In: Accounting
Consider the following alternative projects in the table below. Each project would last for five years.
1) Find the NPV for each project at a 10% discount rate.
2) Find the profitability index for each project at a 10% discount rate.
3) What discount rate would make the NPV=0 (i.e. breakeven in time) for each project?
Use excel to populate the table below. Show all cell references, show all formulas used, and show all calculations clearly.
Project A |
Project B |
|
Initial investment |
$80,000 |
$60,000 |
Annual net cash inflows |
20,000 |
16,000 |
$5,000 in maintenance |
Year 2 |
Year 3 |
Salvage value |
10,000 |
8,000 |
Project A |
|||||
Year |
Cash Outflow |
Cash Inflow |
Net Cash Flow |
Discounting factor at 10% |
Discounted Cash flow |
1 |
$ 20,000.00 |
$ 20,000.00 |
0.909090909 |
$ 18,181.82 |
|
2 |
$ (5,000.00) |
$ 20,000.00 |
$ 15,000.00 |
0.826446281 |
$ 12,396.69 |
3 |
$ 20,000.00 |
$ 20,000.00 |
0.751314801 |
$ 15,026.30 |
|
4 |
$ 20,000.00 |
$ 20,000.00 |
0.683013455 |
$ 13,660.27 |
|
5 |
$ 20,000.00 |
$ 20,000.00 |
0.620921323 |
$ 12,418.43 |
|
5 |
$ 10,000.00 |
$ 10,000.00 |
0.620921323 |
$ 6,209.21 |
|
Present value of Cash Flows |
$ 77,892.72 |
||||
Less: Initial Investment |
$ 80,000.00 |
||||
Net Present Value |
$ (2,107.28) |
||||
Profitability Index (77892.72/80000) |
0.97 |
Project B |
|||||
Year |
Cash Outflow |
Cash Inflow |
Net Cash Flow |
Discounting factor |
Discounted Cash flow |
1 |
$ 16,000.00 |
$ 16,000.00 |
0.909090909 |
$ 14,545.45 |
|
2 |
$ 16,000.00 |
$ 16,000.00 |
0.826446281 |
$ 13,223.14 |
|
3 |
$ (5,000.00) |
$ 16,000.00 |
$ 11,000.00 |
0.751314801 |
$ 8,264.46 |
4 |
$ 16,000.00 |
$ 16,000.00 |
0.683013455 |
$ 10,928.22 |
|
5 |
$ 16,000.00 |
$ 16,000.00 |
0.620921323 |
$ 9,934.74 |
|
5 |
$ 8,000.00 |
$ 8,000.00 |
0.620921323 |
$ 4,967.37 |
|
Present value of Cash Flows |
$ 61,863.38 |
||||
Less: Initial Investment |
$ 60,000.00 |
||||
Net Present Value |
$ 1,863.38 |
||||
Profitability Index (61863.38/60000) |
1.03 |
Requirement
Project A |
Project B |
|
NPV |
$ (2,107.28) |
$ 1,863.38 |
NPV of project A is negative hence it is advisable to go with Project B
Requirement 2
Project A |
Project B |
|
Profitability Index |
$ 0.97 |
$ 1.03 |
Profitability index of more than is considered beneficial hence Project B should be accepted.
Requirement 3
A rate at which NPV is equal to zero is IRR or Internal rate of Return.
Discount rate at which NPV is Zero.
Project A 9.04% Approx
Project B 11.14% Approx
Project A |
|||||
Year |
Cash Outflow |
Cash Inflow |
Net Cash Flow |
Discounting factor at 109.04% |
Discounted Cash flow |
1 |
$ 20,000.00 |
$ 20,000.00 |
0.917094644 |
$ 18,341.89 |
|
2 |
$ (5,000.00) |
$ 20,000.00 |
$ 15,000.00 |
0.841062586 |
$ 12,615.94 |
3 |
$ 20,000.00 |
$ 20,000.00 |
0.771333993 |
$ 15,426.68 |
|
4 |
$ 20,000.00 |
$ 20,000.00 |
0.707386274 |
$ 14,147.73 |
|
5 |
$ 20,000.00 |
$ 20,000.00 |
0.648740163 |
$ 12,974.80 |
|
5 |
$ 10,000.00 |
$ 10,000.00 |
0.648740163 |
$ 6,487.40 |
|
Present value of Cash Flows |
$ 79,994.44 |
||||
Less: Initial Investment |
$ 80,000.00 |
||||
Net Present Value |
$ (5.56)* |
NPV of $ 5.56 is due to Round off.
Project B |
|||||
Year |
Cash Outflow |
Cash Inflow |
Net Cash Flow |
Discounting factor |
Discounted Cash flow |
1 |
$ 16,000.00 |
$ 16,000.00 |
0.899766061 |
$ 14,396.26 |
|
2 |
$ 16,000.00 |
$ 16,000.00 |
0.809578964 |
$ 12,953.26 |
|
3 |
$ (5,000.00) |
$ 16,000.00 |
$ 11,000.00 |
0.728431676 |
$ 8,012.75 |
4 |
$ 16,000.00 |
$ 16,000.00 |
0.655418099 |
$ 10,486.69 |
|
5 |
$ 16,000.00 |
$ 16,000.00 |
0.589722961 |
$ 9,435.57 |
|
5 |
$ 8,000.00 |
$ 8,000.00 |
0.589722961 |
$ 4,717.78 |
|
Present value of Cash Flows |
$ 60,002.31 |
||||
Less: Initial Investment |
$ 60,000.00 |
||||
Net Present Value |
$ 2.31 |
||||
Profitability Index (61863.38/60000) |
1.00** |
NPV of $ 1 is due to Round off.