In: Operations Management
Wormwood, Ltd., produces a variety of furniture products. The planning committee wants to pre- pare an aggregate plan for the next six months using the following information:
Month | ||||||
---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | |
Demand | 160 | 150 | 160 | 180 | 170 | 140 |
Capacity: | ||||||
Regular | 150 | 150 | 150 | 150 | 160 | 160 |
Overtime | 10 | 10 | 0 | 10 | 10 | 10 |
Cost per unit | |
Regular time | $50 |
Overtime | $75 |
Subcontract | $80 |
Inventory holding, per month | 4 |
Subcontracting can handle a maximum of 10 units per month. Beginning inventory is zero. Develop a plan that minimizes total cost. No back orders are allowed. Regular capacity = Regular production.
1. Because total capacity of regular and overtime is greater than the forecast, we don't need to use the subcontractor in this problem. True or false?
2. To satisfy the requirement, not all over time will be used. True or false?
3. To minimize the total cost, we need to hold inventory by the end of which of following month(s)? Select all that apply. 1, 2, 3, 4, 5, and/or 6.
4. To minimize the total cost, we need to use subcontractor in which of following month(s)? Select all that apply. 1, 2, 3, 4, 5, and/or 6.
5. What is the minimized total cost for the plan?
Month | 1 | 2 | 3 | 4 | 5 | 6 |
Demand | 160 | 150 | 160 | 180 | 170 | 140 |
Capacity: | ||||||
Regular | 150 | 150 | 150 | 150 | 160 | 160 |
Overtime | 10 | 10 | 0 | 10 | 10 | 10 |
Production: | ||||||
Regular | 150 | 150 | 150 | 150 | 160 | 140 |
Overtime | 10 | 10 | 0 | 10 | 10 | 0 |
Subcontract | 0 | 0 | 10 | 10 | 0 | 0 |
Inventory | 0 | 10 | 10 | 0 | 0 | 0 |
Cost: | ||||||
Regular | 7500 | 7500 | 7500 | 7500 | 8000 | 7000 |
Overtime | 750 | 750 | 0 | 750 | 750 | 0 |
Subcontract | 0 | 0 | 800 | 800 | 0 | 0 |
Inventory | 0 | 40 | 40 | 0 | 0 | 0 |
Total Cost | 49680 | (sum of all the costs given above) |
In month 1: regular and overtime cover the demand
In month 2: Regular alone covers the demand, but overtime is used to cover the demand for next month and minimize cost. Hence inventory of 10 is carried forward.
In month 3: demand is covered using regular and inventory, subcontract is done to cover the demand of next month, hence inventory carried forward is 10
In month 4: Demand is covered using all regular, overtime, subcontract and inventory
In month 5: regular and overtime cover the demand
In month 6: Only regular is used to cover demand
The costs are calculated in above table:
regular = production*50
overtime = production*75
subcontract = units*80
inventory = units*4
1. False, we do need subcontract
2. True, overtime not used in month 6.
3. To minimize the total cost, we need to hold inventory by the end of month 2 and 3
4. To minimize the total cost, we need to use subcontractor in month 3 &4
5. total cost = 49680