You are managing a large construction project that’s been broken down into sub-projects (or phases). Each...

You are managing a large construction project that’s been broken down into sub-projects (or phases). Each of these sub-projects is scheduled to take between three and six months to complete. At the end of each subproject, you plan to go through the closing processes and document lessons learned. Which of the following BEST describes what you must do at the beginning of each sub-project or phase? a. Make sure you don’t involve the team, to avoid introducing too much project management overhead b. Develop the preliminary scope statement for the phase c. Use the Earned Value Technique to decide whether or not to finish the project d. Release all resources from the project and contact sellers to renegotiate all contracts

Solutions

Expert Solution

Ans: b. Develop the preliminary scope statement for the phase

When you have a project that’s broken up into sub-projects or phases, it’s important that you perform the Initiating processes at the beginning of the project. Answer B is the one that best describes something that happens during the processes in the Initiating group - developing the preliminary project scope statement


Related Solutions

The manipulation of the LIBOR can be broken down into three phases. What were these and...
The manipulation of the LIBOR can be broken down into three phases. What were these and how did they differ in terms of motivation and moral justification?
This program is broken down into phases for your convenience only. Please turn in only the...
This program is broken down into phases for your convenience only. Please turn in only the final phase. Before turning in your program, please make sure that it does something reasonable if the user enters a negative number the first time. Phase I: Write a program for a theater that will keep track of how many people in each of 5 age categories attended a particular movie. Use the 5 age categories listed below in the sample screen output. The...
Case Scenario Analysis: Managing risks in construction projects has been recognized as a very important management...
Case Scenario Analysis: Managing risks in construction projects has been recognized as a very important management process in order to achieve the project objectives in terms of time, cost, quality, safety and environmental sustainability. A study aims to identify and analyze the risks associated with the development of construction projects from project stakeholder and life cycle perspectives. The study identified following risk factors. 1.Tight project schedule 2.High performance/quality expectations 3.Low management competency of subcontractors 4.Incomplete or inaccurate cost estimate 5.Lack...
Project management process involves many phases. Construction is one of the phases. Which of the following...
Project management process involves many phases. Construction is one of the phases. Which of the following aspects of the construction phase do you consider as most important as well as most challenging/demanding? Why do you think so? Third party coordination Quality Management Safety management? Please select only one option and justify your response.
TtThere are two different projects which you are managing as a project manager, the team members...
TtThere are two different projects which you are managing as a project manager, the team members and stockholders for the project are four and six respectfully, calculate the number of communication channels and provide a diagram illustrating the people and the communication channels for each project.
You are a construction engineer working for a large utility contractor. The project you are working...
You are a construction engineer working for a large utility contractor. The project you are working on is in New York City (Manhattan). You are installing approximately 1,000 L.F. of 48” dia. RCP for storm drains. Invert elevation ranges from 9’ to 14’ below grade. Pay lines for the trench are indicated in the attached specification. Soil characteristics range from SM to SC, based on the Unified Soil Classification. What considerations would you make with regards to a trenching &...
Managing other consultants on a project is one of the key and daunting tasks of construction...
Managing other consultants on a project is one of the key and daunting tasks of construction project managers. The architect on your project is not forthcoming with updated drawings? What steps would you take to avoid this situation? Question related to Construction Management subject!
Identify two projects in which you have been involved recently. 1. Describe each project briefly and...
Identify two projects in which you have been involved recently. 1. Describe each project briefly and suggest criteria that may have been used to identify the start of the termination phase of each project. and 2. Give two examples of activities that were performed poorly during the termination phase of either project, and suggest measures that might have been taken to improve the situation.
once a project is under construction, what level of inspections are required during the various phases...
once a project is under construction, what level of inspections are required during the various phases of construction?
X construction is considering two projects to develop. The estimated net cash flow from each project...
X construction is considering two projects to develop. The estimated net cash flow from each project is as follows: Project X Project Y Year 1 110,000 75,000 Year 2 65,000 150,000 Year 3 100,000 60,000 Year 4 115,000 55,000 Year 5 35,000 60,000 Project requires an investment of $200,000. A rate of 15% has been selected for the NPV analysis. Requires to a) Calculate Payback period, ARR, Net Present Value and Profitability Index b) Which Project is to be recommended...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT