Question

In: Accounting

It's About​ Time, Inc. manufacturers 2 lines of​ clocks: Digital and Analog. Under the current costing​...

It's About​ Time, Inc. manufacturers 2 lines of​ clocks: Digital and Analog. Under the current costing​ system, manufacturing overhead is applied to each line based on machine hours. Machine Setup costs account for the majority of manufacturing overhead and are expected to total​ $75,000 for the upcoming period. The controller for the company has suggested to management that an activity based costing system be analyzed and has determined that the number of machine setups drives the total machine setup costs. The following information was compiled for the​ analysis:

Digital

Analog

Total Expected Machine Hours for Budgeted Output

1,500 hours

​2,500 hours

Budgeted Output

750 clocks

500 clocks

Number of Clocks to be Produced per Machine Setup

25 clock

10 clocks

Which of the following statements is correct with respect to machine setup​ costs?

A. Since direct material and direct labor information are not​ given, it is impossible to determine if the product lines are being​ over/undercosted.

B. Under the activity based costing​ system, 37.5% of the machine setup manufacuring overhead costs are applied to the Analog product line.

C. Under the current costing​ system, 60% of the machine setup manufacturing overhead costs are applied to the Digital product line.

D. The current costing system is not​ over/undercosting the product lines with respect to machine setup costs.

E. If the Digital product line is being overcosted with respect to machine setup costs, it is likely that the Analog product line is also being overcosted with respect to machine setup costs.

Solutions

Expert Solution

Digital Analouge
(a) Total expected machine hours for budgeted output 1500 hours 2500 hours
(b) Budgeted output 750 clocks 500 clocks
(c) Number of clocks to be produced [(b) / (c)] 25 clocks 10 clocks
(d) Total machine set ups required 30 50
(e) Machine set up cost per machine hour (1500 hours X $18.75) (2500 hours X $18.75) $       28,125 $       46,875
(f) Machine set up cost pe set up (30 set ups X $937.5) (50 set ups X $937.5) $       28,125 $       46,875
Therefore, the cost distributed as per machine hours or set ups required are same.
Correct statement is E
As under both methods cost is distributed equally and if any higer or lower change occurs in cost it will effect both the costs with same ratio.
Workings:
Computation of cost per machine hour:
(i) Machine overheads cost =           75,000
(ii) Total machine hours (1500 +2500) =              4,000
Cost per machine hour [(i)/(ii)] = $         18.75
(iii) Total Machine set ups (30+20) = 80
Cost pe machine setup [(i)/(iii)] = $       937.50

Related Solutions

2. A digital signal processing system with analog audio signal input in the range of 0-20...
2. A digital signal processing system with analog audio signal input in the range of 0-20 Khz uses oversampling techniques and a second order sigma delta modulator to convert the analog signal into a digital bit stream at a rate of 3.072 Mhz. i) Explain how the digital bit stream may be converted in to a digital multibit stream for x(n). ii) Determine the overall improvement in signal to quantization noise ratio made possible by oversampling and noise shaping and...
1)Explain the need of analog and digital modulation in communication systems. 2)How modulated signals can be...
1)Explain the need of analog and digital modulation in communication systems. 2)How modulated signals can be recovered through coherent detection of carrier. Draw suitable diagram and mathematical expressions.What is meant by over modulated carriers. 3)Drive an expression for transmission efficiency of A.M wave. Under what circumstances carrier wave reversal take place. 4)How SSB-SC modulated waves can be produced. Elaborate your answer with suitable diagram. 5)A device is sending out data at the rate of 1000 bps. (a) How long does...
Timekeeper Inc. manufactures clocks on a highly automated assembly line. Its costing system uses two cost...
Timekeeper Inc. manufactures clocks on a highly automated assembly line. Its costing system uses two cost categories, direct materials and conversion costs. Each product must pass through the Assembly Department and the Testing Department. Direct materials are added at the beginning of the production process. Conversion costs are allocated evenly throughout production. Timekeeper Inc. uses weighted-average costing. Data for the Assembly Department for June are:       Work in process, beginning inventory                            300 units             Direct materials (100% complete)             Conversion costs (50% complete)...
Timekeeper Inc. manufactures clocks on a highly automated assembly line. Its costing system uses two cost...
Timekeeper Inc. manufactures clocks on a highly automated assembly line. Its costing system uses two cost categories, direct materials and conversion costs. Each product must pass through the Assembly Department and the Testing Department. Direct materials are added at the beginning of the production process. Conversion costs are allocated evenly throughout production. Timekeeper Inc. uses weighted-average costing. Data for the Assembly Department for June 2017 are: Work in process, beginning inventory 340 units Direct materials (100% complete) Conversion costs (50%...
Given two lines, state and prove the precise conditions under which reflecting a point about the...
Given two lines, state and prove the precise conditions under which reflecting a point about the two lines is commutative. I have seen this proved on here more than once, but I do not understand the answers that have been provided. I have seen that the two lines must be perpendicular- Why isn't it all sets of two lines? Is there a counterexample that I can visualize? Is that answer even correct? Thank you!
Digital Storage Concept Inc. is considering a change to activity-based product costing. The company produces two...
Digital Storage Concept Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 3,750 direct labor hours. The total indirect labor is budgeted to be $375,000. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information about cell phones and...
Income Statements under Absorption Costing and Variable Costing Gallatin County Motors Inc. assembles and sells snowmobile...
Income Statements under Absorption Costing and Variable Costing Gallatin County Motors Inc. assembles and sells snowmobile engines. The company began operations on July 1 and operated at 100% of capacity during the first month. The following data summarize the results for July: Sales (11,500 units) $1,610,000 Production costs (15,000 units): Direct materials $777,000 Direct labor 373,500 Variable factory overhead 186,000 Fixed factory overhead 124,500 1,461,000 Selling and administrative expenses: Variable selling and administrative expenses $226,500 Fixed selling and administrative expenses...
Income Statements under Absorption Costing and Variable Costing Gallatin County Motors Inc. assembles and sells snowmobile...
Income Statements under Absorption Costing and Variable Costing Gallatin County Motors Inc. assembles and sells snowmobile engines. The company began operations on July 1 and operated at 100% of capacity during the first month. The following data summarize the results for July: Sales (16,500 units) $2,475,000 Production costs (21,000 units): Direct materials $1,165,500 Direct labor 558,600 Variable factory overhead 279,300 Fixed factory overhead 186,900 2,190,300 Selling and administrative expenses: Variable selling and administrative expenses $339,500 Fixed selling and administrative expenses...
   Income statements under absorption costing and variable costing Fresno Industries Inc. manufactures and sells high-quality...
   Income statements under absorption costing and variable costing Fresno Industries Inc. manufactures and sells high-quality camping tents. The company began operations on January 1 and operated at 100% of capacity (160,000 units) during the first month, creating an ending inventory of 25,000 units. During February, the company produced 135,000 units during the month but sold 160,000 units at $570 per unit. The February manufacturing costs and selling and administrative expenses were as follows: Number of Units Unit Cost Total...
Income Statements under Absorption Costing and Variable Costing Gallatin County Motors Inc. assembles and sells snowmobile...
Income Statements under Absorption Costing and Variable Costing Gallatin County Motors Inc. assembles and sells snowmobile engines. The company began operations on July 1 and operated at 100% of capacity during the first month. The following data summarize the results for July: Sales (13,000 units) $2,080,000 Production costs (17,000 units): Direct materials $1,006,400 Direct labor 482,800 Variable factory overhead 241,400 Fixed factory overhead 161,500 1,892,100 Selling and administrative expenses: Variable selling and administrative expenses $293,300 Fixed selling and administrative expenses...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT