In: Operations Management
Mini-Case Study: Project Management at Global Green Books
Publishing
Global Green Books Publishing was started two years ago by two
friends, Jim King and Brad Mount, who met in college while studying
in Philadelphia, USA. In the new business, Jim focused on editing,
sales, and marketing while Brad Mount did the electronic assembly
and publishing of books for Global Green Books. Their business was
successful and profitable in the first two years, largely due to
contracts from two big businesses.
In their third year, they got very busy thanks to their third major
customer, a local college that needed customized eBooks. They hired
several part-time employees to help them with their publishing
business.
But by the end of the third year of operation, Global Green Books
started experiencing critical problems. They were: unable to
leverage all the new employees effectively unable to deliver
eBooks to their customers on schedule unable to provide quality
texts—time and money were being spent fixing defects in their
products unable to control costs—their business was not
profitable in the third year.
Global Green Books saw a significant rise in issues, a lot of
unpleasant “surprises” were cropping up; business was down as new
resources were hired, also some of the projects were poorly
estimated. The local university was unhappy as their eBook products
reached campus late for use by professors and students. In some
cases, the books were a week or two late. Since the courses must
start on schedule and students need their books at the beginning of
their courses, the new lucrative college customer was
unhappy.
One of the new part-time employees hired by Jim and Brad, Samantha,
had taken a project management course at college. Samantha was
excited about the discipline of project management and had
intentionally selected a job with Global Green Books Publishing as
she saw an opportunity to polish her project management skills.
One fine day, Jim invited Samantha, for a lunch meeting. He was
aware that Samantha was familiar with project management, and
wanted to hear what she had to say about the problems he and Brad
were facing. Over lunch, he questioned why their small business
which had operated and implemented projects so successfully over
the first two years was being challenged significantly now. He
specifically listed the problems they were facing and asked for
input to solve them.
Samantha asked for more time to research all the issues but noted
that Global Green Books while being innovative, completed projects
without a roadmap or a project plan and lacked a disciplined
approach to project management. She noted that Jim and Brad did not
use any project software for scheduling and they did not use tools
or techniques to estimate, budget, or to communicate with
stakeholders. Finally, they had no processes in place to manage
project risks and quality.
Impressed with this and other conversations, Jim King asked
Samantha if she would consider joining them as a project associate
or project manager on a full-time basis to help them introduce
project management practices and help them tide over their current
crisis.
Samantha accepted the offer! She has several key skills—she is an
excellent communicator with very good interpersonal skills and
detail-oriented. Within the first three months in her new role as
PM, she introduced formal project management processes, created a
PM manual, and trained the employees to get the work done well.
Within nine months Samantha had fully turned things around. Due to
proactive risk analysis and risk response planning, surprises, and
issues reduced. Communication with stakeholders was enhanced.
Brad and Jim noted that the company was delivering projects on
schedule, the quality processes worked—and customers were happy
with the products!
Comment on the following aspects of the case study:
a) Why did Global Green Books Publishing struggle? b) What were the
specific PM solutions that were introduced by Samantha that worked?
c) What kind of suggestions would you give to Brad and Jim if you
were the PM? d) Are you aware of other similar start-up businesses
that struggle in a similar manner? How did they overcome the
challenges? e) Global Green Books Publishing is a
technology-intensive business, but Samantha is not technically
knowledgeable, will she continue to be a successful project
manager?
As per policy, I have answered 4 subparts.
a)
Answer:- Earlier Global Green Books Publishing had small clients and they used to work without any project plan but as their clients grew, this method was not successful. Neither did they use any tools or techniques to estimate, budget, or to communicate with stakeholders. This lack of project planning and forecasting resulted in a delay to deliver ebooks in time, no quality text, high costs, and defective products. Thus, because of all these reasons, Global Green Books Publishing struggled.
2)
Answer:- The specific PM solutions that were introduced by Samantha that worked were:-
3)
Answer:- If I were the PM the kind of suggestions I would give to Brad and Jim would be to introduce a software tool schedule that will help Green Books timely delivery of products. Estimate the cost involved before the starting of the project. Also, a proper project plan should be analyzed at each stage of implementation and identify any risk involved with it. This can help to provide more quality products and save time and money in fixing defective products.
4)
Answer:- Yes, I am aware of other similar start-ups that struggle in a similar manner.
They overcome the challenges by listing up all the challenges, managed risk, learned from failure, re-investing on a new plan, and turned inevitable crises into opportunities.
**Hi student, if you find this helpful kindly, give a thumbs up, that will be very grateful, also if you have any doubt you can ask me in the comment section.