runoff Coefficient Distance to Inlet Residential & small residences 52.6 10.5 3.0 0.42 1800 Small Business 14.0 6.3 4.5 0.66 850
The stormwater system of a given site includes the surface overland flow which exits by a...
The stormwater system of a given site includes the surface overland flow which exits by a rectangular concrete channel to (Manning‘s n = 0.015) drain it. The drainage channel is 100 m long, 20 cm wide, and has a longitudinal slope of 0.6%. The catchment surface of 1950 m2 has an average slope of 0.7%. The site surface is rough asphalt pavement (Manning‘s n = 0.020) and the distance from the upstream catchment boundary to the channel inlet is 100...
You have a 5 acre commercial development, where flow drains into a gutter. Assume that the...
You have a 5 acre commercial development, where flow drains into a gutter. Assume that the travel time is 15 mins. The rainfall intensity can be determined by the following equation: i=10t-0.4. For the curb and gutter have the following design parameters: n = 0.015, cross slope of 40:1 and longitudinal slope is 3.0%. Determine the gutter flow depth, curb design depth and spread necessary to contain the 10 year peak flow. Determine the size of the catch basin for...
The flow limit of commercial-grade aluminum is given as σ = 120 MPa, the modulus of...
The flow limit of commercial-grade aluminum is given as σ = 120 MPa, the modulus of elasticity is E = 70 GPa and the density is 2.7 gr / cm3. a) There is a 4mm diameter and 3m long wire which made with this material. How many N should be applied to make this wire 3mm longer? b) If a 4 mm diameter wire made of this material is hung from the ceiling, what should be the total length of...
Which of the following are characteristics of an isotonic muscle twitch? The length of the muscle...
Which of the following are characteristics of an isotonic muscle twitch? The length of the muscle remains constant The length of the muscle remains constant and latent period than in an isometric twitch The muscle shortens at a constant velocity and the length of the latent period is longer than in an isometric twitch The muscle shortens at a constant velocity The afferent division of the peripheral nervous system Transmits action potentials to sensory organs Conveys action potentials to the...
Consider the following cash flow for an apartment development project:
Consider the following cash flow for an apartment development project: Year     Cash Flow 0          $(522,720) 1          $(441,716) 2          $74,260 3          $83,684 4          $93,391 5          $1,983,228 What is the IRR? What is the total profit? What is the Net Present Value (NPV) if the discount rate is 10%?  
different cash flow. given the following cash flow at the end of each year, what is...
different cash flow. given the following cash flow at the end of each year, what is the future value of this cash flow at 3%, 9%, and 18% interest rates at the end of year 7? year 1.                     $15,000 year 2.                     $20,000 year 3.                     $29,000 year4 through 6.    $0 year 7.                     $130,000
Given a project with the following characteristics, answer the following questions: You are the project manager...
Given a project with the following characteristics, answer the following questions: You are the project manager of a project to upgrade the generators at cell phone towers. Your project is scheduled to last for 12 months. It is the beginning of month 4. Your crews are to upgrade 8 cell phone towers per month for 12 months. Each generator is planned to cost $40,000 which includes equipment, labor, and fueling costs. You have upgraded 30 cell phone towers and your...
Consider the following set of processes, with the length of the CPU burst given in milliseconds:...
Consider the following set of processes, with the length of the CPU burst given in milliseconds: Process Burst Time Priority P1 2 2 P2 1 1 P3 8 4 P4 4 2 P5 5 3 The processes are assumed to have arrived in the order P1, P2, P3, P4, P5, all at time 0. Draw four Gantt charts that illustrate the execution of these processes using the following scheduling algorithms: FCFS, SJF, non preemptive priority (a smaller priority number implies...
Consider the following set of processes, with the length of the CPU burst given in milliseconds...
Consider the following set of processes, with the length of the CPU burst given in milliseconds       Process            Burst Time      Priority       P1                    2                      2       P2                    1                      1       P3                    8                      4       P4                    4                      2       P5                    5                      3 The processes are assumed to have arrived in the order P1, P2, P3, P4, P5, all at time 0, a. Draw four Gantt charts that illustrate the execution of these processes using the   following scheduling algorithms: FCFS, SJF, nonpreemptive...