In: Operations Management
University wants to develop a Mobile Application for the University’s website along with all the features for e-learning in its innovative First Year Model. This will allow students to access their e-mails, lecture notes, in/after-class activities and many other features. The university wants to launch this App in January 2019. You have just completed your Bachelor’s studies and got an opportunity to prove yourself competent to work for the University’s Project Management Office along with three other new-comers. As a first challenge, you have been placed on board, as a group of four, towards managing the initiation, development and testing of the project. You need to produce a concise project document portfolio based on the University's requirements.
Q> Project Planning Documentation, i.e a comprehensive project management plan covering the various project aspects including the work breakdown structure, cost baseline and a Gantt Chart, which should be developed using Microsoft Project only.
Solution:
The Project Planning Document structure is as shown below:
Project Scope:
To develop a mobile application for the University website to enhance the overall student ease and experience.
------------------
Project Team Structure:
The project will be executed in a Waterfall model approach with A as the Project Manager and 3 team members comprising of 1 Analyst, 1 Developer, and 1 Tester.
# | Name | Project Role | Contact Number |
1 | A | Project Manager | 123-456-7890 |
2 | B | Analyst | 123-456-7890 |
3 | C | Developer | 123-456-7890 |
4 | D | Tester | 123-456-7890 |
------------------
Key Milestones:
Following are the key milestones of the project:
# | Milestone | Description | Date |
1 | Initiation | Scope review and finalize the project plan | 08/15/18 |
2 | Requirements | Complete business requirements | 08/31/18 |
3 | Development | Complete application development | 10/31/18 |
4 | Testing | Complete application and user testing | 12/31/18 |
5 | Launch | Implementation of code | 1/15/19 |
Post the launch, a team will be deployed to conduct user training and provide application support.
------------------
Project Work Breakdown Structure and Schedule:
The Work Breakdown Structure and the Gantt chart are provided below:
The project is expected to start on 08/01/2018 and the launch will be on 01/15/2019. The total duration will be 5.5 months. The milestones are shown on the Gantt chart.
------------------
Project Communication and Governance:
The project communication will be as shown below:
# | Type | Frequency | Format | Owner |
1 | Status Report | Weekly | Project Manager | |
2 | Technical Review | Monthly | In-Person | Project Manager |
3 | Sponsor Review | Quarterly | In-Person | Project Manager |
------------------
Financial Baseline:
The cost baseline is as follows:
# | Milestone | Cost Description | Budget |
1 | Initiation | Manpower cost for the Initiation phase | $10,000 |
2 | Requirements | Manpower cost for the Requirements phase | $20,000 |
3 | Development | Manpower cost and Software cost | $60,000 |
4 | Testing | Manpower cost for Testing phase | $40,000 |
5 | Launch | Cost of implementation and documentation | $20,000 |
Total Budget | $150,000 |
The total budget is estimated at $150,000.