In: Accounting
Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations. Standard Custom Direct labor costs $45,000 $113,000 Machine hours 1,140 1,110 Setup hours 106 430 Total estimated overhead costs are $308,000. Overhead cost allocated to the machining activity cost pool is $195,000, and $113,000 is allocated to the machine setup activity cost pool. Incorrect answer. Your answer is incorrect. Try again.
Compute the overhead rate using the traditional (plantwide) approach. (Round answer to 2 decimal places, e.g. 12.25.) Predetermined overhead rate:
Compute the overhead rates using the activity-based costing approach. (Round answers to 2 decimal places, e.g. 12.25.)
Machining:
Machine setup:
Determine the difference in allocation between the two approaches. (Round answers to 0 decimal places, e.g. 1,225.) Traditional costing
Standard:
Custom:
| Predetermined overhead rate | 195% | of direct labor cost | |
Working:
Total direct labor Cost = $45,000 + $113,000 = $158,000
Total overhead costs = $308,000
Overheads as % of direct labor = ($308,000 / $158,000) x 100 = 195%
2.
| Machining | $86.67 | per machine hour | 
| Machine setup | $210.82 | per setup hour | 
Working:
| Total machining cost | 195000 | 
| Total machine hours | 2250 | 
| Machining cost per machine hour | $86.67 | 
| Total machine setup cost | 113000 | 
| Total setup hours | 536 | 
| Machine set up cost per setup hour | $210.82 | 
| Traditional | Activity based | Difference | |
| Standard | 87750 | 121147 | -33397 | 
| Custom | 220350 | 186853 | 33497 | 
Working:
| Traditional method | ||
| Standard | Custom | |
| Direct labor | 45000 | 113000 | 
| Overhead (@195% of direct labor) | 87750 | 220350 | 
| Activity based costing | ||
| Standard | Custom | |
| Machine hours | 1140 | 1110 | 
| Machining cost per machine hour | $86.67 | $86.67 | 
| Machining cost | 98800 | 96200 | 
| Machine setup hours | 106 | 430 | 
| Machine setup cost per setup hour | $210.82 | $210.82 | 
| Setup cost | 22347 | 90653 | 
| Total overhead costs | 121147 | 186853 |