In: Operations Management
Weber’s rules for organizations will be followed precisely for all projects.
| True | |
| False | 
A project manager with team members from various units will vie with the functional managers of the team for influence over the team, which is similar to a:
| 
 Functional Organization  | 
|
| 
 Projectized Organization  | 
|
| 
 Matrix Organization  | 
|
| 
 Strategic Organization  | 
A ---------------------- plan is advisable when many disparate stakeholders are involved.
Question 3 options:
| 
 Stakeholder Management Plan  | 
|
| 
 Risk Management Plan  | 
|
| 
 Project Management Plan  | 
|
| 
 Scope Management Plan  | 
Project managers need leadership skills to keep the project and team on track.
| True | |
| False | 
While some schedule extensions are almost inevitable when technical risk is high, they are manageable as
| 
 Contingency Management Risk  | 
|
| 
 Known unknowns Risk  | 
|
| 
 Quality Management Risk  | 
|
| 
 Mitigate or Exploit Risk  | 
1) Weber’s rules for organizations will be followed precisely for all projects.
Answer = TRUE
2) A project manager with team members from various units will vie with the functional managers of the team for influence over the team, which is similar to a:
| 
 Answer = Matrix Organization 
 3) Which plan is advisable when many disparate stakeholders are involved. 
  |