In: Accounting
Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations. Standard Custom Direct labor costs $60,000 $103,000 Machine hours 1,400 1,290 Setup hours 96 400 Total estimated overhead costs are $300,000. Overhead cost allocated to the machining activity cost pool is $195,000, and $105,000 is allocated to the machine setup activity cost pool. Compute the overhead rate using the traditional (plantwide) approach. (Round answer to 2 decimal places, e.g. 12.25.) Predetermined overhead rate % of direct labor cost Compute the overhead rates using the activity-based costing approach. (Round answers to 2 decimal places, e.g. 12.25.) Machining $ per machine hour Machine setup $ per setup hour Determine the difference in allocation between the two approaches. (Round answers to 0 decimal places, e.g. 1,225.) Traditional costing Standard $ Custom $ Activity-based costing Standard $ Custom $
Standard | Custom | |
Direct labor | 60000 | 103000 |
Machine hours | 1400 | 1290 |
Set-up hours | 96 | 400 |
Estimated overheads | 300000 | |
Machining activity | 195000 | |
Machine set up | 105000 | |
Plant wide method | ||
Estimated overhead costs | 300000 | |
Direct labor costs | 163000 | |
% of direct labor costs | 184.05% | |
Cost allocated | ||
Standard | Custom | |
Direct labor | 60000 | 103000 |
Allocated costs | 110429 | 189571 |
Activity based method | ||
Machining activity | Machine Set-up | |
Estimated overhead costs | 195000 | 105000 |
Total hours | 2690 | 496 |
Rate per hour | 72.49 | 211.69 |
Cost allocated | ||
Standard | Custom | |
Machine hours | 1400 | 1290 |
Allocation of Machining costs | 101486.00 | 93512.10 |
Set-up hours | 96 | 400 |
Allocation of Machine set-up costs | 20322.24 | 84676.00 |
Total allocated costs | 121808 | 178188 |
Difference | Standard | Custom |
Allocation as per plant wide method | 110429 | 189571 |
Allocation as per activity based method | 121808 | 178188 |
Difference | -11379 | 11382 |
Plantwide allocation method uses one predetermined overhead rate to allocate over costs, regardless of the approach used to allocate overhead, a predetermined overhead rate is established |
Activity based allocation method considers the cost driver rate which is cost pool total divided by cost driver. Per activity rate is identified. It identifies activities and assigns costs to each activity |