In: Finance
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A negative $ 51 $ 23 $ 22 $ 20 $ 16 B negative $ 100 $ 20 $ 39 $ 48 $ 60 a. What are the IRRs of the two projects? b. If your discount rate is 5.2 %, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the IRRs of the two projects? (Round to one decimal place.)
The cash flows for project A:
Year 0:-$51
Year 1:$23
Year 2:$22
Year 3:$20
Year 4:$16
The cash flows for project B:
Year 0:-$100
Year 1:$20
Year 2:$39
Year 3:$48
Year 4:$60
Given that the discount rate is 5.2%.
In the NPV formula, we have used the discount rate=5.2%
Part a and b:
We will calculate the IRR and NPV using excel.
For project A, value of IRR=22.98% and NPV=$20.98
For project B, value of IRR=20.21% and NPV=$44.47
Part c:
Ranking as per IRR:
Rank 1: Project A with IRR=22.98%
Rank 2: Project B with IRR=20.21%
Ranking as per NPV:
Rank 1: Project B with NPV=$44.47
Rank 2: Project B with NPV=$20.98
The ranking are different because of the decision rule.
In case of IRR, a project with IRR greater than cost of capital
should be accepted and in case of NPV, a project with positive NPV
should be accepted because it increases the shareholder's value. In
both the cases, higher values are given higher preference.