In: Accounting
Gandolph Game Company has established the following standards for the prime costs of one unit of its chief product, dartboards. Standard Cost Standard Quantity Standard Price or Rate Direct material $ 5.00 5.00 kilograms $ 1.00 per kilogram Direct labor 1.00 0.20 hour $ 5.00 per hour Total $ 6.00 During September, Gandolph purchased 195,000 kilograms of direct material at a total cost of $214,500. The total wages for September were $40,404, 75 percent of which were for direct labor. Gandolph manufactured 37,000 dartboards during September, using 177,600 kilograms of the direct material purchased in September and 7,770 direct-labor hours. Required: Compute the following variances for September. Please indicate whether each variance is favorable or unfavorable.