In: Operations Management
Company X produces an end product Afor the market. One unit of
Ais made by assembling 1 unit of K, 2 units of L, and 1 unit of M.
One unit of K is made of 2 units of G and 3 units of H; one unit of
L is assembled using 1 unit of M and 2 units of N. Current on-hand
inventories for L and M are 130 and 60, respectively. Scheduled
receipts are 300 for L at the beginning of week 1 and 150 for M at
the beginning of week 2.
Lead times for K and L are one week, and lead times for other
components are two weeks. The final assembly time for A is one
week.
1. Fill in Table 1 to prepare a master production schedule for end
product Ausing a fixed lot size of 200. The beginning inventory for
A is 180; the forecast and committed customer orders
for A are provided in this table.
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Forecast | 80 | 70 | 50 | 70 | 80 | 65 | 90 | 100 |
Customer orders (committed) | 85 | 20 | 30 | 20 | ||||
Projected on-hand inventory | ||||||||
MPS Receipt | ||||||||
MPS Start | ||||||||
Available-to-promise inventory (uncommitted) |
Table 1: MPS table for end product A in Question 1
b. Construct the product structure tree (i.e., the BOM chart) for A.
c. Use your master production schedule in Table 1 to develop a material requirement plan (MRP) for the subassembly L using the lot-for-lot policy.
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
MPS Start for A |
L |
Lead time: 1 week; On hand 130; Scheduled Receipt in week 1: 300 |
|||||||
Gross Requirement | ||||||||
Scheduled Receipts | ||||||||
Projected On Hand | ||||||||
Net Requirement | ||||||||
PO Receipts | ||||||||
PO Releases |
Thanks very much
Determine MPS quantity:
MPS quantity is ordered when projected on-hand inventory before placing MPS falls below 0 units (negative).
Available = Previous available inventory + MPS – Maximum (Forecast, Order)
For week 1, POH = 180 + 0 – 85 = 95
For week 2, POH = 95 + 0 – 70 = 25
For week 3, POH = 25 + 0 – 50 = -250, Place MPS = 200 units in week 3
For week 3, projected on-hand after MPS = 25 + 200 – 50 = 175 units
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
||
Forecast |
80 |
70 |
50 |
70 |
80 |
65 |
90 |
100 |
|
Customer orders |
85 |
20 |
30 |
20 |
0 |
0 |
0 |
0 |
|
gross req. |
Max(80,85) = 85 |
70 |
50 |
70 |
80 |
65 |
90 |
100 |
|
Projected on-hand inventory |
180 |
180-85 = 95 |
25 |
175 |
105 |
25 |
160 |
70 |
170 |
MPS Receipt |
200 |
200 |
200 |
||||||
MPS Start |
200 |
200 |
200 |
||||||
ATP |
75 |
150 |
200 |
200 |
ATP is the quantity that is available after satisfying the customer requirement.
For week 1, ATP = Previous week inventory + MPS of the week – Sum of Customer Orders till the week MPS is scheduled
ATP for week 1 = 180 + 0 – 85 = 75
For the rest of weeks in which MPS is scheduled, the ATP is calculated as follows:
ATP = MPS of the week – Sum of Customer Orders till the week MPS is scheduled
Bill of Materials:
MRP schedule of component L:
Net requirement = GR of week – projected on-hand of previous week – Scheduled Receipts of week
Projected on-hand = Projected on-hand of previous week + SR of week – GR of week + Planned order receipt (PORc) of week
Planned order receipt = Net requirement for Lot-to-lot size
Planned order releases (PORs) = Planned order receipts (PORc) time -phased by item lead time
Updated MRP schedule for U, Y and Z is as follows:
Requirement of L: 2 units for item A
Week |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
MPS Start for A |
200 |
200 |
200 |
|||||
L |
Lead time: 1 week; On hand 130; |
|||||||
Scheduled Receipt in week 1: 300 |
||||||||
Gross Requirement |
0 |
2*200 = 400 |
0 |
0 |
400 |
0 |
400 |
0 |
Scheduled Receipts |
300 |
|||||||
Projected On Hand |
430 |
30 |
30 |
30 |
0 |
0 |
0 |
0 |
Net Requirement |
370 |
0 |
400 |
0 |
||||
PO Receipts |
370 |
400 |
||||||
PO Releases |
370 |
400 |