In: Accounting
On March 1, 2017, the Company entered into an agreement with a
customer, Thornock Square Apartments, to construct a residential
apartment building for a fixed price of $1.5 million. The Company
estimates that it will incur costs of $1 million to complete
construction of the apartment building. The apartment building will
only transfer to Thornock Square Apartments once the construction
of the entire building is complete. In addition, Thornock Square
Apartments has various design requirements that would require
Cannon to incur significant costs to rework the building prior to
selling it to a customer other than Thornock Square
Apartments.
To construct the apartment building, Cannon acquires standard
materials that it regularly uses in construction contracts for both
residential and commercial buildings. These materials are used to
manufacture generic component parts for inclusion in Thornock
Square Apartments’ residential buildings. These standard materials
remain interchangeable with other items until they are deployed in
Thornock Square Apartments building. The Company has made the
following purchases and incurred the following costs throughout the
construction progress:
A. As of June 30, 2017, in total, Cannon has purchased $75,000 of
component parts. As of June 30, 2017, $25,000 of component parts
remain in inventory and $50,000 have been integrated into the
project. Further, Cannon has incurred $12,500 of direct costs to
integrate the component parts into the Thornock Square Apartments
construction project during the three months ended June 30,
2017.
B. During the three months ended September 30, 2017, Cannon
purchased an additional $500,000 of component parts ($575,000 in
total). Of the $575,000 of component parts, $325,000 remain in
inventory and $200,000 have been integrated into the project during
the three months ended September 30, 2017. During the three months
ended September 30, 2017, Cannon incurred an additional $50,000 of
direct costs to integrate the component parts into the Thornock
Square Apartments construction project.
C. As of September 30, 2017, Cannon determined that the project was
over budget and revised its cost estimate from $1 million to $1.25
million.
D. As of December 31 2017, the construction project was completed.
During the three months ended December 31, 2017, Cannon purchased
an additional $425,000 of generic component parts ($1 million in
total). Of the $1 million component parts, $0 remain in inventory
and $750,000 were integrated into the project during the three
months ended December 31, 2017. Cannon has incurred $187,500 of
direct costs to integrate the component parts into the Thornock
Square Apartments construction project during the three months
ended December 31, 2017.
If Thornock Square Apartments cancels the contract, Cannon will be
entitled to reimbursement for costs incurred for work completed to
date plus a margin of 20 percent, which is considered to be a
reasonable margin. Cannon will not be reimbursed for any materials
that have been purchased for use in the contract but have not yet
been used and are still controlled by Cannon.
1) What amount of revenue should be recognized for the following periods: a. The three months ended June 30, 2017? b. The three months ended September 30, 2017? c. The three months ended December 31, 2017? Please explain calculations
2)Create a revenue recognition summary table which summarises the calculations used to find the revenue in each quarter
3)How should the entity recognize revenue for the satisfaction of its performance obligation in FASB code?
(All other chegg answers were wrong for this question)
Note:
Sub part 1
Cost of Materials used - $ 50,000.
Other Costs incurred - $ 12,500.
--------------
Total costs to date- $ 62,500.
-------------
% of work completion = Total costs to date/ Total estimated costs.
= $ 62,500/$ 1,000,000
=6.25%
Revenue to be recognised in June = Total revenue x % of work completion
= $ 1,500,000 x 6.25%
= $ 93,750.
2. Revenue for Sept 2017
Total Revised Estimated costs – $1,250,000
Total costs incurred upto June - $62,500
Cost of Material for Sept - $200,000
Other costs- $50,000
-----------------
Total costs to date - $ 312,500
------------------
% of work completion = Total costs to date/ Total estimated costs.
= $ 312,500/$ 1,250,000
=25%
Total revenue to be recognised till date = Total revenue x % of work completion
= $ 1,500,000 x 25%
= $ 375,000.
Revenue to be recognised in Sept = Revenue to be recognised till date- Revenue recognised in June
= $375,000 - $ 93,750
= $281,250
3.Revenue for Dec 2017
Since the work gets completed in Dec, the unrecognised revenue will be recognised in Dec.
Revenue recognised in Dec 2017 = $1,500,000 - $ 93,750 - $ 281,250
= $1,125,000.
Sub part 2
Period |
Amount |
June |
$93,750 |
Sept |
$281,250 |
Dec |
$1,125,000 |
Sub part 3
However the entity should recognise revenue over time (i.e. work in process) if:
The entity’s performance does not create an asset with an alternative use to the entity and the entity has an enforceable right to payment for performance completed to date + margin