In: Operations Management
Company X produces an end product Afor the market. One unit of
Ais made by assembling 1 unit of K, 2 units of L, and 1 unit of M.
One unit of K is made of 2 units of G and 3 units of H; one unit of
L is assembled using 1 unit of M and 2 units of N. Current on-hand
inventories for L and M are 130 and 60, respectively. Scheduled
receipts are 300 for L at the beginning of week 1 and 150 for M at
the beginning of week 2.
Lead times for K and L are one week, and lead times for other
components are two weeks. The final assembly time for A is one
week.
1. Fill in Table 1 to prepare a master production schedule for end
product Ausing a fixed lot size of 200. The beginning inventory for
A is 180; the forecast and committed customer orders
for A are provided in this table.
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 
| Forecast | 80 | 70 | 50 | 70 | 80 | 65 | 90 | 100 | 
| Customer orders (committed) | 85 | 20 | 30 | 20 | ||||
| Projected on-hand inventory | ||||||||
| MPS Receipt | ||||||||
| MPS Start | ||||||||
| Available-to-promise inventory (uncommitted) | 
Table 1: MPS table for end product A in Question 1
b. Construct the product structure tree (i.e., the BOM chart) for A.
c. Use your master production schedule in Table 1 to develop a material requirement plan (MRP) for the subassembly L using the lot-for-lot policy.
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 
| MPS Start for A | 
| L | 
 Lead time: 1 week; On hand 130; Scheduled Receipt in week 1: 300  | 
|||||||
| Gross Requirement | ||||||||
| Scheduled Receipts | ||||||||
| Projected On Hand | ||||||||
| Net Requirement | ||||||||
| PO Receipts | ||||||||
| PO Releases | ||||||||
Thanks very much
Determine MPS quantity:
MPS quantity is ordered when projected on-hand inventory before placing MPS falls below 0 units (negative).
Available = Previous available inventory + MPS – Maximum (Forecast, Order)
For week 1, POH = 180 + 0 – 85 = 95
For week 2, POH = 95 + 0 – 70 = 25
For week 3, POH = 25 + 0 – 50 = -250, Place MPS = 200 units in week 3
For week 3, projected on-hand after MPS = 25 + 200 – 50 = 175 units
| 
 1  | 
 2  | 
 3  | 
 4  | 
 5  | 
 6  | 
 7  | 
 8  | 
||
| 
 Forecast  | 
 80  | 
 70  | 
 50  | 
 70  | 
 80  | 
 65  | 
 90  | 
 100  | 
|
| 
 Customer orders  | 
 85  | 
 20  | 
 30  | 
 20  | 
 0  | 
 0  | 
 0  | 
 0  | 
|
| 
 gross req.  | 
 Max(80,85) = 85  | 
 70  | 
 50  | 
 70  | 
 80  | 
 65  | 
 90  | 
 100  | 
|
| 
 Projected on-hand inventory  | 
 180  | 
 180-85 = 95  | 
 25  | 
 175  | 
 105  | 
 25  | 
 160  | 
 70  | 
 170  | 
| 
 MPS Receipt  | 
 200  | 
 200  | 
 200  | 
||||||
| 
 MPS Start  | 
 200  | 
 200  | 
 200  | 
||||||
| 
 ATP  | 
 75  | 
 150  | 
 200  | 
 200  | 
ATP is the quantity that is available after satisfying the customer requirement.
For week 1, ATP = Previous week inventory + MPS of the week – Sum of Customer Orders till the week MPS is scheduled
ATP for week 1 = 180 + 0 – 85 = 75
For the rest of weeks in which MPS is scheduled, the ATP is calculated as follows:
ATP = MPS of the week – Sum of Customer Orders till the week MPS is scheduled
Bill of Materials:

MRP schedule of component L:
Net requirement = GR of week – projected on-hand of previous week – Scheduled Receipts of week
Projected on-hand = Projected on-hand of previous week + SR of week – GR of week + Planned order receipt (PORc) of week
Planned order receipt = Net requirement for Lot-to-lot size
Planned order releases (PORs) = Planned order receipts (PORc) time -phased by item lead time
Updated MRP schedule for U, Y and Z is as follows:
Requirement of L: 2 units for item A
| 
 Week  | 
 1  | 
 2  | 
 3  | 
 4  | 
 5  | 
 6  | 
 7  | 
 8  | 
| 
 MPS Start for A  | 
 200  | 
 200  | 
 200  | 
|||||
| 
 L  | 
 Lead time: 1 week; On hand 130;  | 
|||||||
| 
 Scheduled Receipt in week 1: 300  | 
||||||||
| 
 Gross Requirement  | 
 0  | 
 2*200 = 400  | 
 0  | 
 0  | 
 400  | 
 0  | 
 400  | 
 0  | 
| 
 Scheduled Receipts  | 
 300  | 
|||||||
| 
 Projected On Hand  | 
 430  | 
 30  | 
 30  | 
 30  | 
 0  | 
 0  | 
 0  | 
 0  | 
| 
 Net Requirement  | 
 370  | 
 0  | 
 400  | 
 0  | 
||||
| 
 PO Receipts  | 
 370  | 
 400  | 
||||||
| 
 PO Releases  | 
 370  | 
 400  | 
||||||