In: Accounting
Ennerdale Ltd has been asked to quote a price for a one-off contract. The company's management accountant has asked for your advice on the relevant costs for the contract. The following information is available:
Materials
The contract requires 3,000 kg of material K, which is a material used regularly by the company in other production. The company has 2,000 kg of material K currently in stock which has been purchased last month for a total cost of $19,600. Since then the price per kilogram for material K has increased by 5%.
The contract also requires 200 kg of material L. There are 250 kg of material L in stock which are not required for normal production. This material originally cost a total of $3,125. If not used on this contract, the stock of material L would be sold for $11 per kg.
Labour
The contract requires 800 hours of skilled labour. Skilled labour is paid $9.50 per hour. There is a shortage of skilled labour and all the available skilled labour is fully employed in the company in the manufacture of product P. The following information relates to product P:
$ per unit | $ per unit | |
Selling price | 100 | |
Less | ||
Skilled labour | 38 | |
Other variable costs | 22 | |
(60) | ||
40 |
Required:
(a) Prepare calculations showing the total relevant costs for making a decision about the contract in respect of the following cost elements:
(i) materials K and L; and
(ii) Skilled labous
(b) Explain how you would decide which over head costs would be relevant in the financial appraisal of the contract.
Relevant costs of Material K
Required is 3000 kgs. Already
available is 2000kgs.
Hence, the cost of 2000 kgs, which is $19600 is irrelevant.
Cost per kg was 19600/2000 = $9.8 per kg has now gone up by 5%.
New cost per kg = 9.8 x 1.05 =
$10.29
Cost of remaining 1000 kgs= 1000 kgs x $10.29 = $10,290
Relevant cost of Material K = $10,290
Relevant costs of Material L
Required 200 kgs, already available 250 kgs. Hence not required to purchase.
However if 200 kgs were sold instead
of being used, it would earn company $11 per kgs.
Hence, opportunity cost considered for decision making will be $11
x 200 Kgs = $2200
Relevant cost of Material L = $2,200
Relevant cost of Labour
800 hours required.
If 800 hours used, company will not be able to produce product P. Hence, its contribution will be lost. One unit of P takes 4 hours of skilled labour ($38/$9.5 per hour). Hence, in 800 hours, 200 units of P would have been produced. Total contribution lost would be 200 units x $40 = $8000
Labour cost = 800 hours x $9.5 per hour = $7,600
Hence, total relevant cost for labor = 7600 + 8000 = $15,600
In deciding whether overhead is relevant in the financial appraisal of a contract, we see if that particular overhead is avoidable in nature or not. If its avoidable, it is relevant, other wise, it is irrelevant or sunk cost.