Question

In: Finance

Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0...

Slow Ride Corp. is evaluating a project with the following cash flows:
Year Cash Flow
0 –$13,200              
1 5,900              
2 6,600              
3 6,300              
4 5,200              
5 –5,700              

The company uses a 11 percent discount rate and an 8 percent reinvestment rate on all of its projects. Calculate the MIRR of the project using all three methods using these interest rates.

Required:
(a) MIRR using the discounting approach.
(Click to select)17.31%16.12%15.46%17.82%16.97%

  

(b) MIRR using the reinvestment approach.
(Click to select)11.71%12.95%14.36%12.33%12.58%
(c) MIRR using the combination approach.
(Click to select)12.3%11.46%12.66%13.04%12.06%

Solutions

Expert Solution

a) Discounting Approach
All negative cash flows are discounted back to the present at the required return and added to the initial cost
Thus year 0 modified cash flow=-13200-3382.67
=-16582.67
Year 0 1 2 3 4 5
Cash flow stream -13200.000 5900.000 6600.000 6300.000 5200.000 -5700.000
Discounting factor (Using discount rate) 1.000 1.110 1.232 1.368 1.518 1.685
Discounted cash flows -13200.000 5315.315 5356.708 4606.506 3425.401 -3382.673
Modified cash flow -16582.673 5900.000 6600.000 6300.000 5200.000 0.000
Discounting factor (using MIRR) 1.000 1.170 1.368 1.600 1.872 2.190
Discounted cash flows -16582.673 5044.081 4823.963 3936.685 2777.944 0.000
NPV = Sum of discounted cash flows
NPV Reinvestment rate = 0.00
MIRR is the rate at which NPV = 0
MIRR= 16.97%
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
b Reinvestment Approach
All cash flows except the first are compounded to the last time period and IRR is calculated
Thus year 5 modified cash flow=(8026.88)+(8314.1)+(7348.32)+(5616)+(-5700)
=23605.3
Discount rate 11.000%
Year 0 1 2 3 4 5
Cash flow stream -13200.000 5900.000 6600.000 6300.000 5200.000 -5700.000
Compound factor 1.000 1.360 1.260 1.166 1.080 1.000
Compounded cash flows -13200.000 8026.88 8314.1 7348.32 5616 -5700
Modified cash flow -13200.000 0 0 0 0 23605.300
Discounting factor (using MIRR) 1.000 1.123 1.262 1.417 1.592 1.788
Discounted cash flows -13200.000 0.000 0.000 0.000 0.000 13200.000
NPV = Sum of discounted cash flows
NPV Discount rate = 0.00
MIRR is the rate at which NPV = 0
MIRR= 12.33%
Where
Compounding factor = (1 + reinvestment rate)^(time of last CF-Corresponding period in years)
compounded Cashflow= Cash flow stream*compounding factor
c. Combination approach
All negative cash flows are discounted back to the present and all positive cash flows are compounded out to the end of the project’s life
Thus year 5 modified cash flow=(8026.88)+(8314.1)+(7348.32)+(5616)
=29305.3
Thus year 0 modified cash flow=-13200-3382.67
=-16582.67
Discount rate 11.000%
Year 0 1 2 3 4 5
Cash flow stream -13200.000 5900.000 6600.000 6300.000 5200.000 -5700.000
Discount factor 1.000 1.110 1.232 1.368 1.518 1.685
Compound factor 1.000 1.360 1.260 1.166 1.080 1.000
Discounted cash flows -13200.000 0 0 0 0 -3382.67
Compounded cash flows 0.000 8026.88 8314.1 7348.32 5616 0
Modified cash flow -16582.670 0 0 0 0 29305.300
Discounting factor (using MIRR) 1.000 1.121 1.256 1.407 1.577 1.767
Discounted cash flows -16582.670 0.000 0.000 0.000 0.000 16582.670
NPV = Sum of discounted cash flows
NPV= 0.00
MIRR is the rate at which NPV = 0
MIRR= 12.06%
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Compounding factor = (1 + reinvestment rate)^(time of last CF-Corresponding period in years)
Compounded Cashflow= Cash flow stream*compounding factor

Related Solutions

Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0...
Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$28,400 1 10,600 2 13,300 3 15,200 4 12,300 5 –8,800 The company uses a 8 percent interest rate on all of its projects. Calculate the MIRR of the project using all three methods. Required: (a) MIRR using the discounting approach.(Do not round your intermediate calculations.) (b) MIRR using the reinvestment approach. (Do not round your intermediate calculations.) (c) MIRR using the combination approach....
Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0...
Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$13,400 1 6,100 2 6,800 3 6,500 4 5,400 5 –5,900 The company uses a 11 percent discount rate and an 7 percent reinvestment rate on all of its projects. Calculate the MIRR of the project using all three methods using these interest rates. Required: (a) MIRR using the discounting approach.(Do not round your intermediate calculations.) (b) MIRR using the reinvestment approach.(Do not round...
Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0...
Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$ 29,000 1 11,200 2 13,900 3 15,800 4 12,900 5 – 9,400 The company uses a 10 percent interest rate on all of its projects. Calculate the MIRR of the project using the discounting approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) Calculate the MIRR of the project using the discounting approach method....
Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0...
Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$ 29,200 1 11,400 2 14,100 3 16,000 4 13,100 5 – 9,600 The company uses an interest rate of 9 percent on all of its projects. Calculate the MIRR of the project using the discounting approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))   MIRR %    Calculate the MIRR of the project using...
Slow Ride Corp. is evaluating a project with the following cash flows:    Year Cash Flow...
Slow Ride Corp. is evaluating a project with the following cash flows:    Year Cash Flow 0 –$12,800               1 6,200               2 6,800               3 6,300               4 5,200               5 –4,400                  The company uses a 11 percent discount rate and an 10 percent reinvestment rate on all of its projects. Calculate the MIRR of the project using all three methods using these interest rates.     Required: (a) MIRR using the discounting approach.(Do not round your intermediate...
Slow Ride Corp. is evaluating a project with the following cash flows:    Year Cash Flow...
Slow Ride Corp. is evaluating a project with the following cash flows:    Year Cash Flow 0 –$ 29,000 1 11,200 2 13,900 3 15,800 4 12,900 5 – 9,400    The company uses a 10 percent interest rate on all of its projects.    Calculate the MIRR of the project using the discounting approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))      MIRR %    Calculate the MIRR of...
Slow Ride Corp. is evaluating a project with the following cash flows:    Year Cash Flow...
Slow Ride Corp. is evaluating a project with the following cash flows:    Year Cash Flow 0 –$12,600               1 6,000               2 6,300               3 6,100               4 5,000               5 –4,500                  The company uses a 11 percent discount rate and an 9 percent reinvestment rate on all of its projects. Calculate the MIRR of the project using all three methods using these interest rates.     Required: (a) MIRR using the discounting approach.(Do not round your intermediate...
RAK Corp. is evaluating a project with the following cash flows:    Year Cash Flow 0...
RAK Corp. is evaluating a project with the following cash flows:    Year Cash Flow 0 –$ 28,600 1 10,800 2 13,500 3 15,400 4 12,500 5 – 9,000    The company uses a discount rate of 13 percent and a reinvestment rate of 6 percent on all of its projects.    Calculate the MIRR of the project using the discounting approach. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)...
Mittuch Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$...
Mittuch Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$ 15,400 1 6,500 2 7,700 3 7,300 4 6,100 5 –3,500 The company uses an interest rate of 8 percent on all of its projects. Calculate the MIRR of the project using all three methods. (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) MIRR Discounting approach % Reinvestment approach % Combination approach %
RAK Corp. is evaluating a project with the following cash flows:    Year Cash Flow 0...
RAK Corp. is evaluating a project with the following cash flows:    Year Cash Flow 0 –$ 29,500 1 11,700 2 14,400 3 16,300 4 13,400 5 – 9,900    The company uses a discount rate of 13 percent and a reinvestment rate of 6 percent on all of its projects.    1. Calculate the MIRR of the project using the discounting approach. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g.,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT