Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1
Purchase price of the land | $ | 1,390,000 | |
Demolition and removal of old building | 99,000 | ||
Clearing and grading the land before construction | 245,000 | ||
Various closing costs in connection with acquiring the land | 61,000 | ||
Architect's fee for the plans for the new building | 69,000 | ||
Payments to Maxtor for building construction | 3,440,000 | ||
Equipment purchased | 955,000 | ||
Freight charges on equipment | 51,000 | ||
Trees, plants, and other landscaping | 64,000 | ||
Installation of a sprinkler system for the landscaping | 6,900 | ||
Cost to build special platforms and install wiring for the equipment | 31,000 | ||
Cost of trial runs to ensure proper installation of the equipment | 8,900 | ||
Fire and theft insurance on the factory for the first year of use | 43,000 | ||
In addition to the above expenditures, Teradene purchased four forklifts from Caterpillar. In payment, Teradene paid $35,000 cash and signed a noninterest-bearing note requiring the payment of $89,000 in one year. An interest rate of 8% properly reflects the time value of money for this type of loan.
Required:
Determine the initial valuation of each of the assets Teradene
acquired in the above transactions. (Round your answers to
the nearest whole dollars.)
Assets | Initial Valuation |
Land | |
Building | |
Equipment | |
Land Improvements | |
Fork Lifts | |
Prepaid Insurance |
ANSWER
Asset | Intial Valuations |
Land: | |
Purchase price | $1,390,000 |
Demolition and removal of old building | $99,000 |
Clearing and grading | $245,000 |
Various Closing costs in connection with acquiring of Land | $61,000 |
Total cost of the land | $1,795,000 |
Building: | |
Architect's fees | $69,000 |
Payment to Maxtor for Building Construction | $3,440,000 |
Total cost of the building | $3,509,000 |
Equipment | |
Purchase Price | $955,000 |
Freight Charges | $51,000 |
Cost to Build Special platforms and wire installation | $31,000 |
Cost of trial runs to ensure Proper installation | $8,900 |
Total cost of Equipment | $1,045,900 |
Land improvements: | |
Tree , Plants and other Landscaping | $64,000 |
Installation of Sprinkler system | $6,900 |
Total cost of Land Improvement | $70,900 |
Fork Lifts: | |
Cash Paid | $35,000 |
Non Interest bearing Note requiring the payment n One year | $89,000 |
Less: Interest component (89,000 *8/108) | $6,592.59 |
Total cost of ForkLift | $117,407.41 |
Prepaid insurance: | $43,000 |
_____________________________________________
If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating.