In: Accounting
Present Generator |
New Generator |
|
Purchase cost new |
$16,000 |
$20,000 |
Remaining book value |
$9000 |
|
Overhaul needed now |
$8000 |
|
Annual cash operating cost |
$12,500 |
$7500 |
New economic life |
8 years |
10 years |
Salvage value now |
$4000 |
|
Salvage value in 8 years |
$3000 |
$6000 |
Salvage value in 10 years |
0 |
$1000 |
If the hospital keeps and overhauls its present generator, then the generator will be usable for eight more years. If a new generator is purchased, it will be used for eight years until a new hospital building is opened. The new generator would be diesel-powered resulting in a substantial reduction in annual operating costs as shown above.
The hospital computes depreciation on a straight-line basis. All purchases are evaluated using a 16% discount rate.
Required:
Determine the net present value for each option.
What option would you advise be selected and why?
Answer-
NPV(net present value ) is the difference between the amount of cash outflow and cash inflow over a particularized period.It uses interest/discount factor while considreing calcutiong profitablity of a capital project.
Present Generator | ||||
End of year | N.C.F. | Dis Rate @0.16 | Present Value | |
1 | 2 | 3 | 4=2*3 | |
1 | 12,500 | 0.862 | 10,776 | |
2 | 12,500 | 0.743 | 9,290 | |
3 | 12,500 | 0.641 | 8,008 | |
4 | 12,500 | 0.552 | 6,904 | |
5 | 12,500 | 0.476 | 5,951 | |
6 | 12,500 | 0.410 | 5,131 | |
7 | 12,500 | 0.354 | 4,423 | |
8 | 9,500(salvage value -3,000) | 0.305 | 2,898 | |
9 | - | |||
10 | - | |||
Total Cash Outflow | 53,380 | |||
Add: Overhaul | 8,000 | |||
Working Capital | - | |||
8,000 | 8,000 | |||
NPV | $ 61,380 |
New Generator | |||||
End of year | N.C.F. | Dis Rate @0.16 | Present Value | ||
1 | 2 | 3 | 4=2*3 | ||
1 | 7,500 | 0.862 | 6,466 | ||
2 | 7,500 | 0.743 | 5,574 | ||
3 | 7,500 | 0.641 | 4,805 | ||
4 | 7,500 | 0.552 | 4,142 | ||
5 | 7,500 | 0.476 | 3,571 | ||
6 | 7,500 | 0.410 | 3,078 | ||
7 | 7,500 | 0.354 | 2,654 | ||
8 | 1,500 | 0.305 | 458 | Including 6,000 of salvage value | |
9 | - | ||||
10 | - | ||||
Total Cash Outflow | 30,747 | ||||
Add: Investment | 20,000 | ||||
Less Salvage value of old machine | (4,000) | ||||
16,000 | 16,000 | ||||
NPV | $ 46,747 |
Investment | NPV(cost) | |
Present Generator | 8,000.00 | 61,380 |
New Generator | 20,000.00 | 46,747 |
New generator option is better than present generator as it will result in less cost as per calculation showed above.
*There is no revenue mention in question hence decision has been taken on the cost basis.