Question

In: Accounting

Process Costing for a Service Company Madison Electric Company uses a fossil fuel (coal) plant for...

Process Costing for a Service Company

Madison Electric Company uses a fossil fuel (coal) plant for generating electricity. The facility can generate 900 megawatts (million watts) per hour. The plant operates 600 hours during March. Electricity is used as it is generated; thus, there are no inventories at the beginning or end of the period. The March conversion and fuel costs are as follows:

Conversion costs $40,500,000
Fuel 10,800,000
  Total $51,300,000

Madison also has a wind farm that can generate 100 megawatts per hour. The wind farm receives sufficient wind to run 300 hours for March. The March conversion costs for the wind farm (mostly depreciation) are as follows:

Conversion costs $2,700,000

a. Determine the cost per megawatt hour (MWh) for the fossil fuel plant and the wind farm to identify the lowest cost facility in March.

Cost Per Mega-watt Hour
Fossil plant $ per MWh
Wind farm

b. Why are equivalent units of production not needed in determining the cost per megawatt hour (MWh) for generating electricity?

c. What advantage does the fossil fuel plant have over the wind farm? Which of the following is true.

  1. Fossil fuel is easily available.
  2. Fossil fuel plant has a cost advantage over wind farm.
  3. The wind farm is subject to the presence of wind and thus, not reliable.
  4. The fossil fuel plant can be turned on and off on a schedule, while the wind farm is subject to the varieties of nature.

Solutions

Expert Solution

a. Determine the cost per megawatt hour (MWh) for the fossil fuel plant and the wind farm to identify the lowest cost facility in March.

Answer:

Cost Per Mega-watt Hour
Fossil plant 95 per MWh
Wind farm 90 per MWh

Calculation

First we need to calculate the cost per megawatt hour for the Fossil fuel plant by dividing the cost by the megawatt hours.

Fossil Fuel Plant Cost = 51,300,000

We need to calculate the cost, for that we need to multiply the megawatts per hour with the march hours.

That is,

Fossil Fuel Plant Megawatt Hours = 900 * 600 = 540,000

Cost Per Megawatt = Fossil Fuel Plant Megawatt Cost / Fossil Fuel Plant Megawatt Hours = 51,300,000 / 540,000 =  $95

Then we need to calculate the cost per megawatt hour for the wind farm, by dividing the wind farm cost by the wind farm megawatt hours.

Fossil Fuel Plant Cost = 2,700,000

We need to calculate the cost, for that we need to multiply the megawatts per hour with the march hours.

That is,

Wind Farm Megawatt Hours = 100 * 300 = 30,000

Cost Per Megawatt = Wind farm Megawatt Cost / Wind farm Megawatt Hours = 2,700,000 / 30,000 =  $90

b. Why are equivalent units of production not needed in determining the cost per megawatt hour (MWh) for generating electricity?

Answer:

The equivalent units of production are not computed because the electricity itself is the finished product.

Explanation:

The production of electricity is not similar to factory production. Because the factory production is done by batches. But if electricity is generated from a source, it is the final product. So, there is no need to determine equivalent units of production, as electricity itself is a finished product.

c. What advantage does the fossil fuel plant have over the wind farm? Which of the following is true.

Answer:

  1. Fossil fuel is easily available. - True
  2. Fossil fuel plant has a cost advantage over wind farm. - False
  3. The wind farm is subject to the presence of wind and thus, not reliable. - True
  4. The fossil fuel plant can be turned on and off on a schedule, while the wind farm is subject to the varieties of nature. - True

Explanation:

The Fossil fuel plant generated 540,000 megawatts for March, but the Wind farm generate only 30,000 megawatts. The Fossil fuel plant can generate more electricity than the Wind farm. The main reasons are that the fossil fuels are easily available but the wind farm depends on the presence of wind. But wind farm has less cost, though the fossil fuel generate more and have more benefit over wind farm.


