Question

In: Operations Management

(Based on Alton Bridge Video Clip) Large construction projects, like buildings and bridges, are some of...

(Based on Alton Bridge Video Clip) Large construction projects, like buildings and bridges, are some of the most complex projects to manage. The construction of the bridge from

Alton, Ill. to St. Louis provides an excellent example of a complex project. Describe three challenges the Alton Bridge project had faced and how they were resolved?

Solutions

Expert Solution

One of the three Challenges Alton Bridge project faced was when they was building the towels for the build in phase 2. Due to the wind they had to build the tower on the ground where the crew assembled the towers reinforcing steel, that was custumer fit for the different measurement for the steel bar the towers. they use crones to left the towers in the air. The poured concrete in the higher section of the tower. However the concrete failed the state quality test, the concrete was super lightweight . To resolved this issue they had to shut down the tower and had to remove 215 cubic feet of concrete. The most important things was not to rush to make up time. Due to late fall weather it was every dangerous and cause delay, so they had to finish in the early spring. The 2ndchallenge happen in phase 3 they had a crane tip over and they hit an old sunken barge while excavating. So they had they had to cut a huge steel sqare out of the old sunken barge. To resolve this costly delay they use accurate scheduling( like PERT and CPM) to save a lot of money. The 3rd challenges had in phase 6 when it rained, rain and kept on raining. It the construction site to go under water. Their was barely any work that could be done the bridge until mid September. To resolved this they required major revision and crashing to fix this. Basically shorten normal through the use of additional resources to if the cost benefit the time saved


Related Solutions

The costs (in millions) of 26 construction projects at a large industrial facility are given below....
The costs (in millions) of 26 construction projects at a large industrial facility are given below. 0.707 0.918 1.143 1.240 1.553 2.003 3 .692 4.069 4.324 5.292 7.214 7.642 10.523 13.371 14.577 14.837 15.317 15.320 20.099 21.571 27.973 29.522 30.028 34.100 38.173 51.284 Is there sufficient evidence to conclude that the median cost for construction projects at this facility is under 20 million dollars? (α = 0.05)
You are managing a large construction project that’s been broken down into sub-projects (or phases). Each...
You are managing a large construction project that’s been broken down into sub-projects (or phases). Each of these sub-projects is scheduled to take between three and six months to complete. At the end of each subproject, you plan to go through the closing processes and document lessons learned. Which of the following BEST describes what you must do at the beginning of each sub-project or phase? a. Make sure you don’t involve the team, to avoid introducing too much project...
Describe (in details) 5 factors, based on which contractors would specify their fees in construction projects.
Describe (in details) 5 factors, based on which contractors would specify their fees in construction projects.
I would like to create discount based on the following items on small piza , large...
I would like to create discount based on the following items on small piza , large pizza and drinks as well. for instance for small pizza, if qty of  small pizaa is > 10   give 50% discount if qty of  small pizaa is > 8    give 40% discount if qty of  small pizaa is > 6 givs 30%  discount if qty of  small pizaa is > 4 give 20%  discount else 0% // Program objective: requires user to input the data, program runs through the data,calcualtes...
Give some example like the large organization has greater project failure than a small organization. You...
Give some example like the large organization has greater project failure than a small organization. You can provide some statistics on it (250-300 Words, No handwriting, No Copy Paste)
In recent years, some Asian-based MNCs have taken advantage of the very low interest rates in Europe by borrowing large amount of euro to finance
In recent years, some Asian-based MNCs have taken advantage of the very low interest rates in Europe by borrowing large amount of euro to finance their operations. Write a short essay that explains the advantages and possible disadvantages (if any) due to this type of financing. Show how you do you estimate these borrowings in the short term and long term. How does euro appreciation and depreciation affect the cost of capital of Asian-based MNCs.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT