Question

In: Accounting

Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...

Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1

Purchase price of the land $ 1,390,000
Demolition and removal of old building 99,000
Clearing and grading the land before construction 245,000
Various closing costs in connection with acquiring the land 61,000
Architect's fee for the plans for the new building 69,000
Payments to Maxtor for building construction 3,440,000
Equipment purchased 955,000
Freight charges on equipment 51,000
Trees, plants, and other landscaping 64,000
Installation of a sprinkler system for the landscaping 6,900
Cost to build special platforms and install wiring for the equipment 31,000
Cost of trial runs to ensure proper installation of the equipment 8,900
Fire and theft insurance on the factory for the first year of use 43,000

In addition to the above expenditures, Teradene purchased four forklifts from Caterpillar. In payment, Teradene paid $35,000 cash and signed a noninterest-bearing note requiring the payment of $89,000 in one year. An interest rate of 8% properly reflects the time value of money for this type of loan.

Required:
Determine the initial valuation of each of the assets Teradene acquired in the above transactions. (Round your answers to the nearest whole dollars.)

Assets Initial Valuation
Land
Building
Equipment
Land Improvements
Fork Lifts
Prepaid Insurance

Solutions

Expert Solution

ANSWER

Asset Intial Valuations
Land:
Purchase price $1,390,000
Demolition and removal of old building $99,000
Clearing and grading $245,000
Various Closing costs in connection with acquiring of Land $61,000
Total cost of the land $1,795,000
Building:
Architect's fees $69,000
Payment to Maxtor for Building Construction $3,440,000
Total cost of the building $3,509,000
Equipment
Purchase Price $955,000
Freight Charges $51,000
Cost to Build Special platforms and wire installation $31,000
Cost of trial runs to ensure Proper installation $8,900
Total cost of Equipment $1,045,900
Land improvements:
Tree , Plants and other Landscaping $64,000
Installation of Sprinkler system $6,900
Total cost of Land Improvement $70,900
Fork Lifts:
Cash Paid $35,000
Non Interest bearing Note requiring the payment n One year $89,000
Less: Interest component (89,000 *8/108) $6,592.59
Total cost of ForkLift $117,407.41
Prepaid insurance: $43,000

_____________________________________________

If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating.

*****************THANK YOU**************


Related Solutions

Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Purchase price of the land $ 1,280,000 Demolition and removal of old building 88,000 Clearing and grading the land...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Purchase price of the land $ 1,230,000 Demolition and removal of old building 83,000 Clearing and grading the land...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Purchase price of the land $ 1,320,000 Demolition and removal of old building 92,000 Clearing and grading the land...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,000 Architect’s fees (for new building) 11,000 Legal fees for title investigation of land 8,000 Property taxes on land (for period beginning March 1, 2018) 4,200 Construction costs 620,000 Interest on...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2019 2020 Costs incurred during the year $ 290,000 $ 150,000 Estimated additional cost to complete 145,000 — Billings during the year 260,000 265,000 Cash collections during the year 240,000 285,000 Required: Record the preceding transactions in MSK’s books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...
On January 1, 2018, Fulton Corporation purchased land as a factory site for $80,000. Fulton paid...
On January 1, 2018, Fulton Corporation purchased land as a factory site for $80,000. Fulton paid $30,000 and signed a noninterest-bearing note requiring the company to pay the remaining $50,000 on January 1, 2021. An interest rate of 5% properly reflects the time value of money for this type of loan agreement. An old building on the property was demolished, and construction began on a new building that was completed on December 31, 2018. Costs incurred during this period are...
Question 2: On September 25, 2020, ATS Corporation purchased land as a factory site for 600,000...
Question 2: On September 25, 2020, ATS Corporation purchased land as a factory site for 600,000 TL. An old building on the property was demolished and removed and the construction of a new building which was completed on November 24, 2020. Costs incurred during this period are listed below: Demolition of old building 60,000TL Architect’s fees 15,000TL Legal fees for title investigation and purchase contract 8,000TL Construction costs 1,000,000TL (Salvaged materials resulting from demolition were sold for 120,000TL.) Required: How...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31,2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below.                                                                                                                                                                                    2020                                    2021                      2022 Contract costs incurred during the year                            $3,400,000            $2,400,000          $2,900,000 Estimated costs to complete the contract at Dec 31          ...
Sandhill Corp. purchased land with two old buildings on it as a factory site for $454,000....
Sandhill Corp. purchased land with two old buildings on it as a factory site for $454,000. The property tax assessment (that is, assessed value) on this property was $357,000: $255,000 for the land and the rest for the buildings. It took six months to tear down the old buildings and construct the factory. The company paid $62,200 to raze the old buildings and it sold salvaged copper, lumber, and brick for $6,500. Legal fees of $1,860 were paid for title...
Ivanhoe Corp. purchased land with two old buildings on it as a factory site for $454,000....
Ivanhoe Corp. purchased land with two old buildings on it as a factory site for $454,000. The property tax assessment (that is, assessed value) on this property was $356,000: $249,000 for the land and the rest for the buildings. It took six months to tear down the old buildings and construct the factory. The company paid $60,100 to raze the old buildings and sold salvaged copper, lumber, and brick for $6,700. Legal fees of $1,860 were paid for title search...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT