In: Accounting
Exercise 17-1 (Part Level Submission) Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations. Standard Custom Direct labor costs $41,000 $103,000 Machine hours 1,240 1,490 Setup hours 109 370 Total estimated overhead costs are $304,000. Overhead cost allocated to the machining activity cost pool is $199,000, and $105,000 is allocated to the machine setup activity cost pool. (a) Your answer is correct. Compute the overhead rate using the traditional (plantwide) approach. (Round answer to 2 decimal places, e.g. 12.25.) Predetermined overhead rate % of direct labor cost Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Link to Text Attempts: 1 of 3 used (b) Your answer is correct. Compute the overhead rates using the activity-based costing approach. (Round answers to 2 decimal places, e.g. 12.25.) Machining $ per machine hour Machine setup $ per setup hour Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Link to Text Attempts: 1 of 3 used (c) Determine the difference in allocation between the two approaches. (Round answers to 0 decimal places, e.g. 1,225.) Traditional costing Standard $ Custom $ Activity-based costing Standard $ Custom $ Click if you would like to Show Work for this question:
$304,000 |
211.11% |
of direct labor cost |
$144,000 |
Machining: |
||
$199,000 |
$ 72.89 |
per machine hours |
2730 machine hours |
||
Machine Setup: |
||
$105,000 |
$ 219.21 |
per setup hours |
479 setups |
Traditional Costing: |
||
Standard |
Custom |
|
$ 41000 x 211.11% |
$86,555 |
|
$ 103000 x 211.11% |
$217,443 |
|
Total OH allocation |
$86,555 |
$217,443 |
Activity based Costing: |
||
Standard |
Custom |
|
Machining: |
||
1240 MH x $ 72.89 |
$90,384 |
|
1490 MH x $ 72.89 |
$108,606 |
|
Machine Setup: |
||
109 Setup hr x $ 219.21 |
$23,894 |
|
370 Setup hr x $ 219.21 |
$81,108 |
|
Total OH allocation |
$114,277 |
$189,714 |