Question

In: Accounting

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019.

Expenditures on the project were as follows:

January 1, 2018 $ 1,000,000
March 1, 2018 600,000
June 30, 2018 800,000
October 1, 2018 600,000
January 31, 2019 270,000
April 30, 2019 585,000
August 31, 2019 900,000


On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest rate. The loan was outstanding all of 2018 and 2019. The company’s other interest-bearing debt included two long-term notes of $4,000,000 and $6,000,000 with interest rates of 6% and 8%, respectively. Both notes were outstanding during all of 2018 and 2019. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required:
1. Calculate the amount of interest that Mason should capitalize in 2018 and 2019 using the weighted-average method.
2. What is the total cost of the building?
3. Calculate the amount of interest expense that will appear in the 2018 and 2019 income statements.
  

Solutions

Expert Solution

Answer:-

  1. Calculate the amount of interest that Mason should capitalize in 2018 and 2019 using the weighted-average method.

Expenditure of 2018

January 1, 2018$1,000,000x12/12= $1,000,000

March1, 2018$ 600,000x10/12= $500,000

June30, 2018$800,000x6/12= $400,000

October 1, 2018$ 600,000x3/12=$150,000

The Accumulated

Expenditure (before interest)$30,00,000

Average Accumulated expenditures=$2,050,000

Interest capitalized in 2018 =$2,050,000*10%=$205,000

Expenditure of 2019

January1, 2019$3,205,000x9/9=$3,205,000

($3,000,000 + 205,000)

January 31, 2019$270,000x8/9=$240,000

April 30, 2019$585,000x5/9=$325,000

August 31, 2017$ 900,000x1/9=$100,000

The Accumulated

Expenditure (before interest)$4,960,000

Average Accumulated expenditures=$3,870,000

Interest Capitalized

$3,870,000- $3,000,00= $870,000

Interest capitalized in 2019= $271,980

Weighted-average rate of all other debt:

  1. What is the total cost of the building?

Accumulated expenditures 9/30/19

before interest capitalization$4,960,000

2017 interest capitalized $271,980

Total cost of building$5,231,980

  1. Calculate the amount of interest expense that will appear in the 2018 and 2019 income statements.

  $3,000,000x10%                             =$300,000

      $4,000,000x6%                               =$240,000

       $ 6,000,000x8%                             =$480,000

Total interest incurred                          =$1,020,000

Less Interest Capitalized                      =($205,000)

Interest Expenses                                =$815,000

Total interest incurred                          =$1,020,000

Less Interest Capitalized                      =($271,980)

Interest Expenses                                =$748,020


Related Solutions

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,420,000 March 1, 2018 1,140,000 June 30, 2018 1,340,000 October 1, 2018 1,140,000 January 31, 2019 351,000 April 30, 2019 684,000 August 31, 2019 981,000 On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,070,000 March 1, 2018 840,000 June 30, 2018 380,000 October 1, 2018 710,000 January 31, 2019 1,170,000 April 30, 2019 1,485,000 August 31, 2019 2,700,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,300,000 March 1, 2018 720,000 June 30, 2018 340,000 October 1, 2018 640,000 January 31, 2019 450,000 April 30, 2019 765,000 August 31, 2019 1,260,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 660,000 June 30, 2018 520,000 October 1, 2018 620,000 January 31, 2019 360,000 April 30, 2019 675,000 August 31, 2019 1,080,000 On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,940,000 March 1, 2018 1,680,000 June 30, 2018 1,880,000 October 1, 2018 1,680,000 January 31, 2019 432,000 April 30, 2019 765,000 August 31, 2019 1,062,000 On January 1, 2018, the company obtained a $4,800,000 construction loan with a 14% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT