In: Accounting
Business Decision Case Elizabeth Flanigan and Associates is an engineering and design firm that
specializes in developing plans for recycling plants for municipalities. The firm uses a job costing
system to accumulate the cost associated with each design project. Flanigan employs three levels of
employee: senior engineers, associate engineers, and clerical staff. The salary cost of the senior en-
gineers and the associate engineers is assigned to each project as direct labor. The salary cost of the
clerical staff is included in overhead, along with the cost of engineering supplies, automobile travel,
and equipment depreciation. The cost of airline travel, motels, building permits, and fees from other
consultants is charged to each project as direct material. Overhead is applied to projects using a pre-
determined overhead rate based on total engineering hours. The rate for 2014 is $5 per hour.
The six different salary levels for 2015 for the employees of Elizabeth Flanigan and Associates
are listed below. The hourly rate is determined by dividing the yearly salary by 2,000 hours per year.
Senior engineer
Level 1: $44,000 per year ($22 per hour)
Level 2: $36,000 per year ($18 per hour)
Associate engineer
Level 3: $30,000 per year ($15 per hour)
Level 4: $24,000 per year ($12 per hour)
Clerical staff
Level 5: $16,000 per year ($8 per hour)
Level 6: $12,000 per year ($6 per hour)
The billings that are sent to the municipalities for engineering services utilize cost-plus billing.
Typically, the total costs accumulated for a project (direct material, direct labor, and overhead) are
multiplied by 140% to determine the amount of the billing. The difference between the billed amount
and the accumulated cost is the “plus” in cost plus.
During March 2015, Flanigan accumulated the following information related to Job 295 for
Johnson Creek City:
Senior engineer hours
Level 1 . . . . . . . . . . . . . . . . . . . . . . . . 52
Level 2 . . . . . . . . . . . . . . . . . . . . . . . . 84
Associate engineer hours
Level 3 . . . . . . . . . . . . . . . . . . . . . . . . 106
Level 4 . . . . . . . . . . . . . . . . . . . . . . . . 44
Clerical hours
Level 5 . . . . . . . . . . . . . . . . . . . . . . . . 20
Level 6 . . . . . . . . . . . . . . . . . . . . . . . . 66
Building permits . . . . . . . . . . . . . . . . $1,500
Airline travel and motel . . . . . . . . . . $865
Discuss the next two problems:
Required
a. What amount should be billed to Johnson Creek City for March 2015?
b. How much profit was earned on Job 295 during March 2015?
a. Amount billed to Johonson Creek City = $11,997
Working:
No. Of hours | Rate | Amount | |
Direct material | |||
Building Permits | 1500 | ||
Airline travel and motel | 865 | ||
Total Direct Material | 2365 | ||
Direct labor | |||
Level 1 | 52 | 22 | 1144 |
Level 2 | 84 | 18 | 1512 |
Level 3 | 106 | 15 | 1590 |
Level 4 | 44 | 12 | 528 |
Total Direct Labor | 286 | 4774 | |
Overhead: | 286 | 5 | 1430 |
(Total engineering hours x $5 per hour) | |||
Total Cost | 8569 | ||
Billing | (140% of Cost ) | 11997 |
b. Profit earned on job 295 = $4,302.
Working:
Actual cost : | |||
Direct material (A) | 2365 | ||
Direct labor (B) | 4774 | ||
Overheads : | |||
Level 5 staff | 20 | 8 | 160 |
Level 6 staff | 66 | 6 | 396 |
Total Overheads (C) | 556 | ||
Total Actual cost (A+B+C) (D) | 7695 | ||
Billing done (E) | 11997 | ||
Profit earned (E-D) | 4302 |