Related Solutions

Service Industry Costing: Select a service industry company of your choice that uses costing and explain...
Service Industry Costing: Select a service industry company of your choice that uses costing and explain the benefits of costing for service companies. Cite your work and include sufficient detail.
1. In the electricity market, the U.S. overwhelmingly uses fossil fuels, primarily coal and natural gas....
1. In the electricity market, the U.S. overwhelmingly uses fossil fuels, primarily coal and natural gas. One of the backstop resources is electricity generated from wind. If the price of wind energy decreases a. we will stop using fossil fuels sooner. b. we will continue using fossil fuels for an even longer period of time before transitioning to the backstop resource. c. there will be no impact on when we transition from fossil fuels to wind. d. the demand for...
A typical coal-fired electric generating plant will burn about 3 metric tons of coal per hour....
A typical coal-fired electric generating plant will burn about 3 metric tons of coal per hour. Most of the coal burned in the United States contains 1 to 4 % by weight sulfur in the form of pyrite, which is oxidized as the coal burns: 4FeS2(s) + 11 O2(g) = 2 Fe2O3(s) + 8 SO2(g) Once in the atmosphere, the SO2 is oxidized to SO3, which then reacts with water in the atmosphere to form sulfuric acid: SO3(g) + H2O(l)...
Campo Company Process Costing Exercise Campo Company uses a process costing system. On March 1, it...
Campo Company Process Costing Exercise Campo Company uses a process costing system. On March 1, it had no work-in-process inventory. During the month it started 1,020,000 liters of product and shipped 960,000 liters to its upstream distribution partner. The cost of the resources used by Campo in March amounted to $408,330 direct materials and $1,521,370 conversion costs. The production supervisor estimates that the ending work in process is 40% complete on March 31. Determine (a) cost of product shipped and...
Rathburn, Inc. is a service firm that uses process costing. The firm worked on a total...
Rathburn, Inc. is a service firm that uses process costing. The firm worked on a total of 1,200 cases this month, 900 of which were completed during the period. The remaining cases were 45% complete. The firm incurred $274,650 in direct labor and manufacturing overhead costs during the period, and had $4,800 in direct labor and manufacturing costs in beginning inventory. Using the weighted average method, what was the total cost of cases completed during the period?
1. Rathburn, Inc. is a service firm that uses process costing. The firm worked on a...
1. Rathburn, Inc. is a service firm that uses process costing. The firm worked on a total of 1,300 cases this month, 900 of which were completed during the period. The remaining cases were 35% complete. The firm incurred $192,200 in direct labor and manufacturing overhead costs during the period, and had $5,400 in direct labor and manufacturing costs in beginning inventory. Using the weighted average method, what was the total cost of cases still in process at the end...
Coal is burned at an electric power generation plant at a rate of 150 kg/minute with...
Coal is burned at an electric power generation plant at a rate of 150 kg/minute with 8% excess air (dry). The coal has a composition (mass based) of xC (kg C/coal), xH (kg H/coal), xS (kg Sulfur/coal) and xash (kg ash/coal). The coal produces 20 kg/minute of ash. The outlet gases, on a dry basis (i.e. we exclude any water from the calculation), have the composition (volume basis): yCO2=0.1418, yCO=0.024, ySO2=0.003, yO2=0.027, yN2=0.8042. Calculate the coal composition, air demand and...
A neighborhood fuel cell power plant is to be designed for an electric power output of...
A neighborhood fuel cell power plant is to be designed for an electric power output of 2000 kW with liquid– water product. Estimate the flow rates of hydrogen and oxygen during peak power production, assuming an 80% efficient power conditioner is used to convert DC to AC power and the fuel cell efficiency is 55%. What is the plant heat rate?
Consider a coal-fired steam power plant that produces 175 MW of electric power. The power plant...
Consider a coal-fired steam power plant that produces 175 MW of electric power. The power plant operates on a simple ideal Rankine cycle with turbine inlet conditions of 7 MPa and 550°C and a condenser pressure of 15 kPa. The coal has a heating value (energy released when the fuel is burned) of 29,300 kJ/kg. Assuming that 75% of this energy is transferred to the steam in the boiler and that the pump has an efficiency of 80% and the...
A 600 MW pulverized coal-fired power plant of 40% efficiency uses coal with an ash content...
A 600 MW pulverized coal-fired power plant of 40% efficiency uses coal with an ash content of 15% and a heating value of 26,700 kJ/kg. Assume 35% of the ash content goes up the stack as particulate matter in the flue gas. The PM emission is controlled by an ESP which has the following efficiencies and weight distribution in the given size ranges. Find the fly ash emitted in g/s.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT