Question

In: Civil Engineering

A. Calculate the price of pit-run gravel delivered to the site per cubic yard (bank measure)...

A. Calculate the price of pit-run gravel delivered to the site per cubic yard (bank measure) based on the following data: The pit is located 10 miles from the site. Trucks cost $43.75 per hour including fuel and maintenance; they have 12 cubic yards (loose material) capacity and travel at an average speed of 30 miles per hour. The swell factor for this material is 15%. Trucks take 5 minutes to unload at the site. The loader costs $82.50 per hour and loads material at the pit at the rate of 40 cubic yards per hour. The truck driver’s wage is $45.00 per hour, and the equipment operator’s wage is $54.00 per hour.

Solutions

Expert Solution

Given:

Distance between site and pit = 10 miles

Swell factor of material = 15%

Truck capacity = 12 cubic yards (loose material)

Truck average speed = 30 miles / hour

Unload or dump time = 5 minutes

Truck cost = $43.75 per hour

Truck driver's wage = $45 per hour

Loader productivity = 40 cubic yards / hour

Loader cost = $82.5 per hour

Operator's wage = $54 per hour

Solution:

The number of trucks required to avoid idling of loading equipment should be calculated. From this, the cost of transportation (hauling) of material per hour can be found out. The cost per hour divided by the quantity that can be loaded in one hour will give us the price of soil per cubic yard.

Truck capacity (Bank quantity) = Truck capacity (loose quantity) / Swell factor x 100

= 12 cubic yards / 115 x 100

= 10.435 cubic yards.

Truck cycle time = Loading time + Travel time to the site + Unloading time (dump) + Travel time back to site

Loading time = Truck capacity / Loader productivity

= 10.435 cubic yards / 40 cubic yards per hour

= 0.2609 hour = 0.2609 x 60 minutes

= 15.65 minutes

Travel time to the site = Diatance / Average speed

= 10 miles / 30 miles per hour

= 0.33 hour = 20 minutes

Travel time back to pit = Travel time to the site (because distance is equal)

= 20 minutes

Now substitute the above values to find truck cycle time

Truck cycle time = 15.65 + 20 + 5 + 20

= 60.65 minutes

Number of trucks required = Truck cycle time / Loading time for one truck

= 60.65 minutes / 15.65 minutes per truck

= 3.875 trucks

Consider 4 number of trucks.

Cost per hour = cost of loading + cost of hauling (transport to the site)

Cost of loading = Loader cost + Operator's wage

= $82.5 per hour + $54 per hour

= $136.5 per hour

Cost of hauling (Transport) = ( Truck cost + Driver's wage ) x Number of trucks

= ( $43.75 per hour + $45 per hour ) x 4

= $ 355 per hour

Now substitute the above values to find the cost per hour

Cost per hour = $136.5 per hour + $355 per hour

= $491.5 per hour

Price of delivery per cubic yard of material = Cost per hour / Quantity of material loaded per hour (Loader productivity)

= $ 491.5 / 40 cubic yards

= $12.29 per cubic yards

The price of pit-run gravel delivered to the site is $12.29 per cubic yards.


Related Solutions

Gravel is being dumped from a conveyor belt at a rate of 40 cubic feet per...
Gravel is being dumped from a conveyor belt at a rate of 40 cubic feet per minute. It forms a pile in the shape of a right circular cone whose base diameter and height are always the same. How fast is the height of the pile increasing when the pile is 21 feet high? Recall that the volume of a right circular cone with height h and radius of the base r is given by V=(1/3)πr2h
Determine the quantities of materials required per cubic yard to create a concrete mix. The specifications...
Determine the quantities of materials required per cubic yard to create a concrete mix. The specifications require a maximum size aggregate of 3/4 in., a minimum cement content of 6 sacks per cy, and a maximum water-cement ratio of 0.5. Assume 7% air voids. Consider the ratio of course aggregates to be 65% of the total aggregates by volume. Please refer to the standard weights & densities (at the end of the test) for specific gravities and unit conversions.
Determine the quantities of materials required per cubic yard to create a concrete mix. The specifications...
Determine the quantities of materials required per cubic yard to create a concrete mix. The specifications require a maximum size aggregate of 3/4 in., a minimum cement content of 6 sacks per cy, and a maximum water-cement ratio of 0.5. Assume 7% air voids. Consider the ratio of course aggregates to be 65% of the total aggregates by volume. Please refer to the standard weights & densities (at the end of the test) for specific gravities and unit conversions.
Calculate the number of free electrons per cubic centimeter (and per atom) for sodium from resistance...
Calculate the number of free electrons per cubic centimeter (and per atom) for sodium from resistance data (relaxation time 3.1*10-14 s)
1. Calculate the number of atoms per cubic centimeter of lead given that the density of...
1. Calculate the number of atoms per cubic centimeter of lead given that the density of lead is 11.3 ?/??3 and its atomic weight is 207.21. 2. Calculate the ionization potential of a singly ionized ?? 4 atom. 3. (a) How much energy would be released if 1 g of deuterium were fused to form helium according to the equation 2? + 2? → ?? 4 + ?? (b) How much energy is necessary to drive the two deuterium nuclei...
Calculate the number of photons per cubic centimeter inside a cavity whose walls are heated to...
Calculate the number of photons per cubic centimeter inside a cavity whose walls are heated to 3000 K. Compare this to the corresponding number at 3 K.
Question: Calculate the mass density (in kilogram per cubic meter) of a cylinder whose mass is...
Question: Calculate the mass density (in kilogram per cubic meter) of a cylinder whose mass is (13.77 ± 0.11) g, diameter is (1.83 ± 0.07) cm, and height is (3.25 ± 0.05) cm. In all calculations below, you must also determine the uncertainties in the calculated values. 1. Calculate the percent uncertainty for the mass of the cylinder. ( 1 2 3 4 5 ) (2.25 pts) 2. Calculate the percent uncertainty for the diameter of the cylinder. ( 1...
The long-run growth is measured as the increase in real GDP per capita and this measure...
The long-run growth is measured as the increase in real GDP per capita and this measure has changed over time and it also varies across countries. A country’s standard of living depends on its ability to produce goods and services (productivity). How do we measure long-term economic growth of a country? What are the key determinants of long-run economic growth? What is the relationship between economic growth and productivity? What is the major source of growth in labor productivity?
a) Price elasticity of demand for cigarettes is -0.5 in the short-run. Currently, the price per...
a) Price elasticity of demand for cigarettes is -0.5 in the short-run. Currently, the price per pack of cigarettes is $5.50 in Louisiana. $0.86 of this price is state tax and about $1 of the price is federal tax. Each year 350 million packs of cigarettes are sold in Louisiana. If the state government increases the state tax to $1.08 per pack, what would be the new state tax receipts from cigarettes after this tax increase? b) How would your...
Calculate the number of atoms per cubic meter in Cobalt (Co) (units atoms/m3). Write your answer...
Calculate the number of atoms per cubic meter in Cobalt (Co) (units atoms/m3). Write your answer with 4 significant figures
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT